ML19340F053
| ML19340F053 | |
| Person / Time | |
|---|---|
| Site: | Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png |
| Issue date: | 09/24/1980 |
| From: | Brunner E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Counsil W CONNECTICUT YANKEE ATOMIC POWER CO. |
| Shared Package | |
| ML19340F048 | List: |
| References | |
| NUDOCS 8101160591 | |
| Download: ML19340F053 (2) | |
See also: IR 05000213/1980015
Text
'
4
\\#
%
.
.,
t
UNITED STATES
g
&
NUCLEAR REGULATORY COMMISslON
.,f
REGION I
e '.
g
631 PARK AVENUE
S
of
KING OF PRUSSI A. PENNSYLVANI A 19404
%, .....f
Docket No. 50-213
& 2 4 1980
Connecticut Yankee Atomic Power Company
ATTN: Mr. W. G. Counsil
Vice President - Nuclear
Engineering and Operations
P. O. Box 270
Hartford, Connecticut 06101
Gentlemen:
Subject:
Inspection 50-213/80-15
This refers to the routine inspection conducted by Mr. J. Wiggins of this office
on August 25-28, 1980, at the Haddam Neck Plant, Haddam, Connecticut, of activ-
ities authorized by NRC License No. DPR-61 and to the discussions of our findings
held by Mr. Wiggins with Mr. J. Ferguson of your staff at the conclusion of the
inspection, and to a subsequent telephone discussion between Mr. Wiggins and Mr.
Ferguson on September 3, 1980.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter. Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
.
Based on the results of this inspection, it appears that certain of your activi-
l
ties were not conducted in full compliance with NRC requirements,.as set forth
in the Notice of Violation, enclosed herewith as Appendix A.
These items of
noncompliance have been categorized into the levels as described in our corres-
,
pondence to you dated December 31,1974.
This notice is sent to you pursuant to
l
the provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations.
Section 2.201 requires you to submit to this
office, within twenty (20) days of your receipt of this notice,'a written state-
ment or explanation in reply including:(2) corrective steps which will be taken
(1) corrective steps which have been
taken by you and the results achieved;
l
to avoid further items of noncompliance; and (3) the date when full compliance
will be achieved. Additionally, include in your written reply, a similar response
'
addressing the licensee identified item discussed in Paragraph 3 of the inspection
report.
l
81011605f(
__,
.
._
-
,
.
. . .
.
.
..
Connecticut Yanku Atomic Power Company
2
ggP 2 41980
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Feleral Regulations, a copy of this letter and the enclosures will
be placed in the NRC's Public Document Room.
If this report contains any infor-
mation that you (or your contractor) believe to be proprietary, it is necessary
that you make a written application within 20 days to this office to withhold
such information from public disclosure. Any such application must be acccmpanied
by an affidavit executed by the owner of the infonnation, which identifies the
document or part sought to be withheld, and which contains a statement of reasons
which addresses with specificity the items which will be considered by the
Comission as listed in subparagraph (b) (4) of Section 2.790.
The infonnation
sought to be withheld shall be incorporated as far as possible into a separate
part of the affidavit.
If we do not hear from you in this regard within the
specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
El
. Brunner, Chief
Re tor Operations and Nuclear
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Office of Inspection and Enforcement Inspection Report Number
'
50-213/80-15
cc w/encls:
R. Graves, Plant Superintendent
l
D. G. Diedrick, Manager of Quality Assurance
J. R. Himelwright, Licensing Safeguards Engineer
l
l