Monthly Operating Rept for Dec 1980
ML19341A018
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/12/1981
From: Miller L
Public Service Enterprise Group
To:
Shared Package
ML18085A535 List:
References
NUDOCS 8101210458
Download: ML19341A018 (8)


Text

.,m V

AVERAGE DAILY UNIT PChTR LEEL DOCET NO. 50-311 UNIT salem No. 2 DATE January 12, 1981 C0f@LETED BY L.K. Miller TELEPHONE 609-365-7000 Ext. 507 K)NTi December 1980 DAY AVERAGE DAILY POWER LEEL DAY AVERAGE DAILY P0hTR LEVEL (We-NET) -

(MiE-NET) 1 0

17 0

2 0

18 0

3 0

19 0

4 0

20 0

5 0

21 0

6 0

22 0

0 23 0

7 0

0 8

24 0

0 9

25 0

0 10 26 0

0 11 27 0

0 12 28 0

0 13 29 3

0 0

14 30 0

0 15 31 0

16 i

i 8?i-7, g 9 IO /t1 OYfI 2

cantATING ta:A REPar Docer to.:

50-311 tan :

January 12, 1981 L.K. Miller m gy, 2:stom: 609-365-7000 Fv A 507 cratAT:NG m2US Salem No. 2 not,,,

1.

mit Neum:

2.

amp:nting Period:

December 1980 3.

Licznsed Omnimi Pcur Oeft):

3411 4.

Nanuplate Rating (Gross lede):

1162 5.

Design Electrical Rating (Net lede):

1115 6.

M== Dupendable Capacity 1 Gross fede): 1149 7.

Maximan Dupendable Capacity (Not Mie):

1104 8.

If C=vj== Occur in Capacity Ratings (Itmas marber 3 2: rough 7) Since Last amport, Give amason:

9.

Power Invel Ib 14ich anstricted, If Any (Net 19de):

5% Thermal

10. annacms For Restrict.icns, If Any Pending Full Power Operating Liscense Siis Mcnth Year to Data camalative 744 6169 6169
11. Ihzrs In asporting Period
12. mareer of thzrs anactor was Critical 0

268.2 268.2

13. anactor asserve mW axrs 0

0 0

14. Hours Generator On-Line 0

0 0

15. Unit Baserve Shutrban sours 0

0 0

16. Gross Omrmal Energy Generated 0+is) 0 0

0

17. Cress Electrical Ibergy Generatedoes) 0 0

0

18. Net Electrical Energy Generatad0eds) 0 0

0 i

19. Unit Service Factor 0

0 0

0 0

0

20. Unit Availmhility Factor
21. mit t'=t*'4ty Factor (Using ICC Net) 0 0

0

22. Unit Capacity ractor (Using DDL Net) 0 0

0

23. Unit Forced Outage Rate 0

0 0

24. Shutzbes ScM1=d Over Next 6 femths (Type, Date, and Duraticm of Each):

l

25. If Shut Dtwn At Dd of asport Period, Estimatad Date of StartW:
26. Ohits In Test Status (Prior to Cczmercial Operation):

Forecast Achiewd INr m L CR m CALITr 6/30/80 8/2/80 9/01/80 N/A In m AL ErmcTRICrry

&-1-7.PJ N/A N/A Pg. 3 of 9 CCMERCIAL QPERATICN

mtT siamnee we twat Romermi 50-311 noegEr no,,

Rnwr MEs December 1980 unit'NAME: Salem #2 DATE: January 12, 1981 L.K. Miller i

COMPLETED BY:

TELEPilONE: 609-365-7000 Ext. 507, remno 0F mPATim SIRTITit 9 LIO2CE SYSI1M QMUNDrr CRUSE Me Q)RRBCTIVE g

W.

DAR TYPE (if]URS)

RFNN 00NN EVENT (INE4 Q11ES ACTION 10 P"JCIUR RF3 W r I PREVENT RRCUIUE2r2 1

N/A l

s I

1 2

3 4

5 F: r rmd Reamma pethnd Exhibit C - Instructions slxhibit 1-Sc.aus S Sdieduled A-Rp11[ ment Failure (Explain) 1-Manual for Pr p ration of Data Smroe B-Phintenance or Test Dstry Shrets for Licenssee 2-Manual Scram.

