ML19329B202

From kanterella
Jump to navigation Jump to search
Insp Rept 50-346/74-04 on 740604-05.Noncompliance Noted: Use of Unapproved Weld Rod on Main Coolant Pump Groove Weld
ML19329B202
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 06/24/1974
From: Dickerson M, Hayes D, Sutton J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19329B201 List:
References
50-346-74-04, 50-346-74-4, NUDOCS 8001310553
Download: ML19329B202 (13)


See also: IR 05000346/1974004

Text

.

.

&

.

.

O

I

U. S. ATOMIC ENERGY COMMISSION

(d

l

DIRECTORATE OF REGULATORY OPERATIONS

REGION III

Report of Construction Inspection

.

RO Inspection Report No. 050-346/74-04

'

~

Licensee: Toledo Edison Company

4

Edison Plaza

300 Madison Avenue

Toledo, Ohio

43652

Davis-Besse Unit 1

~

License No. CPPR-80

'

Oak Harbor, Ohio

Category-

A

.

Type of Licensee:

PWR (B&W) - 872 Mwe

Type of Inspection: Routine - Announced

Dates of Inspection: June 4 and 5, 1974

-

d

Date of Previous Inspection: May 14, 1974 (Second Managenent Meeting)

hl

[ Zi/' 7f

Principal Inspector'

M. W. Dickerson

/(Datd)

h hew

AccompanyingInspector:!J.W.Sutton

d 8f!7f

'Dath)

(

,

?

Other Accompanying Personnel: None

hk%

Reviewed By f

D. W. Hayes, Senior Reactor Inspector

dJf

1'

Reactor Construction Branch

'(Dati)

.

/

DOFI E TO: PDR

LPDR

NSIC

_

m

TIC

(m)

.. . . .

8001310 6 3

.

. . . .

.

. _.

,p

!

_

.- _ _ _ _ _ _ _ _ _ _ . _ _ _ - - _ _ _ _ _ _ _ _ _ _

,

.

'

.

e

.

V

' SUMMARY'0F FINDINGS

Enforcement Action

A.

Violations

One of the activities at the Davis-Besse site appear to be in violation

'

of AEC regulations and in nonconformance with the Babcock and Wilcox

Company (B&W) welding procedure, as identified below, and 'is considered

to be of Category II severity.

I

10 CFR Part 50, Appendix B, Criterion V, states, in part, that:

" Activities affecting quality shall be prescribed by documented

instructions, procedures,

. and shall be accomplished in

...

_

accordance with those instructions, procedures, or drawings."

B&W welding instruction sheet WIN-120-2, Revision 0, indicated that

the maximum size ~ weld rod to be used for the main coolant pump

groove weld would be 1/8" diameter.

-

Contrary to the above, a 3/16" weld rod was used prior to being approved

by Bechtel Corporation (Bechtel) engineers for use on the designated

coolant pump weld.

(Paragraph 2)

i

x,,,/

B.

Safety Matters

.

No safety matters were identified.

Licensee Action on Previously Identified Enforcement Matters

A.

Lack of Weld Inspection Procedure for Class lE Welds (R0 Inspection

' Reports No. 050-346/74-01 and No. 050-346/74-02)

During the inspection of January 8 - 10, 1974, it was established that

'

support and seismic welds, associated with Class 1E equipment, were being

inspected without benefit of written procedures or instructions. Moreover,

no documentation was available to establish that all the subject welds

were being inspeccad.

During this inspect 17n, the steps taken to correct this noncompliance, as

stated in the Toledo Edison Company (TECO) letter dated March 22, 1974,

were reviewed by the inspector and determined to be acceptable.

Included

was a review of detailed inspection procedures.

An extensive review of

records by the inspector, was also completed during the previous inspection.

This matter is considered resolved.

-2-

)

v

s

.

_

.~.

_ _ . .

__ . . _ .

. _ _ ,

i

'

.-

_ _ _____ --

.-

-. . . . . -.

.s.

.

.

p\\

(

s

/

g/

B.

