Forwards IE Insp Repts 50-443/80-06 & 50-444/80-06 on 800519-0627 & Notice of Violation
ML19345C639
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 08/01/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Tallman W
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
Shared Package
ML19345C640 List:
References
NUDOCS 8012080045
Download: ML19345C639 (2)


See also: IR 05000443/1980006

Text

3

.

.

f

0

UNITED STATES

4

j,

1

NUCLEAR REGULATORY COMMisslON

_

p

yo

r

7

,j

REGION I

[

(l, g

L.

- e

saiPanx AvsNur

75 0

,

9

xiNo oF PRUS$1 A, PENNSYLVANIA 19406

~

.

MB011380

Docket Nos. 50-443

. A

g

y

g

-

50-444

p

y

-

,

u,

4

-

Public Service Company of New Hampshire

ATTN: Mr. W. C. Tallman

Chairman and Chief Executive Officer

1000 Elm Street

Manchester, New Hampshire 03105

Gentlemen:

Subject: Combined Inspection 50-443/80-06 and 50-444/80-06

This refers to the routine inspection conducted by Mr. A. Cerne of this office

on May 19-June 27, 1980 at the Seabrook Station, Units 1 and 2, Seabrook, New

Hampshire of activities authorized by NRC License Nos. CPPR-135 and CPPR-136 and

to the discussions of our findings held by Mr. Cerne with Messrs. Herrin, Singleton,

and others of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with NRC requirements, as set forth in the

Notice of Violation, enclosed herewith as Appendix A.

This item of noncompliance

has been categorized into the levels as described in our correspondence to you

dated December 31, 1974. This notice is sent to you pursuant to the provisions

of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of

Federal Regulations. Although Section 2.201 requires you to submit to this

office, within 30 days of ycur receipt of this notice, a written statement of

explanation, we note that this item of noncompliance was corrected prior to the

completion of our 17spection, and therefore, no response with respect to this

matter is required.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any infor-

mation that you (or your contractor) believe to be proprietary, it is necessary

that you make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must be accompanied

by an affidavit executed by the owner of the information, which identifies the

8012080 d6

.

.

.

Public Service Company of New Hampshire

2

document or part sought to be withheld, and which contains a statement of reasor.s

which addresses with specificity the items which will be considered by the

Commission as listed in subparagraph (b) (4) of Section 2.790.

The information

sought to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

N/ M

Robert T. Carlson,

hief.

Reactor Construction and Engineering

Support-Branch

Enclosures:

1.

Appendix A. Notice of Violation

2.

Combined Office of Inspection and Enforcement Inspection

Report Number 50-443/80-06 ana 50-444/80-06

cc w/ encl:

John DeVincentis, Project Manager