O 3 - Page 1 f/V C J- D S u n E Part III .

A

  • Sec. 2.1

/s '

N-0QN4 Revised 10/18/74 TENNESSEE VALLEY MNIUAL ALTrHORITY OPERATIONAL QUALITY ASSURANCE gRT III, SECTION 7.1 i diA..S2 PROCUREMENT OF MATE assign quality assurance TITLE be followed 'y 5 fj of this procedure is to arts for SCOPE - The purpose responsibilities and establish procedures toi ls, components, an -

' the procurement of mater aand maintenance of TVA's nucparts for tho the operation of this Materials, components,mponents and spare (CSSC) identifiewith the requ structures, systems,accordance and co l shall be procured in units l procedure. a bulk basis in r feet , etc. , with ble a

DEFINITIONS - 1.

Material -Items purchased onof pounds, squ L descriptive narrative fications.

codes and material speci a complete assembly a complete 2.

Comeonent-Item purchased asin a system, as that can be installedan intended function.

assembly, to perform a repair or replacement I

L Soare Part-Items purchased as component.

3 element of a cedure, the term pres ~sure Coolant I

4. Pressure Boundary -In this proabbreviated fined in form

~. of "Re L

boundary is anPressure Boundary" which is de

[

PROCEDURE ent j

'b 1.0- General Process For f Procurem the procurement ofassociated w appropriate management o re parts of quality assurance To assure assignments materials, components, and spa operation of nuclearare plants, outlined in Table 1.

responsibilities L

L 80 07160yfyt -

TABLE 1 D g2aY e h g[*

235 $ 82 s sa '

. RESPONSIBILITIES FOR PROCUROHENT #4

  • [

g Quality Assurance Action Organization Quality Assurance Function Manual Reference

  • 1. Initiate Request to Stock New Items Plant and/cr central office- Specifies quality assurance Part III, Sec. 2.1 (form TVA 6523-9) su; Purchase section supervl.sor requirements **

Request (form TVA 2652) (for all other requests)

2. Prepare purchase requisition Plant Power Stores Unit Incorporates specifications Part III, Sec. 2.1 (form TVA 201) and special conditions into purchase request
3. Approval of purchase' requisition Plant superintendent and/or Approves quality assurance Part III, Sec. 2.1 central office requirements
4. Request for quotation or invita- Division of Purchasing Incorporates quality Part III, Sec. 2.1 tion to bid (form TVA 9640 or 5050) assurance requirements in procurement documents
5. Evaluation of quotation or bid Plant and/or central office Evaluates quality assurance Part III, Sec. 2.1 (if required) response
6. Award of contract Division of Purchasing Contracts quality assurance Part III, Sec. 2.1 requirenents
7. Vendor inspection (if required) Inspection and Testing Checks manufacturing quality Part III, Sec. 2.1 Branch or others assurance
8. Receipts, inspection, storage Plant Power Stores Unit and Verifies and preserves Part III, Sec. 2.2 plant section supervisor quality assurance docunents
9. Isv.ue Plant Power Stores Unit and Stores - documents issue. Part III, Sec. 2.3 plant section supervisor Section supervisor - respon- ,

sible for handling and integrity of item until installed

10. Use Plant section supervisor Documents correct installa- Part II, Sec. 2.0 tion and use t

AA s

  • Revision
    • Deletion liIC L________________

R-1 I

I l~ l I C. F

~ .

<. 7 7 l l .i b.i

Pcg3 3

~

Part III Sec. 2.1

, N-0QAM Revised

.- 8/29/78 2.0 Responsibilities and Requirements

  • Material and equipment required in the operation and maintenance of TVA's
d. nuclear plants are purchased by the Division of Purchasing. Purchase specifications prepared by the originator of a request form the basis of

'- the contract between TVA and the supplier. A Contracting Officer is named for each contract by the Division of Purchasing. The Contracting Officer is responsible for assuring that provisions of the contract are met. All technical interpretations cre made by the organization which h originates the specifications. Contracts are awarded only to qualified ma'ufacturers. Contracts provide access by TVA inspectors to areas of a manufacturer's plant and access to any associated records when a

' source inspection, audit, or surveillance is planned.

2.1 Preparation of Purchase Requests All items of the critical structures, systems, and components as

- identified in Appendix A of this manual shall be considered to require quality assurance surveillance.