Failure to Follow Class ~1E Weld Control Procedures (R0 Inspection Reports

No. 050-346/74-01 and No. 050-346/74-02)

During the inspection of January 8-10, 1974, documentation was not available

to establish that welding operation, associated with Class lE electrical

equipment, was being controlled in accordance with applicable procedures.

During this inspection, the steps taken to correct this nonconformance,

as stated in TECO letter dated March 22, 1974, were reviewed by the

inspector and determined to be acceptable. Included was a review of detailed

instructions relative to welding operations and the attendant inspection

requirements. This matter is considered resolved.

Decay Heat Removal Cooler Installed Without Proper Documentation Available

C.g'at the Site (RO Inspection Report No. 050-346/74-02)

During the previous inspection, it was established that the data package

for decay heat removal cooler DH-HX1B did not include a manufacturer's

data report (U-1) nor did the quality assurance release specify that a

manufacturer's data report was available for this vessel.

.

During this inspection, the steps taken to correct this matter, as stated

p

in TECO letter dated April 19, 1974, were reviewed by the inspector and

( j\\

determined to be acceptable. Included was a review of the manufacturer's

data report dated November 9, 1971. This matter is considered resolved.

x

Design Changes

No new design changes were identified.

Unusual Occurrences

No unusual occurrences were identified.

OtikerSignificantFindings

e

A.

Current Findings

1.

The licensee indicated that, as of June 1, 1974:

(1)

Construction was 64% complete, and (2)

engineering was 91% complete.

2.

The TECO quality assurance organization was augmented on May 20, 1974,

buy the addition of Mr. C. J. Greer as a Field Quality Assurance

Specialist.

.

-3-

/

s

,

.

- . - . .

.

. - - -

-.-

._-

. - .

__

_ . _ . _ _

.

-

,

~

.

(m

\\

B.

Unresolved Matters

)

sG'

1.

Class 1E Electrical Weld Acceptability

Nonconformance Reports (NCR's) No. BC-048, dated January 28, 1974, and

No. BC-052, dated February 18, 1974, were issued by Fischback and Moore

(FEM) relative to the possible use of damaged and/or wet electrodes in

the production welding of Class 1E welds prior to the 'Stop Work Order'

of January 8, 1974. Resolution of the NCR's was based upon the opinion

of the Bechtel construction manager's representative that failure of a

number of welds tested was not due to the use of damaged and/or wet

electrodes. However, this conclusion does not appear to be based on a

sound engineering evaluation. Moreover, of the 25 welds examined by

,

penetrant testing, saven were rejected, and it appears that the accept-

ability of the welds completad prior to the 'Stop Work Order' are ques-

tionable.

These matters remain open pending the results of additional

f

review by the licensee.

(Paragraph 1)

-

2.

Reactor Coolant Pumps Suction Weldment Linear Indications

The above matter was reported by TECO to RO:III in conformance with

10 CFR Part 50.55(e) requirements. A final report on the detailed

findings was not available for review during the current inspection.

,

(Paragraph 3, Report Details)

,

3.

Incomplete Welding Records, Reactor Coolant Pump - Primary Piping

'~'

Weld material and weld documentation records do not reflect the exact

record of work in progress. This matter will be reviewed during the

next scheduled inspection.

C.

Status of Previously Reported Unresolved Matters ,

, , -

1.

Class lE Electrical Cable Trays (R0 Inspection Report No. 050-346/74-02)

During the previous inspection,.it was learned that procurement and

receipt of electrical cable trays for Class lE electrical cable was

-

no longer considered Q-listed (Class lE) .

(The tray installation was

still considered as Q-listed). No information, verbal or documented,

was made available in regard to the basis for this decision.

During this inspection, it was learned that the installation of trays

for Class lE cable was

also not considered Q-listed.

Relative to justificatien for removal of the trays from the Q-list, Bechtel

,

letter Anas to Novak, dated March 7, 1974, states that there is no

requirement that the trays be Q-listed.

This is apparently based on the

statement that, if the tray fails during a seismic event, the cable would

be capable of supporting itself between the supports.

A

-4-

(~. J

.

.

-- -

.o

-

..

. . . , - .

- - - . - - .

--

,

.

.

Since the rationale that the tray, supported by and supporting Class lE

equipment, does not have to be treated accordingly, appears to be

inconsistent, this matter has been referred to Headquarters for resolution.

2.

. estinghouse Electric Corporation (W) High Pressure Injection Pump

W

Motors (R0 Inspection Reports No. 050-346/74-01 and No. 050-346/74-02

During the referenced inspections, it was reported that:

(1) the subject

,

motor acceleration time was 6.46 seconds at 70% rated supply voltage,

whereas the specification requires the motors to accelerate their drives

.

to normal operating speed within six (6) second at this voltage, and

(2) a resolution of the pump motor deficiency was underway by W.

During.this inspection, it was determined that the two motors, No.

,

HP-P1B and No HP-PlA, were shipped by B&W to W on March 29, 1974, and

April 11, 1974, respec:ively. This matter remains open pending a

satisfactory resolution of the deficiency.

-

Management Interview

A.

The following persons attended the management interview at the conclusion of

the inspection.

.

Toledo Edison Company (TECO)

.

,

J. D. Lenardson, Quality Assurance Engineer

G. W. Eichenauer, Quality Assurance Field Representative

j

E. C. Novak, Chief Mechanical Engineer

Bechtel Corporation (Bechtel)

H. A. Ablondi, Project Quality Assurance Engineer

B.

Matters discussed and comments, on the part of management personnel, were

as follows.

,

1.

The inspector reviewed the status of previously unresolved matters described

in the Summary Section of this report. During this review, the satis-

,

factory resolution of previous violations for:

(1) lack of a weld inspectiod

procedure for Class lE welds, (2) failure to follow Class lE weld control

procedures, and (3) the installation of decay heat removal cooler, DH-HX1B,

without proper documentation available at the site, were also discussed.

2.

The inspector stated that, based on his review of NCR's No. BC-048 and

No. BC-052, it appeared that they had been resolved on the basis of

opinion, rather than a sound engineering decision. Moreover, that of the

.

25 welds randomly selected for penetrant testing, seven had been rejected

for excessive porosity, slag, or linear indications and that, with this

high rejection rate, all of the welds made prior to January 8,1974,

-5-

.

. . .

o

!

l

'

<

.

i

O-

appeared to be suspect. A representative of the licensee indicated

that these matters would receive additional revi'ew.

.

3.

The inspector stated that, during his review of documentation pertaining

to the main coolant pump welds, it appeared that weld material was

used without a formal review and approval by Bechtel. The licensee

was informed that this appeared to be in violation of 10 CFR Part 50,

Appendix B, Criterton V.

,

4.

The inspector stated that it appeared that the main coolant pump weld

material and weld documents reviewed did not reflect the exact record

of the work in pror;ess. The results indicate that an in-depth audit

of the welding records would be advisable and that RO would review the

. ,

results during the next scheduled inspection.

The licensee indicated

that this matter would be discussed and be resolved.

$

_

.

.

+

.

O

I

,

.

e

4

-6-

l0

-

l

l

.

l

.

.

--.

--

.

- ..

. . . .

&

'

--

-

--

- - = _ _

. _ _ _ __

_

,

.

REPORT DETAILS

_

Persons Contacted

The following persons, in addition to individuals listed under the Management

Interview Section of this report, were contacted during the inspection.

.

i

Toledo Edison Company (TECO)

-

E. A. Wilcox, Quality Assurance Field Specialist

w

Bechtel Corporation (Bechtel)

s

J. G. Grover, Quality Control Engineer - Electrical

g

W. B. Daly, Senior Field Welding Engineer

'

?lschback and Moore, Incorporated (F-M)

D. M. Moeller, Quality Control Manager

H. J. Harris, Lead Inspector (Acting)

-

Bubcock and Wilcox Company (B&W)

W. R. Klinger, Site Project Manager

j

J. W. Marshall, Quality Control Supervisor

s_/

D. E. Kinsala, Project Engineer

Results of Inspection

1.

Class lE Electrical Weld Acceptability

Review of F-M NCR's No. BC-048, dated January 28, 1974, and No. BC-052,

dated February 18, 1974, established that:

(1) they had been resolved by

Bechtel based upon opinion, and (2) welds completed prior to the 'Stop Work

Order' of January 8, 1974, were being accepted, based upon visual inspection

'

in spite of the rejection of seven of 25 randomly selected welds subjected

to liquid penetrant avamination.

NCR No. BC-048 had been issued as a result of a Bechtel audit (No. 115)

dated January 7, 1974, which resulted in the 'Stop Work Order' of January 8,

1974.

The NCR was issued because uncontrolled weld rod was found " cold"

and " unused" in the F-M fabrication shop. As a satisfactory condicion

for resolution, Bechtel field e 3 ncering recommended that:

(1) 25

1

'i

of the Q-listed welds, completed prior to January 8, 1974, be ground and

liquid penetrant examined in accordance with ASME Section VIII, Division

I, to verify that the welds meet the requirements of AWS Dl.0-69 and do

-7-

<

l

l

1

i

-

_.. -

.. ._

. . _ .

_ _ _ _ _

_ _ _ _

.

. . -

- -

_

_

- - _ _

_

.

-

-

..

.

. -

. . . . - _ .

.m,

-

-

-

.

O

\\\\ 'J

not contain defects caused by use of wet or damaged electrodes.

The welds

were to be chosen at random and, if found satisfactory, the remaining welds

would be considered satisfactory upon visual examination in accordance with

AWS Dl.0-69.

In the event any of the 25 welds were found unsatisfactory

due to wet or damaged electrodes in the opinion of the construction manager's

representative, another sample of 25 welds would be chosen.

As a result of the liquid penetrant examination, seven welds were rej ected,

and NCR No. BC-052 was issued. Resolution was by repair and reinspection of

the seven welds, plus a statement that, in the opinion of the sonstruction

manager's representativg, the in.*.tial rejects (porosity, Flag, and linear

indications) were not caused by wet or damaged weld rods.

la technical

,

assessment or engineering evaluation was available to substantiate this

decision (other than the reports of inspection by Testmaster dated February 12,

1974, and February 26, 1974). Moreover, no engineering evaluation was

8 available which would substantiate the apparent decision to accept all welds

~

made prior to January 8, 1974, based on a visual examiniation in spite of

the relatively high failure rate of those which were examined by the liquid

penetrant method. As a result of this review, the inspector requested that

the licensee provide additional justification for the acceptance of NCR's No.

BC-0484 and No. BC-052 and acceptance of welds made prior to January 8, 1974,

based upon visual evnmination. This matter remains open pending this addi-

tional justification.

nf)

2.

Welding Procedare No. WIN-120-2, Revision 0

'%_,/

During the inspector's review of records pertaining to the Inconel reactor

coolant pump weldment, No. WJ-2-1, it is noted that welding procedure No.

WIN-120-2, Revision 0, was in use for only one day, October 1, 1973.

The

procedure allowed a maximum of 1/8" weld rod to be used for this weldment.

On October 2, 1973, the weld rod size was changed to 5/32". A revision to

the procedure was submitted for Bechtel approval on October 8,1973. Formal

Bechtel approval to use this size rod was made on November 6, 1973, as

Revision 1 to WIN-120-2. Welding operations, using 5/32" weld rod was

carried on during the period October 2, 1973, to November 6, 1973, without

formal approval.

-

-

3.

Reactor Coolant Pump Weldments

The inspector reviewed available documentation pertaining to the discovery,

by RT, of microfissures in the suction weldment (WJ-2-1) of reactor coolant

_,

pump PlA2. This matter was reported to RO:III under 10 CFR Part 50:55(e)

requirements.

Two B&W letters to Bechtel, dated March 22, 1974, and April 19,

1974, were reviewed. The March 22 letter indicated the steps to be taken

.

to determine the origin of the ceramic constituents found during study of

the weldment sample taken from weld WJ-2-1.

The letter of April 19 indicated

the progress and additional investigation being made to resolve this matter.

)

-8-

\\

.

%.J

- _ _ . .

_

_.

_

,

,

..

_

- . _ _

_

.A

. ~ .

.

-

.

V

The avaminntion of a sample from the stainless steel-pump discharge weldment,

which had shown similnr radiographic indications as the Inconel weldment,

indicated '. hat the indications in the stainless welds resulted from slag

inclusion and that microfissuring was not present. In regard to the Inconel

weldment, the studies indicated chemical constituents that were foreign to

the weld materials. Further studies are being made.

Procedures for repairs

'

of all coolant pump suction welds are being developed.

This matter will be

reviewed during a subsequent inspection.

,

4.

File of Nuclear Energy Property Insurance Association Reports

The inspector reviewed five letters containing recommendations relative to

,

fire protection matters which were on file at the site.

The letters were

dated February 24, 1971, July 20, 1971, February 14, 1972, February 13, 1973,

and April 25, 1974. An updating, contained in each subsequent report (following

[ the initial report) indicated that recommendations were being followed.

-

5.

Reactor Vessel

.

a.

Review of Quality Control System

.

The B&W QC system, for the ractor vessel receipt, handling, storage, and

installation, was determined to be acceptable relative to:

(1) instal-

g'~'

lation specifications and procedures, (2) use of experienced personnel

in the installation, and (3) installation inspection. Acceptability was

(V

,

established by selective examination of the following:

(1) B&W Specifications

'

(a) No. FS111-la-14, Receipt, Off-Loading, Handling, Storage and

Installation of the Reactor Vessel, Revision 1, dated April 25,

1973.

(b) No. FSill-la, Attachment No. 2, dated July 1,1971 (Aligning

and Leveling Requirements and Preparation of Foundations).

.

(c) No. FS-111-la, Attachment No. 3, dated November 1,1969 (Water

'

Type Leveling).

(2) Field Construction Procedures

(a) No. 03, Unloading Reactor Vessel, Revision 3, dated December 1,

1972.

.

(b) No. 04, Unloading of Reactor Vessel Head, Revision 1, dated

November 9, 1972.

p

-9-

(v)

~~

- -.

__

.-

.

._

_

-_

.

. . - . . _ _ _

_

.m

.

.

,

.

-

.

-

)

(c) No. 06, Unloading of Reactor Vessel for Storage, Revision 1,

dated December 18, 1972.

-

(d) No. 08, Reload, Upend, and Prepare to Set Reactor, Revision 2,

dated August 13, 1973.

(e) No. 10, Final Setting of Recetor Vessel, Revision 1, dated

,

August 13, 1973.

4

.

(f) No. 11, Set Reactor Vessel MK-191, Revision 1, dated August 13,

1973.

(g) N . 12, Attach Support Places MK-193.to Reactor, Revision 2,

o

,

dated August 13, 1973.

(h) No.16, Move Closure Head to Containment Building Revision 2,

df

dated October 8, 1973.

-

(i) No. 47, Set Head Storage Stand, Revision 2, dated December 17,

1973.

-

1

(j) No. 48, Move Closure Head to 603' Level, Revision 0, dated

December 12, 1973.

.

Ok) No. 56, Install Closure Head on Storage Stand, Revision 0,

dated January 31, 1974.

b.

Records Review

An ev==4 nation of the QC records for the reactor vessel established that

the vessel had been satisfactorily received, handled, stored, and installed.

Records relative to each of the field construction procedures, enumerated

above, were included in the review.

c.

' Observation of Work

'

Observatica of the reactor vessel, as it is stored in place, indicated

.

'

that the installation had been completed in a satisfactory manncr and that

appropriate protective measures were in effect.

6.

Reactor Vessel Internals

a.

Implementation of Quality Assurance Program

A review of the TECO, Bechtel, and B&W organizations and their functional

.

relationships indicated that applicable quality requirements were being

met relative to the reactor vessel internals receipt, handling and

installation.

- 10 -

s

.

-

- -.

. . - .

,

__

~

___

_

_

.

-;_ . - - - . . - .

. .k

.

'

,

.

\\

b.

Review of Quality Control System

-

The B&W QC system for the reactor vessel internals receipt, handling,

storage, and installation was determined to be acceptable including:

(1) Quarantine of nonconforming components.

,

(2) Installation specifications and procedures.

,

(3) The use of experienced personnel.

(4) Installation inspections.

,

Acceptability was established by selective examination of the following:

df

(1) B&W Specification No. FS-lll-lc, Receipt, Inspection, Handling,

-

Storage, and Installation of the Reactor Vessel Internals, dated

January 5, 1971.

(2) Field Construction Procedures

(a) No. 58, Unload and Store Reactor Vessel Internals, Revision 3,

.

dated May 2, 1974.

(b) No. 61, Remove Internals From Shipping Rig and Assemble,

'~

Revision 1, dated May 1, 1974.

(c) N . 64, Install Bolts MK-380 - Reactor Internals, Revision 0,

o

dated May 15, 1974.

(d) No. 65, Install Thermal Shield Upper Restraints - Internals,

Revision 0, dated May 15, 1974.

7.

Primary Piping - Welding

Record Review

-

t

The following quality records for primary piping weld No. WJ-4-4 were

a-==4ned by the inspector:

a.

QA inspector's records.

b.

Welders' qualification records and list of current qualified welders.

.

The records were found to be in order and signed by designated personnel.

Ninety-eight percent of the primary piping has been installed, and review

of radiographs by B&W is in progress.

,

,

l

,

.

l

.

-n,_

_ ~

-

_m

-

_

- -

_ _ .

.

- _

- -

_

--

_ . - -

. -

-. _ --

.

_ _ _ .

. ..-.

am.

_ , , _

'

-

.

.

a

-

.

>

!

l

8.

Main Steam Piping

Installation of main steam piping has started.

Piping is in the process

of fitup and being tack welded. Further review of this item is planned for

,

subsequent inspections.

1

l

i

-

,

l

!

$

'

_

/

.

~

,

!

i

.

!

.

4

.

!:

I

I

>

l

- 12 -

.

8

-,.ya,,

-

. - , , - - - - - - -

--~w---

Y

A-,

-

,,,w,


,-,w-----w.n--+

-N

-A

=-ow--,a

_ _ _ _

_ __

-

_ _ . _ . . -

.

.

ptGT ca .,

"

8

UNITED STATES

.'{

$'.

ATOMIC ENERGY COMMISSION

.

,

Q

y

OIRECTORATE OF REGULATORY OPERATIONS

REGION Ill

  • p

799 ROOSEVELT ROAD

TELEPHoNC

GLEN ELLYN, ILLINOIS 6ol37

(312) ess-2660

A.

RO Inspection Report No.

050-346/74-04

June 25, 1974

Transmittal Date

'

Distribution:

Distribution:

RO Chief, FS&EB

RO Chief, FS&EB

RO:HQ (5)

RO:HQ (4)

[

DR Central Files

L:D/D for Fuels & Materials

i

~

Regulatory Standards (3)

DR Central Files

Licensing (13)

RO Files

RO Files

-

.

B.

RO Inquiry Report No.

Tranamittal Date

i

s_/

Distribution:

Distribution:

RO Chief, FS&EB

RO Chief, FS&EB

RO:HQ (5)

RO:HQ

DR Central Files

DR Central Files

Regulatory Standards (3)

R0 Files

Licensing (13)

RO Files

C.

Incident Notification From:

(Licensee & Docke,t No. (or License No.)

,

Transmittal Date

Distribution:

Distribution:

RO Chief, FS&EB

RO Chief, FS&EB

RO:HQ (4)

RO:HQ (4)

Licensing (4)

L:D/D for Fuels & Materials

DR Central Files

DR Central Files

.

RO Files

RO Files

I

- '

---

v

19

l

%

2

R

,

~

.

R

.>

7

>

. . .

. . _ . . - .

-

O

,

, e