Event Ikport(Ik3t) File C-Refueling D-legulatory Restriction 3-Automatic Scram.

(NURfG-0161)

E-Oterator Training & Lloense rxunination 4-Continuation of r-Artninistrative G-operational Error (Explain)

Previous Outage ti-other (r.glain) 5-Load Reduction 9-Other Page 4 Of 9 8-1-7.R1

m

.m SALEM GENE.

ING STATION SAFETY RELATED EQUIPMENT WORK ORDER LOG UNIT 3 WORK ORDER NUMBER DEPT EQUIPMENT IDENTIFICATION EXPLANATION OF WORK PERTORMED

~~311997 MD Vent Duct Description Of Problem - Seal hole around vent duct from Unit 2 A/C Room to Unit 2 Control Room.

Corrective Action Taken - Filled hole with cera blanket, then filled remaining hole with simkit.

912334 MD Flux Mapping Description Of Problem - Reinstall flux thimbles into reactor.

Corrective Action Taken - Reinstalled flux thimbles.

929516 MD Valve, 23MS167 Description of Problem - Valve will not indicate open.

Corrective Action Taken - Repacked valve.

934081 MD valve, 22Rh19 Description Of Problem - Closing coil does not close.,

Corrective Action Taken - Replaced 3 relays.

934082 MD Valve, 21SJ40 Description Of Problem - 230V ACB trips during valve operation.

Corrective Action Taken - Readjusted breaker at lA east vital 230V control center.

934155 MD 2F 4KV Bus Description Of Problem - Underfrequency alarm is on.

Corrective Action Taken - Repaired alarm.

937123 MD 22 Fan Coil Unit Description Of Problem - Outboard fan bearing temperature 200*F tripped unit.

Corrective Action Taken - Put new grease in both bearing housings.

939261 MD 2 Reactor Sump Pump Description of Problem - Pump failed to shutdown.

Corrective Action Taken - Cleaned contacts.

944715 MD 2A Emergency Diesel Description Of Problem - Failure alarm is annunciated.

Corrective Action Taken - Rewired switch TD7332.

I 945350 MD 25 Service Water Screen Description Of Problem - Reduction gear needs a plug.

Corrective Action Taken - Installed plug.

Page 5 of 9

q m

^ '

WORK ORDER NUMBER DEPT EQUIPMENT IDENTIFICATION EXPLANATION OF WORK PERFORMED 945388 MD 25 Service Water Strainer Description Of Problem - Flush and grease.

Corrective Action Taken - Flushed and added oil.

945400 MD Pressurizer Relief Tank Description Of Problem - Repair ruptured disc.

Corrective Action Taken - Installed new disc and gasket.

945964 MD 2C Safeguard Emergency Description of Problem - Loss of voltage alarm, local trouble alarm will not Cabinet clear.

Corrective Action Taken - Replaced card in Slot 44.

946097 MD Transient Data Recorder Description of Problem - Auto reverse micro switch inoperable.

Corrective Action Taken - Replaced stop screw.

911698 PD Air Particular Detector Description of Problem - Flow reading below spec's..

Corrective Action Taken - Replaced filter paper.

928455 PD Instru, 2R41A Description Of Problem - Investigate comm I errors.

Corrective Action Taken - Replaced 866I module with new one.

928464 PD Instru, NR46 Description Of Problem - Pen does not respond.

Corrective Action Taken - Overhauled recorder.

928465 PD Instru, 2R41B Description Of Problem - Investigate comm I errors.

Corrective Action Taken - Repaired 866I module.

928481 PD Instru, 2R12B Description Of Problem - Analyzer module upper window is.629 volts.

Corrective Action Taken - Adjusted upper and lower windows.

928482 PD Instru, 2N31-35, 2N32-36 Description Of Problum - Perform electrical test for comparison with

'Jnit No. I valves.

Corrective Action Taken - Rebuilt connectors at SR pre-amp.

928562 PD Instru, 2R12B Description Of Problem - No scan to compute.

Corrective Action Taken - Reprogrammed and changed module.

Page 6 of 9

q p

n o

WORK ORDER N UMQER DEPT EQUIPMENT IDENTIFICATION EXPLANATION OF WORK PERFORMED 932637 PD Instru, 2RllA Description Of Problem - Investigate comm i errors to computer.

Corrective Action Taken - Replaced buffer and opto-couplers on receiver portion of comm loop.

923653 PD Instru, 2R12B Description Of Problem - Analyzer module upper window out of spec.

Corrective Action Taken - Reset upper and lower window.

932658 PD Instru, 2PT536 Description Of Problem - 2BS536A resetting out of spec.

t i

Corrective Action Taken - Replaced defective comparator.

933972 PD Valve, 22AF21 Description Of Problem - Exceeds stroke time.

[

t Corrective Action Taken - Stroked valve and calibrated.

I 934074 PD Valve, 2NT35 Description Of Problem - Console valve position in'ica, tion erratic.

l d

Corrective Action Taken - Replaced meter movement.

)

934075 PD 21 Accumulator Pressure Description of Problem - Failed center scale.

Corrective Action Taken - Calibrated indicator, cleaned contacts.

034080 PD Valve, 23AFil Description Of Problem - Does not make up open limit switch.

Corrective Action Taken - Adjusted limit switch.

934091 PD valve, 21Arll Description Of Problem - Exceeds required stroke time.

Corrective Action Taken - Stroked valve and adjusted positioner.

934092 PD valve, 22AFil Description Of Problem - Exceeds stroke time.

Corrective Action Taken - Stroked valve and adjusted positioner.

934147 PD Audio Count Rate Drawer Description Of Problem - Remove from Unit 2 and install in Unit 1.

Corrective Action Taken - Moved audio count rate channel from Unit 2 to Unit 1.

934271 PD Instru, N41 Power Range Description Of Problem - Drawer found out of spec.

Drawer Corrective Action Taken - Adjusted NM301, NM302, NM306, NM307. Adjusted ion current gain for B detector.

Page 7 of 9

,m WORK ORDER NUMBER DEPT EQUIPMENT IDENTIFICATION EXPLANATION OF WORK PERFORMED 934277 PD Instru, 2 FT 51".)

Description Of Problem - Loop found out of calibration.

Corrective Action Taken - Calibrated output.

~

934350 PD Instru, RMS System Description Of Problem - Reboot computer and reset failed channels.

Corrective Action Taken - Reinitialized computer.

937078 PD Boron Inj. Tank Flow Description Of Problem - Flow meter is stuck at 5 gpm.

Corrective Action Taken - Valve was red tagged, flow went to normal.

t 937166 PD Valve, 2Cvl72 Description Of Problem - Doesn't make either limit switch.

Corrective Action Taken - Repositioned actuator.

937167 PD valve, 21MS18 Description Of Problem - Doesn't have any open indication.

I l

Corrective Action Taken - Tightened loose bolts around' actuator, i

987192 PD Valve, 2SJ18 Description Of Problem - Repair mir supply bleedoff.

Corrective Action Taken - Repaired bleedoff petcock.

$44866 PD Instru, 2R41A Description Of Problem - Filter tear alarm.

Corrective Action Taken - Changed paper tape.

E Page 8 of 9

1 _ - _ ^...._ :.:._ _

REFUELING INFORMATION I

e DOCKET NO.:

50-311 UNIT:

Salem #2 j

DATE:

January 12, 1981 COMPLETED BY: L.K. Miller TELEPHONE: 600-365-7000 Ext. 507 MONTH:

December 1980 1.

Refueling information has changed from last month:

YES NO X

2.

Scheduled date of next refueling:

March 20, 1982 3.

Scheduled date for restart following refueling:

June 13, 1982 4.

A.

Will Technical Specification changes or other license amendments be required?

YES NO NOT DETERMINED TO-DATE December 1980 B.

Has the reload fuel design been reviewed by the Station Operating X

Review Committee?

YES NO If no, when is it scheduled?

March 1982 5.

Scheduled date (s) for submitting proposed licensing action:

March 1982 (If Required) 6.

Important licensing considerations associated with refueling:

None 7.

Number of Fuel Assemblies:

A.

In-Core 193 l

B.

In Spent Fuel Storage 0

0.

Present licensed spent fuel storage capacity:

1,170 Future spent fuel storage capacity:

1,170 9.

Date of last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:

Discharge March 1999 9 Of 9 Page 8-1-7.R4