Forwards Resident Safety Insp Repts 50-334/89-18 & 50-412/89-18 on 890901-1013 & Notice of Violation.Weakness Identified in Oversight by Senior Mgt in Control of Overtime During Unit 2 First Refueling Outage
ML19332C739
Person / Time
Site: Beaver Valley
Issue date: 11/15/1989
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Sieber J
DUQUESNE LIGHT CO.
Shared Package
ML19332C740 List:
References
NUDOCS 8911280492
Download: ML19332C739 (2)


See also: IR 05000334/1989018

Text

-

,a

2,;

* -.

gf,

. . .

-

.

"'

4

NOV 151989 -

]

F

<

,

L Docket /L'icense:

50-334/DPR-66

50-412/NPF-73

.Duquesne Light Company

' ATTN: : Mr. J. D. Sieber

j

-

Vice President, Nuclear Group

Post Office Box 4

Shippingport, Pennsylvania 15077

,

LGentlemen:

SUBJECT: -Combined Inspection Report Nos. 50-334/89-18 and 50-412/89-18-

This refers to the routine resident safety inspection by Messrs. J. Beall and

R

P.. Wilson at the Beaver Valley Power Station in Shippingport, Pennsylvania.

'The reporting period covers the time from September 1 - October. 13, 1989. The

-

. inspection consisted of: document reviews, interviews and observation of

. activities.. The findings were summarized and discussed with you and members of

1

your staff.at the conclusion of the inspection.

"U

. Based.on the results of this inspection, it appears that in two instances,

activities-were not conducted in compliance with NRC requirements with respect

to overtime.and communications.

In addition, a weakness was identified in

-oversight by senior' management in the control of overtime during the Unit 2

'lfirst refueling outage.

In responding to violation A, please include your

plans f a correcting this weakness.

-l

The response directed by this letter and the accompanying Notice are not

subject to the clearance procedures of the Office of Management and Budget as

required by the Paperwork Reduction Act of 1989, PL 96-511.

Your cooperation with us is appreciated.

Sincerely,

Origihal Signed By:(fang 6

(

[t > Edward C. Wenzinger, Chief

a

Projects Branch No. 4

Division of Reactor Projects

Enclosures:

.

1.

Appendix A, Notice of Violation

2.-

NRC Region I Combined Inspection Report Nos.

50-334/89-18 and 50-412/89-18

l

\\

h(

OFFICIAL RECORD COPY

IN89-18 - 0001.0.0

10/27/89

\\" /

8911280492 891115

'

PDR

ADOCK 05000334

Q

PDC

'

_

nype

m en

J Q'. j. .

'

-

4..

% -,4;

-

'

T

.'Duquesne Light Company'

N0fl 51389

e

-

2.

-u

s

cc w/encls:

.

-

.

J. J. Carey, Executive' Vice President, Operations.

.

J. 0.
Crockett, General Manager, . Corporate Nuclear Services

o.

'W. S.~ Lacey, General Manager, Nuclear Operations

N. R. Tonet, Manager, Nuclear Engineering

T . Ps, Noonan, Plant Manager

,

.S.~ C Fenner, Manager, Quality Assurance.

,

.

- K, D. Grada, Manager, Nuclear- Safety

Public Document Room (PDR)

-Local Public Document: Room (LPDR)

,'

Nuclear Safety' Information Center (NSIC)

,

NRC Resident Inspector--

. Commonwealth of Pennsylvania

bec:

Region I Docket Room'(with concurrences)

Management Assistant, DRMA (w/o enclosures)

~

.C.J.-Cowgill, DRP'

.

N.F.'Dudley, DRP

P. S,-Tam, LPM, NRR

.

-

.R. J. Bores,.DRSS

(

DRP:RIGD

DRP:RI

d

CCowgill/pj

EWeny/89inger

11/sy/89

11/f6

0FFICIAL RECORD COPY

IN89-18 - 0002.0.0

11/09/89