Forwards IE Bulletin 80-07,Suppl 1, BWR Jet Pump Assembly Failure. Response Required
ML19337A162
Person / Time
Site: Millstone Dominion icon.png
Issue date: 05/13/1980
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
References
NUDOCS 8009090111
Download: ML19337A162 (1)


Text

Tn

) aseg UNITE 3 STATES

/.

g[o,,

NUCLEAR REGULATORY COMMISSION

,(

g REGION 1 D

j 431 PAR A AVENUE KING OF PRUSSI A. PENNSYLVANI A 19406 May 13, 1980 0:cket No. 50-245 Northeast Nuclear Energy Company ATTN:

Mr. W. G. Counsil Vice President - Nuclear Engineering and Operations P. C. Box 270 Hartford, Connecticut 06101 Gentlemen:

The enclosed IE Bulletin No. 80-07, Supplement No. 1, "BWR Jet Pump Assembly Failure," is forwarded to you for action.

A written response is required.

This Supplement specifies the NRC offices that should receive written reports submitted in response to this Bulletin.

If you desire additional information regarding this matter, please contact this office.

Sincerely, f

AfbArt Boyce H. Grier Director

Enclosures:

1.

IE Bulletin No. 80-07, Supplement No. 1 2.

List of Recently Issued IE Bulletins CONTACT:

D. L. Caphton (215-337-5254) cc w/encls:

J. F. Opeka, Station Superintendent D. G. Ofedrick,' Manager of Quality Assurance J. R. Himmelwright, Licensing Safeguards Engineer 80 090 90.lll

ENCLOSURE 1 SSINS No.:

6820 Accession No.

UNITED STATES 8005050055 NUCLEAR REGULATORY COMMISSION 0FFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 IE Bulletin No. 80-07 Supplement No. 1 Date: May 13, 1980 Page 1 of 1 BWR JET PUMP ASSEMBLY FAILURE C.

Reporting Requirements The information in Items A.3, and B.1, is requested under the provisions of 10 CFR 50.54(f).

Accordingly, you are requested to provide within the i

time periods specified in these items, written statements of this informa-tion, signed under oath or affirmation.

These reports should be submitted to the Director of the appropriate NRC Regional Office and a copy should be forwarded to the NRC Office of Inspection and Enforcement, Division of Reactor Operations Inspection, Washington, D.C.

20555.

Approved by GAO, B180225 (R0072); clearance expires 7-31-80.

Approval was given under a blanket clearance specifically for identified generic problems.

i

3 ENCLOSURE 2 IE Bulletin No. 80-07 Supplement No. 1 Date: May 13, 1980 Page 1 of 1 RECENTLY ISSUED IE BULLETINS Bulletin Subject Date Issued Issued To No.

i 80-06 Engineered Safety 3/13/80 All Power Reactor l

Feature (ESF) Reset Facilities with an Controls Operating License (OL) (For Action)

All Power Reactor Facilities with a Construction Permit (CP) (For Information),79-03A Longitudinal Weld 4/4/80 All Power Reactor Defects in ASME Facilities with an i

SA-312, Type 304 OL or CP Stainless Steel Pipe 1

80-07 BWR Jet Pump Assembly 4/4/80 BWR 3 & 4's with OL Failure (For Action)

BWR's with CP (For Information) 80-08 Examination of Con-4/7/80 All Power Reactor tainment Liner Facilities with Penetration Welds an OL or CP 80-09 Hydromotor Actuator 4/17/80 All Power Reactor Deficienci.es Facilities with an OL or CP 80-10 Contamination of 5/6/80 All Power Reac-Nonradioactive tors with OL System and Resulting (for action)

Potential for Unmoni-with CP (for tored, Uncontrolled infor.T,ation) l Release to Environment l

80-11 Masonry Wall Design 5/8/80 All Power Reactor Facilities with an OL, Except Salem 2 80-12 Decay Heat Removal 5/9/80 All PWRs with an OL Syster Operability 80-13 Cracking in Core Spray 5/12/80 All BWRs with an Sparge's OL i

'