Forwards IE Insp Rept 50-293/80-20 on 800504-08 & Notice of Violation
ML19332A944
Person / Time
Site: Pilgrim
Issue date: 06/04/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Angognini G
BOSTON EDISON CO.
Shared Package
ML19332A942 List:
References
NUDOCS 8009190078
Download: ML19332A944 (2)


See also: IR 05000293/1980020

Text

-

.

.y(d# Ni

UNITED STATES

g

4

NUCLEAR' REGULATORY COMMISSION

,,

<f

,h

REGION I

ed

g.

631 PARK AVENUE

KING OF PRUSSI A. PENNSYt.V ANI A 19406

JUN

4 1980

Docket N

50-293

Boston Edison Company M/C Nuclear

ATTN: Mr. G. Carl Andognini, Manager

^

Nuclear Operations Department

800 Boylston. Street

Boston, Massachusetts

02199

Gentlemen:

Subject:

Inspection 50-293/80-20

This refers to the inspection conducted by Mr. W. Rekito of this office on May

4-8, 1980, at Pilgrim Nuclear Power Station, Unit 1, of activities authorized by

NRC License No. DPR-35 and to the discussions of our findings held by Mr. Rekito

with Mr. P. McGuire of your staff at the conclusion of the inspection.

9

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and - esentative records, interviews with personnel, and observations and

independent calculations by the inspector.

Based on the results of this inspection, it appears that certain of your activ-

ities were not conducted in full compliance with NRC requirements, as set forth

.

in the Notice of Violation, enclosed herewith as Appendix A.

These items of

'

noncompliance have been categorized into the levels as described in our corres-

pondence to you dated December 31, 1974.

This notice is sent to you pursuant to

the provisions of Section 2.201 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Federal Regulations.

Section 2.201 requires you to submit to this

office, within twenty (20) days of your receipt of this notice, a written state-

ment or explanation in reply including:(.2) corrective steps which will be taken

(1) corrective steps which have been

taken by you and the results achieved;

to avoid further items of noncompliance; and (3) the date when full compliance

will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any

information' that you' (or your contractor) believe to be proprietary, it is

necessary that you make a written applicaticn within 20 days to this office to

..

8009190 0 73

.

.

'

.

1

.

.'

,

.

Boston Edis;n Company M/C Nuclear

'

JUN

4 1980

2

withhold such information from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b)(4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

_-

r

Ed

J. Brunner, Chief

R a tor Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection Report Number

50-293/80-20

cc w/encls: