Forwards IE Info Notice 80-16, Shaft Seal Packing Causes Binding in Main Steam Swing Disc Check & Isolation Valves. No Written Response Required
ML19323D817
Person / Time
Site: Hatch, Vogtle  Southern Nuclear icon.png
Issue date: 04/29/1980
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
References
NUDOCS 8005220380
Download: ML19323D817 (1)


Text

r-l j#

4 **

UNITED STATES O

NUCLEAR REGULATORY COMMISSION g

4

)$

o 4

a 1j REGION 11 101 MARIETTA AT N.W., SUITE 3100 ATLANTA, GEORGIA 30303

%,....+

APR 2 91980 In Reply Refer To:

RII:JPO 50-3.21,_50:366 Q0-424, 50_425)

Georgia Power Company Attn:

'J.

11. Miller, Jr.

Executive Vice President 270 Peachtree Street, N.W.

Atlanta, Georgia 30303 Gentlemen:

The enclosed IE Information Notice No. 80-16 provides information on two instances of main steam swing check or isolation valves binding due to shaft packing.

Sincerely, hh

% h%

James P. O Rei ly t

Director

Enclosures:

1.

IE Information Notice No. 80-16 2.

Recently Issued IE Information i

Notices l

i i

i l

i

/

I 1

?

I

_ _____. 8_0 05 2 2 0 3 8 0_ _

hPR 2 5 1999 Georgio Power Company.I cc w/ encl:

M. Manry, Plant Manager Post Office Box 442 Baxley, Georgia 31513 C. E. Belflower Site QA Supervisor Post Office Box 442 Baxley, Georgia 31513

^

K. M. Gi11espie Construction Project Manager Post Office Box 282 Waynsboro, Georgia 30830 E. D. Groover QA Site Supervisor Post Office Box 282 Waynesboro, Georgia 30830 W. A. Widner, General Manager Nuclear Generation Georgia Power Company Post Office Box 4545 Atlanta, Georgia 30303 l

i

. ~.

e.

~

.Av e au -

i I

l i

l f.

- - - + - - - -

l. r :....

.-... a

...: : L: 1 -

=

t

SSINS No.: 6870 Accession No.:

UNITED STATES 8002280667 NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, DC 20555 April 29, 1980 IE Information Notice No. 80-16 SHAFT SEAL PACKING CAUSES BINDING IN MAIN STEAM SWING DISC CHECK AND ISOLATION VALVES Description of Circumstances:

Recently two instances of binding of swing check valves have occurred. -During disassembly of the main steam isolation valves at Indian Point 2, it was observed that all four reverse flow check valves were stuck at or near fully open. These 28" valves are manufactured by Atwood & Morrill Co.

Investigation revealed that this condition was apparently caused by excessively tight shaft packing which did not allow free movement of the valve disc.

This condition was reported on January 31, 1980. An evaluation determined that with the existence of the reported condition in event of a main steam line break upstream of a main steam isolation valve together with coincident single failure of a main steam isolation valve to close in another loop, the potential existed for blowdown of the contents of two steam generators.

Main steam line break analyses applicable to Indian Point 2 have been performed assuming blowdown of the contents of one steam generator and have not considered multiple steam generator blowdown. Therefore, it is possible that the reported condition could have contributed to the exceeding of a safety limit as defined in the Unit 2 Technical Specifications if a main steam line break had occurred.

The reported condition was corrected by adjusting the packing of these valves in all four loops and verifying that valve disc movement is not restricted.

During testing in the hot standby mode at the Trojan Nuclear Plant on April 15, 1980, three of the four main steam line isolation valves failed to close when manually actuated. The cause of the occurrence was binding in the shaft packing. The valve is air opened and is closed by gravity, steam flow and a small spring force; the valves were manufactured by Atwood & Morrill Co.

The licensee believes that the valves would have closed during actual operations with steam flow in the line. The valves were repaired and tested satisfactorily.

Modifications to the valves to install air operators to help close the valves are being investigated by the licensee.

This Information Notice is provided as notification of a possible significant matter.

It is expected that the recipients will review the information for possible applicability to their facilities and appropriate corrective action taken.

No written response to this IE Information Notice is required.

l n.

IE Information Notice No. 80-16 Enclosure April 29, 1980 RECENTLY ISSUED IE IhTORMATION NOTICES Information Subj ect Date Issued To Notice No.

Issued 80-16 Shaft Seal Packing Causes 4/29/80 All power reactor Binding in Main Steam Swing facilities with an OL Check and Isolation Valves or CP 80-15 Axial (Longitudinal) 4/21/80 All light water reactor Oriented Cracking In facilities holding power Piping reactor OLs or cps 80-14 Safety Suggestions From 4/2/80 All power reactor Employees facilities with an OL or CP 80-13 General Electric Type SBM 4/2/80 All light water reactor Control Switches - Defective facilities holding power Cam Followers reactor OLs or cps 80-12 Instrument Failure Causes 3/31/80 All holders of power Opening of PORV and Block reactor OLs and cps Valve 80-11 General Problems with ASCO 3/14/80 All holders of Reactor Valves in Nuclear Application OL, CP, fuel fabrica-Including Fire Protection tion and processing Systems facilities 80-10 Partial Loss of Non-Nuclear 3/7/80 All power reactor Instrument System Power facilities holding Supply During Operation OLs and cps 80-09 Possible Occupational 3/7/80 All holders of Health Hazard Associated power reactor OLs with Closed Cooling Systems and near term cps 80-08 The States Company Sliding 3/7/80 All power reactor Link Electrical Terminal facilities with an OL Block or a CP 80-07 Pump Shaft Fatigue Cracking 2/29/80 All Light Water Reactor Facilities holder power 1

reactor OLs and cps

,