Forwards IE Insp Rept 50-334/80-11 on 800415-17.No Noncompliance Noted
ML19323J142
Person / Time
Site: Beaver Valley
Issue date: 05/01/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Dunn C
DUQUESNE LIGHT CO.
Shared Package
ML19323J143 List:
References
NUDOCS 8006190274
Download: ML19323J142 (2)


See also: IR 05000334/1980011

Text

.

.

-

.

.E.

.

To

<

,

,

.

UNITED STATES

/

  • o

NUCLEAR REGULATORY COMMisslON

]

o

REGION I

. ll

$.

431 PARK AVENUE

8

2

KING OF PRUSSI A PENNSYLVANIA 19406

\\*s***/

MM G 1 M0

Docket No. 50-334

,

Duquesne Light Company

ATTN: Mr. C. N. Dunn

Vice President

Operations Division

435 Sixth Avenue

Pittsburgh, Pennsylvania 15219

Gentlemen:

,

Subject:

Inspection 50-334/80-11

This refers to the inspection conducted by Mr. R. McBrearty of this office on

1

<

April 15-17,1980 at the Beaver Valley Station, Unit 1, Shippingport, Pennsylvania

of activities authorized by NRC License No. DPR-66 and to the discussions of our

'

findings held by Mr. McBrearty with Mr. J. A. Werling of your staff at the

,

conclusion of the inspection.

1

Areas examined during this inspection are _ described in the Office of Inspection

l

and Enforcement Inspection Report which is enclosed with this letter. Within

i

these areas, the' inspection consisted of selective examinations of procedures

4

and representative records, interviews with personnel, and observations by the

inspector.

'

'

-

i

Within the scope of this inspection, no items of noncompliance were observed.

l

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

.

!

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

,

report will be placed in the NRC's Public Document Room.

If this report contains

i

any information that you (or your contractor) believe to be proprietary, it is

,

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure.

Any such applict.? ion must be

accompanied by an affidavit executed by the owner of the informatie , which

j

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Consnission as listed in subparagraph (b) (4) of Section

2.790. The information sotight to be withheld shall be incorporated as far as

possible into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified period the report will be placed in the Public

,

Document Room.

,

f

'

,

'

,-

8.006.190.779

-Q

.

.

. .

-.

. . - .

. --.

-

- -

.

.

..

-

_

Duquesne Light Company

2

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

Robert T. Carlson, Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

Office of Inspection and Enforcement

i

Inspection Report Number 50-334/80-11

cc w/ encl:

F. Bissert, Technical Assistant Nuclear

R. Washabaugh, QA Manager

J. Werling, Station Superintendent

G. Moore, General Superintendent, Power Stations Department

J. J. Carey, Director of Nuclear Operations

R. Martin, Nuclear Engineer

J. Sieber, Superintendent of Licensing and Compliance, BVPS

,