+*p* *8 cg%g UNITED STATES l'
I NUCLEAR REGULATORY COMMISSION n
..j WAssiNoTON D. C. 20666 I
(...+/
October 11, 1989 j
Dociet tio. 50-267 l
f l
Mr. A. Clegg Crawford l
Vice President, Nuclear Operations Public Service Company of Colorado Post Office Boy b40 l
Denver, Colorado 802 % 0840
Dear fir. Crawford:
r
SUBJECT:
FORT ST VRAIN FIRE PROTECTION SCHEDULE The staff has evaluated your letter dated June 16, 1989; in particular, those i
sectiont dealing with fire protection modifications required by 10 CFR Part 50, Appendir R.
Section 10 CFR 50.48, " Fire Protection," and Appendix R to 10 CFR Part 50, " Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1,1979," set forth certain protection features required to satisfy the General Design Criterion related to fire protection (10 CFR Fart 50, Appendix A, Criterion 3). Section 10 CFR 50.48 contains a complete discussion of the schedular requirements licensees are to follow in implementing Appendix R to 10 CFR Part 50.
10 CFR 50.48(c)(2) requires that licensees complete all modifications required f
to satisfy Ap)endix R. and not requiring prior R C approval or plant shutdown, within 9 montu after tSe effective dato of 50.48 end Appendix R, which was
~
rebruary 17, 1980. However, you requested exemption from portions of Appendix R applicable to Fort St. Vrain and on May 18, 1988, the NRC approved that exemption and the actions you proposed to take in order to achieve the same degree of
-i safety as required by the regulations. Th9 exemption did request relief from the schedule required by 50.48(c)(2), but because you could not implement the modifications you proposed in your exemption request until the staff approved it ar.d issued a safety evaluation (SE) on your proposals, the staff considers that the time for implementing the modifications began to run from the time the date of issuance of the SE. Accordingly, these modifications should have been completed by February 10,1989.
j l
The staff has received from Public Service Company of Colorado a number of comit-ments concerning fire protection modifications.
By letter dated April 29, 1987, you comitted to complete the emergency lighting system by August 26, 1987 and the fire detection system by May 15, 1987.
By-letter dated August 21, 1987, you j
modified this comitment to complete' emergency lighting by January 15, 1988, and fire detection by february 1,1988.
By letter dated January 15,1988, you modified this comitment to complete emergency lighting by March 1,1988.
By letter dated July 8,1988, you reported that emorgency lighting and fire detection were physically complete.
However, by letter dated January 20, 1989, i
you proposed a new completion schedule for emergency lighting hnd fire detection of June 30, 1989.
By your letter dated June 16, 1989, you again modified this proposal and comitted to complete emergency lighting by October 1,1989, and fire detection by August 15, 1989. Additionally, you comitted to complete all fire protection modifications by October 31, 1989.
)
00$k$$$$$)$7 h
1
'C!
Mr. A. Clegg Crawford,
Your performance in meeting these schedules is unacceptable.
J.t is f p ertant l
to emphasize that Fort St. Vrain must comply with Commission requ1'rements, even j
though you have terninated power operation. We are especially concerned aboint the completion of fire detection modifications, as well as other fire protection features.
The NRC staff will consider Fort St. Vrain to be in violation of 10 CFR 50.48 as of October 31, 1989.
Please certify in writing to us your completion of the fire detection and all other fire protection modificaticr.s en or before October 31, 1989.
If 611 requirer' changes are not.nade by October 31, 1989 as now comitted, appropriate enforcenent action including daily civil penalties may be considered.
The information requested in this letter affects fewer than 10 respondents; therefore OMB clearance is not required under P.L.96-511.
Siiteerely.
W e^f N' Gary M. Holahan, Acting Director Division of Reactor Projects - !!!,
IV, Y and Special Projects Office of Nuclear P.eactor Regulation cc: See next page 1
.b T
i l
c,
~
~
~
^
October 11, 1989 Mr. A. Clegg Crawford Your performance in neeting these schedules is unacceptable.
It is irnportant to emphasize that Fort St. Vrait, must comply with Commission requirements, even though you have terminated power operation. We are especially ccncerned about the completion of fire detection modifications, as well as other fire protection features.
The NRC
- taff will consider Fort St. Vrain to be in violation of 10 CFR 50.40 as of October 31, 1989.
Please certify in writing to us your completion of the fire detection and all other fire protection modifications en or before October 31, 1989.
If all required changes are not made by October 31 1989 as' now connitted, appropriate enforcement action including daily civil penalties may be considered.
The information requested in this latter affects fewer than 10 respondents; therefore OMB clearance is not required under P.L.90-511.
Sincerely, Gary M. Holahan, Acting Director l
Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc: See next page l
DISTRIBUTION tDocket 111e NRC PDR Local POR PD4 Reading G. Holahan ADR4 Of0$
S. Weiss P. Noonan
.l l
K. Heitner OGC-Rockville E. Jordan B. Grimes ACRS (10)
PD4 Plant File i
FSV 8984 g
- See previous concurrences-PD4/LA*
PD4/PM*
OE*
O C'.,*
PDNP/D*
(%)D:DSP Hoonan KHeitner:bj JLieberman EReis SWeiss "
GHolahan-10/ // /89'
'08/28/89 08/28/89 09/01/89 09/29/89 10/02/89 -,
a i
+
4
.E Mr. A. Clegg Crawford Your performance in meeting these schedules is unt.cceptable.
It is innporta to emahasize that Fort St. Vrain must comply with Comission requirements, ven thougi you have terminated of pcwer operaticn.
,/
The i#f steff considers Fort St. Vrsin to be in violation of 10 CFR J0.48.
Please ceitify in writing to us your completion of the emergency 1rghting, fire detection and all other fire protection modifications on oc'before October 31, 1989.
/
/
, Upon your certificatiot.' that you have met all fire protection requirenents, a decisionwillber.adeastoappropriateenforcementactjo'n.
If all required c
changes are not nade by October 31, 1989 as now commi$ted, appropriate enforcerient action including daily civil penalties may be considered.
6
/
The information requested in this letter e.ffects, fewer inan 10 respondents;.
therefore OMB clearance is not required under P.L.96-511.
Sinc [ rely,
/
Sary M. Holahan, Acting Director
/DivisionofReactorProjects-III, IV, Y and Special Projects
/,e Office of Nuclear Reactor Reculation ec: See next page
/'
DTSTRIBUTION
/
/
PD4 Reading
/
G. Holahan
/
ADR4 S. Weiss
/
P. Noonan
/
K. Heitner
/
OGC-Rockvi'le E. Jcrdan
/
B. Grimes
/
ACRS(10)
/
PD4 Flant, File
/
FSV 8984,/
/
- See pretious concurrences PDiM1,t
\\
PD4/LA*
PD4/PM*
OE*
OGC AN hoonan XHeitner:bj JLieberman ERei 4MANp SWeisy 08/28/89 08/28/89 09/01/89 09/J1/9 Sup2put
,4972/89 l
lO
'(AjD:DRSP Ghlahan id'i 09/ /89 fl
.c
.: y L'
u
A o
i Mr. R. O. Williams
-?-
I 1he NRC staff considers Fort St. Vrain to be in violation of 10 CFR 50d 8.
i i
Please certify in writing to us your completion of the emergency lighting, fire detection and all other fire protection modifications on or before the I
dates you have consnittei to for completics.
j/
Upon your carrtification that you have met all fire protectionIequirements, a decisionwillbemadeattoappropriateenforcementaction/.'Ifallreouired changes are not made by October 31,198? as now connitted daily civil j
penalties inay be considered, j
/
The information requested in this letter affects fewer'than 10 respondents; therefore OMB clearance is net required under P.L.96-511.
/
Sincerely (
Kenneth L. Heitner, Project Manager N6n-Power Reactor, Deconnissioning
' nd Environmental Project Directorate a
Division of Reactor Projects - Ill, IV, Y and Special Projects Office of Nuclear Reactor Regulation c: See next page
[
[
DISTRIBUTION Docket File
/
NRC PDR
/
Local POR
/
I PD4 Reading
/
G. Holahan
/
AC'14
/
S. Veiss
/
P. Neonan
/
K. Heitner
/
OGC-Rockville
/
- /q E. Jordan
/
3
/
B. Grimes l
ACRS (10)
/
f fh g PD4 Plant File e
pNoonan
/
PD4/PM 0
OGC OGC PDNP/D D4/LA
/'
KHeitner:bj i berman EReis JGoldberg SWeiss 1
08L@/8 05/1S/89 0
l/89 08/ /89 08/ /89 08/ /89 r
(A)D:DRSP GHolahar 08(' /89
Mr. A. Clegg Crawford Public Service Company of Colorado fort St. Vrain CC:
Mr. D. W. Warenbourg, itanager Robert it. Quillen, Director t;uclear Engineering Division Radiation Control Division Public Service Company Department of Health of Colorado 4210 East lith Avenue i
P. O. Box 340 Denvc ', Colorado 80220 Cenver, Colorado 80201-0840 I
Mr. Deviti Alberstein, Manager Mr. Charles H. Fuller Fort St. Vrain Services Manager, Nuclear Production GA International Services Corport. tion and Station Manager Post Offico Box 85608 Public Service Company of Colorado San Diego, California 92138 16805 Weld County Road 19-1/2 Platteville, Colorado 80651 Mr. H. L. Brey, Manager Nuclear Licensing anc Resource Mr. P. F. Tomlinson Manager Management Division QualityAssuranceDIvision Public Service Company of Cclorado Public Service Conipany of Colorado P. O. Box B40 16805 Weld County Road 19-1/2 Denver, Colorado 80201-0840 Platteville, Colorado 80651 i
Senior Resident inspector Mr. D. D. Hock U.S. Nuclear Regulatory Comission President and Chief Executive Officer P. O. Box 640 Public Service Coapany of Colorado Platteville, Colorado 8001 Post Office Box 840 Denver, Colorado 80201-0840 Kelley, Standfield & 0'Donnell ATTH: Mr. J. K. Tarpey Comreitment Control Program Public Service Company Building Coordinator Room 900 Public Service Company of Colorado l
550 15th Street 2420 W. 26th Ave. Suite 100-D Denver, Colorado 80202 Denver, Colorado 80211 Regional Adniinistrator, Region IV U.S. Nuclear Regulatory Comission 611 Ryan Plaza Drhe, Suite 1000 Arlington, Texas 76011 Chairman, Board of County Comissione's of Weld County, Colorado Greeley, Colorado 80631 Regional Representativo Radiation Programs Environmental Protection Agency 1 Denver Place 999 18th Street, Suite 1300 Denver, Colorado 80202-2413
.