ML19340A600
| ML19340A600 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 05/25/1973 |
| From: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Brian Lee COMMONWEALTH EDISON CO. |
| Shared Package | |
| ML19340A601 | List: |
| References | |
| NUDOCS 8008280653 | |
| Download: ML19340A600 (5) | |
See also: IR 05000010/1973002
Text
_ _
_
.
.
.
.
.
g
'
g
k
g QL J
,,
-
U
.
Zvd
p*GY c
g
UNITED STATES
T ])
e
l
ATOMIC ENERGY COMMISSION
i
T
DIRECTORATE OF REGULATORY OPERATIONS
REGION Pil
Ms o' "
799 ROOSEVELT ROAD
mg
GLEN ELLYN. ILLINOIS 60137
(312) 85s-2660
May 25, 1973
Commonwealth Edison Company
Docket No. 50-10
ATTN: Mr. Byron Lee, Jr.
Docket No. 50-249
Vice President
P. O. Box 767
Chicago, Illinois
60690
Contimmen:
This refers to the inspection conducted by Massrs. Maura and Brown of this
office on April 17, 19, 20, and 23-25. 1973, of activities at Dresden Units 1
'
and 3 authorized by AEC Operating Licenses No. DPR-2 and No. DPR-25, and to
tha discussion of our findings held by Mr. Maura with Messrs. Worden, Morris,
and Roberts of your staff at the conclusion of the inspection on April 25, 1973.
-
Areas mumined during this inspection included Unit 3 refueling operations
and the results of fuel sipping and reconstitution; work performed in the
Unit 3 torus during this outage; performance and surveillance testing of
Unit 1 125 volt batteries, emergency diesel generator, control rod drives,
and reactor coolant system; and Unit 1 abnormal occurrences since November
1972. Within these areas, the inspection consisted of selective examinations
of procedures and representative records, interviews with plant personnel,
and observations by the inspectors.
In addition to the above matters, the inspectors e= =ined the corrective actions
described in your letters of November 21, 1972, and February 7, 1973, which
were in reply to out letters of October 19, 1972, and January 18, 1973,
respectively. It was noted that the corrective action described in your
letter of February 7, 1973, with regard to the reporting of abnormal occurrences
in accordance with paragraph J.5 of the Technical specifications, was not
implemented during the week of March 5-11, 1973. This matter is referenced
in iten B.2 of the enclosure. We also noted that you have completed the
design review of Unit 1 primary steam drum safety valves, as identified in
our letter of May 15, 1972, and that the highest calculated stress level is
within tha alloweble limit. We have no further question on these items at
this time.
During this inspection, it was found that certain of your activities associated
with Unit 1 appear to be in noncompliance with AEC requirements. The items
and references to the pertinent requirements are listed in the enclosure to
this letter.
.8008280 [63
-
._.
.
,
,
.'
'
-
~
$
- 2
.
.
Commonwealth Edison Company
-2-
May 25, 1973
Thia letter is a notice of violation sent to you persuant to the provisions
of Section 2.201 of the AEC's " Rules of Practice," Part 2, Title 10, code of
Pederal Regulations. Section 2.201 requires you to subctit to this office,
within twenty (20) days of your receipt of this notice, a written statement
or explanation in reply including:
(1) corrective steps which have been
taken by you, and the results achieved; (2) corrective steps which will be
taken to avoid further violations; and (3) the date when full compliance
will be achieved. Such a statesent or explanation should be provided for
each of the items listed in the enclosure. With respect to item C.2 of our
enclosure, we have examined your corrective actions relative to procedure
modifications and have no further questions at this time. However, your
response to this item should include your actions with respect to how this
and similar evente are being incorporated into your retraining program so
that the number of operator errors are minlaimed.
It is our understanding from discussions with your site management that you
will develop the necessary emergency procedures to ensure safe and efficient
plant shutdown in the event that:
(1) the Unit 1125 volt battery chargers
are lost from service, and (2) all Unit 1125 volt de power is lost. We
will examine these matters further during a future inspection.
,
Should you have any questions concerning this inspection, we will be glad
to discuss them with you.
Sincerely yours,
Boyce H. Crier
Regional Director
Enclosure
Description of Noncompliance Items
cc:
W. P. Worden
Dresden Station Superintendent, w/ enc 1
bec: R0 Chief, FS&EB
RO:HQ (4)
Licensing (4)
DR Central Files
Regions I & II
Local PDR
DTIE
. .
. -
-
.
. -
-
-
_
_
.- - -
-
-
.._ _
- -.-- = - --
- . - - - - - - -
.
.
-
,
.
I
j
/
.
,
.
I
ENCLOSURE
Commonwealth Edison Company
Dockats No. 50-10 and No. 50-249
Certain activities under your licenses appear-to be in noncompliance with
AEC regulatory requirements as listed below:
A.
Deviations from Unit 1 Technical Specifications surveillance testing
requirements were as follows:
1.
Paragraph B.16.f(1) requires that measurements of the voltage and
specific gravity of the pilot cell, the temperature of the adjacent
cells and the overall battery voltage shall be made weekly.
Contrary to the above, the voltage of the pilot cell and the
temperature of the adjacent cells were not measured during the
weeks of January 1-7, 1973, and January 15-21, 1973. Also,
the specific gravity and voltage of the pilot cell, the tempera-
ture of the adjacent cells, and the overall battery voltage was
not measured during the week of February 19-25, 1973.
~
2.
Paragraph B.16.3(1) requires that the diesel generator be manually
started and loaded once each month to demonstrate operational
readiness. The test is to last long enough for the diesel engine
and the generator to reach equilibrium temperature at full load.
Contrary to the s'aove, documentation to show that the generator
was started and loaded to full load output and maintained in that
condition until the engine and generator reached equilibrium
temperature during the month of December 1972 could not be
located by the licensee.
B.
Deviations from Unit 1 Technical Specifications reporting requirements
were as follows:
1.
Paragraph J.3.a requires that all abnormal occurrences shall be
'
promptly reported to the Manager of Production or his delegated
alternate and shall be promptly reviewed by the SRB.
Contrary to the above, the abnormal occurrence concerning the
j
bypassing of in-core monitoring string 113 was not reported to
'
the Manager of Production or the Superintendent of Production,
4
'
Division A, until approximately 63 hours7.291667e-4 days <br />0.0175 hours <br />1.041667e-4 weeks <br />2.39715e-5 months <br /> after the event had
taken place and was not reviewed by the SRB until approximately
nine days af ter the event had taken place.
. . .
-,
-
. .--
-.
-
=.
.-_
.
_
_
. _ . _
. _ - _ _
-
--
-
.
_
.
.
.
'
'
Paragraphe J.5.a and J.5.b require that abnormal occurrences be
2.
f
reported to the AEC.
Contrary to the absve, operation during the week of March 5-11,
-
1973, with the emergency condenser shell-side water temperature
in excess of its limit of 100'F was not reported to the AEC.
4
C.
Deviations from Unit 1 Technical Specifications operating requirements
were as follows:
'
1.
Paragraph J.2.a(9) requires that detailed written procedures,
includ:"ng applicable checkoff tests and instructions shall be
prepared and approved to assure the safe shutdown of the plant
in the event of a flood designated as a Probable Maximum Flood.
Contrary to the above, the licensee has failed to prepare and
approve such a procedere although this requirement has been in
effect for over 10 months.
2.
Paragraph B.9.a requires that an in-core monitoring system be
provided capable of automatic scram at not more than 125 percent
of rated local power whenever the reactor is operating at power
levels greater than 350 Mwt. The scram is to be actuated by
coincidence of signals from two or more monitors, provided that
the arrangement does not have the effect of leaving unmonitored
a core region exceeding any vertical cylindrical core volume
-
four feet in diameter within the central 8.5-foot diameter
vertical cylindrical core volume.
Contrary to the above, on April 8-9, 1973, with the reactor at
407 Mwt, the licensee bypassed the scram capabilities of in-core
monitor string 113, leaving two four-foot diameter vertical
cylindrical core volumes without the required scram capability
foi
a, period of approximately 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.
.
- 2 --
i
i
l
.
. _ _ _ _ -
.
.
--
_ _ . --_
.
.
- . . _ ,
,
.
-
__
~
.;.
..:
.
..
,
-
.
,
.
<
f
g
UNITED STATES
'.y
' .
.
f.
ATOMIC ENERGY COMMISSION
.
DIVISION OF COMPl LANCE
f
, ,
RE:GION lit
799 ROOSEVELT ROAO
,
,
arts ,
GLEN ELLYN, ILLINOls 60137
012) ess-zaso
050-010/73-02
A.
RO Inspection Report No.
050-249/73-03
Transmittal Date
May 31, 1973
Distribution:
Distribution:
RO Chief, FS&EB
R0 Chie f, FS&EB
RO:HQ (5)
RO:HQ (4)
DR Central Files
L:D/D for Fuel & Materials
Regulatory Standards (3)
DR Central Files
{
Licensing (13)
'
l
i
B.
RO Inquiry Report No.
Transmittal Date
.
Distribution:
Distribution:
RO Chie f , FS&EB
RO Chie f, FS&EB
RO:HQ (5)
RO:HQ
DR Central Files
DR Central Files
Regulatory Standards (3)
Licensing (13)
{
i
..
!
!
l'
C.
Incident Notification From:
i
(Licensee & Docket No. (or License No.)
,
,
Transmittal Date
!
'
Distribution:
Distribution-
RO Chie f , FS&EB
RO Chie f, FS&EB
,
'
RO:HQ (4)
RO:HQ (4)
Licensing (4)
L:D/D for Fuel & Materials
l
'
DR Central Files
DR Central Files
,
!
4
.'
!!A
I
._