The primary responsibility for initiation of quality assurance requirements in the procurement of materials, components, and spare parts rests with the originator of the purchase request.

He is responsible for assuring that regulatory, code, design basis,

. _ _ and other requirements are properly included or referenced in the request.

9 The originator of each request for material, components, or spare parts within the scope of the operational quality assurance program shall be familiar with the function of the system for which he is ordering material; with the importance of the material

_ or equipment to be ordered to plant safety; and with the applicable codes, standards, criteria, design bases, and regulatory require,ments.

The request shall include those quality assurance requirements consistent with the importance of the purchased material or equipment

~

to plant safety. -

The appropriate section supervisor is responsible for notifying

- Power Stores of any changes which would affect the reorder of stock

.tems.

- The intent of these requirements shall be to procure material ~ and equipment equal to or better than that utilized in the original design and construction of the affected system.

-- 2.2 Assignment of Quality Surveillance Levels Purchases of items for nuclear plants are divided into two general ,

categories. Items for general use not related to critical structures, I

~'

systems, or components shall be purchased through regular procurement 8

, channels that do not involve the assignment of nuclear quality assurance. requirements. Noncritical structures and equipment are 4dentified in Appendix A of this manual.

h

  • Revision '/

.y v W

th W7r

~ '

P;g) 4 Part III __

Sec. 2.1 N-0QAM ,

Revised 2/4/80 __

. Materials, components, and spare parts purchased for installation --

in the critical structures, systems, and components shall be purchased through unique channels established to ansure that nuclear quality assurance requirements have been satisfied. To provide for uniform interpretation of regulatory requirements and to assist those charged -

with the responsibility of ordering materials, components, and spare parts, the Division of Nuclest Power has adopted the following policy which is intended tq be specific and practical.

Materials, components, and spare parts which will become part of the S

['

critical structures, systems, and components shall have assigned to the purchase request one of four levels of quality assurance surveil- ,s lance. Assignment and application of one of the four levels shall be to assure quality of a purchased item to an extent consistent with its -

importance to nuclear safety. Also, the packaging and shipment of -

these items shall be commensurate with their importance to nuclear safety. __

The originator of the purchase request is responsible for assignment ,,

of the appropriate level. ,

The four levels of quality assurance surveillance are described in detail in the following paragraprm.

2.2.1 Level I Level I quality assurance surveillance shall be assigned to: (1) those materials, components, and spare parts which --

are a part of and whose failure would violate the reactor coolant pressure boundary; (2) those other CSSC items that cannot be bought by industry standards or reference -

part number; and (3) certain items that must be specifically

~

bought as Level I and are so defined in DPM No. N76A10.

The reactor coolant pressure boundary is a part of the critical structures, systems, and components. Attachment 1 .

of this spare parts procedure defines the reactor coolant

- pressure boundary. Appendix A at the end of .this manual lists.the critical structures, systems, and components. __

    • Deletion %.X' ft -

s / ~~

1 JGD J JRC g,q,$Q f

W 9

"en E - , .

Paga 5 Part III Sec. 2.1 E

x-ooia Revised 2/13/80 Normally Level I shall not be assigned if the assignment of Level II, III, or IV provides adequate quality assurance surveillance.

Items assigned Level I quality assurance surveillance shall undergo a receipt inspection, identification confirmation, g and segregated storage as outlined in Part III, Section 2.2.

The originator of the purchase request is responsible for I the listing of specific documentation and engineering specification requirements under the assigned level.

A. Applicable codes, standards, and approved drawings for fabrication.

B. Materials and materials certification.

C. Inspection requirements. .

D. Vendor's quality assurance requirements.

5 E. Performance test requirements.

F. Instruction for documentation sub'mittal and retention.

Refer to attachment 2 for checklist of types of inrormation which may be required.

In lieu of detailed specifications listed above, items I assigned Level I may be purchased by part number and reference to the original contract and to the specifications and code requirements thereof and a certification by che I vendor that these requirements have been fulfilled. The purchase requisition should contain, but not be limited to, the fellowing:

A. Original v.mdor contract number.

B. Original TVA contract number.

C. Equipment identification.

D. Identification and part number of item being purchased. .

E. Inspection requirements.

The originator of the purchase request shall be responsible for determining the need for inspection at the vendor's plant. If required, a statement should be made on the I purchase requisition in regard to responsibilities for inspection. Either the accompanying specification should detail the requirements of inspection or, if I purchased from the original vendor by part number, the purchase requisition should outline the inspection requirements.

Upon award of contract, the Division of Purchasing shall forward a copy of the contract including We inspection requirements to the Inspection and Testing Branch if they a have been assigned responsibility for inspection.

E

Pcgn 6 '

  • g Part III Sec. 2.1 g N-oQAM Revised

. E 2/13/80

  • When selecting sources for Level I items or services,the purchase request originator should refer to the Qualified Vendors' Listing in Appendix 7. DPM No. N76A10, of the Nuclear Power Division Procedures Manual. The attachment should be referenced, not attached, on the purchase request and requisition for purchases of an original nature.

Should " sole-source" purchasing be required, the previous supplier and contract number should be included on the B

3 purchase request or requisition.

2.2.2 Level II Level II quality assurance surveillance shall be assigned to those CSSC materials, components, and spare parts that can be purchased by positive identification, provided that E

3 these items are not Level I. Level II surveillance permits in-kind replacement of items when the specified industry code and standard provide positive identification. positive -

identification shall be established for an item by using one of the following methods:

A. Documentation supplied with the original equipment and/or from name plate / tag information attached to the original equipment.

B. The item's description as specified by the engineering drawing bill of material.

C. The item's description as specified in the technical specification.

D. The item's noun name and part number when supplied by the original supplier, manufacturer, or vendor.

The originator of the purchase request shall be responsible for determining the need for inspection at the vendor's ,

plant. If required, a statement should be made on the purchase requisition in regard to responsibilities for in-spection. Either the accompanying specification should -

detail the requirements of inspection or, if purchased from the original vendor by part number, the parchase re-quisition should outline the inspection requirements.

Each purchase requisition for Level II items shall include the f ollowing statement:

If any changes are made by the seller to the item descriptions specified by TVA, the reason for the changes shall be given by the seller by placing each changed item in one of the categories listed E

3 below. All category B items shall be submitted ,

by the TVA purchasing agent to the originator of the purchase request for evaluation prior to award.

  • Revision A'v, a  %-

8JGD

, 'yp,JRC

Pcg2 7 Part III I' Sec. 2.1 N-OQAM Revised 1/28/80 A. The description changes for the items listed below are only for clarification. The items supplied are identical to the items specified I by TVA.

Item Nos.

B. The description changes for the items listed below propose substitutes that are equal to or better than the items specified by TVA.

Item Nos.

Where applicable, the requisition should also require that the vendor submit a Certificate of Compliance to industry codes and standards.

  • Normally Level II shall not be assigned if the assignment of Level III or IV provides adequate quality assurance surveillance.

Level II iteas shall receive a receipt inspection, ideatification confirmation, and segregated storage as outlined in Part III, Section 2.2. Generally, the extent of the receipt inspection for Level II items shall only be for apparent damage and to identify I the part number.

2.2.3 Level III Level III quality assurance survei. lance may be assigned to those materials, components, and spare parts of the CSSC which j are sufficiently standardized that an equivalent part manu-a f actured by another company may be substituted for the original part. The fellowing are examples of items which may be ,,

purchased as level III:

Bearings and Oil Seals Square and Hex Bolts. -

Screws, and Nuts Resistors Internal Wiring for Switchboards, Panels, and Control Stations Greases, Lubricants, and Chemical Additives Fuel Oils DPM No. N76A4 describes the standards and cross-reference guides which may be used to purchase level III items. Only those items listed in this division procedure and no others may be purchased as level III items.

  • Leve III shall not be assigned if the assignment of Level IV prov de adequate quality assurance surveillance.

\ '..

  • Revision N /' '

JGD JRC

g P:g2 8 M Part III Sec. 2.1 N-0QAM '

Revised 1/28/80 Level III shall not be assigned to items which may not be substituted (e.g., items modified for a specific component) and shall not be assigned to parts, components, or services that are " Basic Components," as defined in 10 CFR part 21.

2.2.4 Level IV Level IV quality assurance surveillance is assigned to the materials, components, and spare parts of the critical structures, systems, and components (CSSC) that obviously have no safety-relhted function. The assignment of this level of quality surveillance is intended to document that a review has been made of the safety aspects of the CSSC item to be purchased and a decision made that none are involved. These items may be purchased through regular procurement channels. Examples of items assigned this level of quality assurance surveillance are:

A. Noncritical screws, bolts, nuts, or washers.

B. Valve handwheels.

C. Cotter pins.

D. Identification tags or plates.

3.0 Initiation and Review of Purchase Requests Administrative processing of purchase requests is identified in NUC PR Division Procedures Manual, Procedure ~ No. N72A14 Items found to be defective and handled as non-conforming material shall not be reordered until the correct item can be identified.

3.1 Routine Purchase Request - Initial Stock

~

Requests for the purchase of the initial stock of materials, components, and spare parts for the systems covered by this procedure shall be initiateo by the responsible section supervisor. The .

supervisor shall submit a written purchase request approved by the plant superintendent to the Supervisor, Power Stores Unit. The -

request shall include the necessary data to purchase the material, component, or spare part; the purchase specification if required; and tha appropriate quality surveillance level.

3.2 Reorder of Stock Items Purchase requisitions required for replenishment of initial stock within the maximum-minimum level limits established by the responsible section supervisor shall be originated by the Power Stores Unit supervisor. Approved specifications covering prior receipts shall be used.

i

.~

a ,

E- Paga 9 Part III Sec. 2.1 E -

N-0QAM Revised 1/10/80 3.3 Direct Charge Purchases Direct charge purchase items include material and equipment not normally carried in inventory which are procured in response to I requirements for repair or planned maintenance activities. All actions of Table 1 shall be followed except item 8, Storage.

3.4 Emergency Purchase Requests Emergency purchase requests shall be handled in the same basic manner as normal reques,ts, except that approvals may be established by telephone communication and procurement initiated in advance of I a formal written purchase request which must follow. However, quality surveillance requirements as outlined in paragraph 2.0 of this procedure shall not be relaxed.

3.5 Field Purchase Orders ,

Fiald purchases may be requested by a section supervisor who shall assign quality assurance surveillance levels as required. After I approval of the request by the plant superintendent, the Supervisor, Power Stores Unit, issues a field purchase order. Quality surveil-lance requirements as outlined in paragraph 2.0 of this procedure E shall not be relaxed.

3.6 Procurement Document Chanses Procurement documents shall include all quality-related purchase requisition requirements, and these shall not be changed without the review and approval of the originator and the responsible quality assurance organization. The plant superintendent has the I authority to change the quality assurance surveillance levels provided (1) that the new level meets the requirements of this quality assurance procedure: (2) that a change to Level I cannot be made without prior review by the NUC PR Quality Assurance Staff E and approval of the Assistant Director of Nuclear Power (Operations);

and (3) that the change of level be documented in accordance wieh Attachment 3.

  • In order to establish a consistent division policy relative to the assignment of different QA levels to identical items at various nuclear plants, and to specify standardized technical and/or QA requirements for procured articles, the Power Stores central office supervisor has the authority to initiate a Quality Assurance and Engineering Change Request, Attachment 4, which would be generic to all nuclear storerooms. These change request forms must be reviewed by the Nuclear Power QA Staf f, approved by the Assistant Director of Nuclear Power (Operations), and documented in accordance with Attachment 4 A copy of each completed Attachment 4 form shall I be submitted to the affected nuclear plant superintendents for plant documentation. A Local Change of Operational QA Level Assign-ment and/or Change to Material or Spare Part Description, Attachment 3, E need not be completed for these items.

3.7 Central Of fice-Initiated Purchase Documents Purchase documents initiated in the central office for Levels I, II, III, or IV materials, ccmponents, and spare parts shall be submitted to the affe e d plant fer their review and approval.

  • Revision /

1 JGD V JRC

.. c-t_

Peg 2 10 Part III Sec. 2.1 N-0QAM l

M Revised '

11/24/78 4.0 Quotation and Bid Review and Award Quotations and bids by manufacturers are reviewed by Power Stores and the originator, if requested, to ensure that no exceptions are taken. Exceptions which may affect quality shall be accepted only after being subjected to the same review / approval cycle as the original procurement document. The speci-fication requirements and the manufacturer's quality assurance plan -1.all be reviewed with the manufacturer when necessary to be certain that he under-stands all requirements and that his quality assurance program fulfills specification requirements. Awards are made only to qualified manufacturers.

The determination that vendors are qualified is usually based on TVA audits, audits by others (e.g. , NRC, ASME, or CASE), review of the vendor's per-formance history, or by review of the vendor's QA manual. Detail requirements for evaluating the qualification of vendors are found in DPM No. N76A10, Appendix 5. After award of the contract, assessment of the effectiveness of quality control by the manufacturer and other suppliers shall be made at intervals consistent with the importance, complexity, and quantity of the product. Such assessment by P PROD shall be based on test reports, reports of inspections at the manufacturer's facilities, audit reports, receipt inspection reports, or other evidences. Corrective action shall be taken where needed.

5.0 TVA Certification or Manufacture TVA may elect to accept responsibility for originating quality assurance

ocumentation in the purchase of materials, components, or spare parts when documentation required from the supplier is either not available or excessively expensive, or causes undesirable delay in delivery. TVA shall provide adequate testing and certifying facilities to supply the necessary quality assurance documentation.

TVA may manufacture, repair, or recondition materials, components, and spare parts for use in the critical structures, systems, and components.

Adequate production, testing, and certifying facilities shall be available and quality assurance documentation shall be supplied. The originator of the request shall specify the appropriate quality assurance surveillance ~

level and the documentation to be supplied.

6.0 Certification Bv Outside Agencies TVA may contract with an outside agency for quality assurance documentation 3 in the purchase of spare parts. For example, a contract may be arranged with the primary nuclear steam system supplier to provide quality assurance E

services covering spare parts purchased from this supplier or its subcontractors, t

I

? . *4 Page 10a '

Part III Sec. 2.1 N-WAM Revised 7.0 l'urchase of Spare and Repincement Parts From Prime Supplier Sparc and replacement items which were originally under a prime supplier's (i.e., NSSS's or A/E's) scope of supply may be ordered from that p ri me supplier with some procurement control responsibilities delegated to the prien supplier. Quality assurance levels will be assigned as described ab ve; however, for QA Level I items, the originator of the pucchase request need not list the specific doc entation and engineering specification requirements if the spare and replacement items are to be provided in I accordance with the supplier's quality assurance program which assures that the items are equal to or better than the original items. The P PROD Quality Assurance Staf f shall make certain that the prime supplier is periodically audited to assure his quality assurance program is properly implemented.

  • 8.0 Modification Materials .

When materials are procured for work covered by an approved ECN, the material specifications given by EN DES on the engineering drawings shall be included in P PROD procurement documents. These EN DES material requirements shall take precedence over standardized P PROD material specifications normally used.

I SINIITTED j APPROVE ,

Chief, pcIcar Generation Branch M tor of Power Production

^

n Q

Attachments:

1. Pressure Boundary Definition and Interpretation ~
2. Purchase Originator's Documentation Guide
3. Form Memorandum for Local Change of QA Level Assignment .
  • Revision I .

I

I' .

Page 11 I

  • A,t t achment _1, ,

Part III Sec. 2,1 N-OQ/sM Revised I DEFINITION - Reactor Coolant System 10/18/7h I "The reactor coolant system is that system which contains primary reactor coolant at operating pressure during nomal reactor operations." (Footnote 2, Page 2, Para.15-120,Section XI, of ASME Boiler and Pressure Vessel Code,1971 I .

Edition.)

DEFINITION - Reactor Coolant Pressu're Boundarv.

I " Reactor coolant pressure boundary means all those pressure-containing components of boiling and pressurized water-cooled nuclear power reactors, such as pressure vessels, piping, pumps, and valves, which are: .

(1) Part of the reactor coolant system, or I (2) Connected to the reactor coolant system, ~o to and including any and all of the following:

(i) The outemost containment isolation valve in system piping which penetrates primary reactor containment, I -

(ii) The second of two valves nor ally closed during nomal reactor operation in system piping which does not penetrate primary reactor containment, (iii) The reactor coolant system safety and relief valves.

For nuclear power reactors of the direct cycle boiling water type, the reactor coolant system extends to and includes the I outemost containment isolation valve in the main steam and feedwater piping." (10 CFR 50.2)

INTERPRETATION - Reactor Coolant Pressure Boundary "The scope of these rules covers the strength and pressure integtity of the structure of pumps and valves whose failure I would violate the pressure boundary. They are not intended to be applicable to valve operators, controllers, position indicators, pump impellers, pump drives or other accessories I and devices, unless such items themselves are pressure parts.

These rules provide requirements for new construction. They cove,r mechanical and themal stresses but do not cover I

deterioration that may occur in service as a result of corrosion, radiation effects, and instability of material."

(Draf t ASME Code For Pumps and Valves For Nuclear Power, November 1968, Paragraph 110.) (1971 ASME Boiler and Pressure I Vessel Code,Section III - Nuclear Power Plant Components; Paragra;Qs NA-ll10, NA-ll20, NA-1130, and NE-1141 restate the above Pump and Valve Code concepts for Nuclear Power Plant '

Components.)

I

Page 12 Part III Sec. 2.1 N-04N4 f(r vine d lo/ll!/'/ sl TVA INTERPRETATION - Violation of Reactor Coolant Pressure Boundary The following statements reflect TVA's specific interpretations of the intent of codes, standards, and regulations concerning the meaning of the phrase " violation of the pressure boundary" as used in connection with specifying quality assurance I requirements in the procurement of materials, 3 components, and spare parts covered by this p rocedure.

~

A. Failure of a pump or valve to perform its intended function does not necessarily constitute a violation of the pressure boundary.

B. Leaks associated with packings, gaskets, seals, and seats do not constitute a violation of the E pressure boundary. 3 .

C. A violation of the reactor coolant pressure g boundary e: ists when a fluid retaining component g within the li: sits of the pressure boundary as defined on page 11 of this procedure fails to perform its fluid retaining function to the extent that normal pressure or flow associated with that l

a component is significantly affected or technical specification limits are exceeded.

D. A violation of the reactor coolant pressure , boundary exists when a fluid retaining component such as a a pump, valve, or pipe within the limits of the pressure boundary as defined on page 11 of this - I procedure fails and results in a radiation hazard to either the plant personnel or the general public I in excess of the limits of exposure or permissible 5 levels.as set forth in 10 CFR 20 or other applicable regulations.

SUPPLEMENTARY NOTES - 1. Although not strictly included in the definition of pressure boundary, Ldvel I quality assurance surveillance has been assigned in this procedure to the purchase of pump impellers and shaf ts and valve discs. Level I surveillance may be assigned to other items of this nature as determined by l the originator of the purchase request. E o

I

I .

Pee 13 I

  • Part III Sec. 2.1 N-OQAM Revised I

10/18/74

2. Page 12 of this procedure, Violation of Reactor Coolant Pressure Boundary, addresses to the meaning of the word " violation." There is no intent to I modify or extend the definition of " pressure boundary" as noted on page 11.

I 3. A flow check valve is an isolation valve (TVA G-28 appendix A, class A) .

4.

I TVA General Construction Specification G-28, Construction of Piping System For Boiling Water Reactor Nuclear Plants, provides for classification of piping systems in classes ranging from class A I through class N. Quality assurance requirements are identified as applying to class A, B, C, D, and E piping systems by General Construction I Specification G-27. The piping classification assigned to each section of line is identified on various piping drawings. Repair or replacement piping should satisfy requirements at least I equivalent to that specified for the original pipe.

5. B 31.7, Nuclear Power Piping, does not cover piping 1 inch or smaller, therefore, " class A" does not cover piping 1 inch or smaller, however in some instances, TVA drawings show an assignment of class A to some 3/4-inch lines.
6. Design criteria or specifications, as built. shop drawings, and other records should be available I to the originator of a purchase request which identify, by number, ASTM specifications for stedl piping. Individual ASTM standard specifications I contain detailed instructions for writing purchase orders for the purchase of piping to these ASTM specifications.

I ~

I I

I

1 j

  • l l

Page lh '

Part III ,

1 Sec. 2.1 .

N-0QAM ^teachment 2, Revised ,

10/18/7h Purchase Ort s,l nator'" Documentation Guide The following is a checklist reminder for use by the originator of a purchase request in selecting the documents which shall be required to verify the quality of the purchased item. The originator shall select from this list or other sources and state on the purchase requisition his selection of the documentation required.

Type of Information

1. Drawings
2. Diagrams ,
3. Material Record Certifications A. Chemical B. Physical C. Mill Test Reports ,
4. Fabrication Procedures _

A. IIeat Treatment B. Weld Procedures i C. Weld Procedure Qualifications D. Major Repair Procedures E. Others as Specified

5. Fabrication Records A. Heat Treatment  ;

B. Major Repair C. Weld Records Including Welder Qualifications ,

D. ASME Code Forms E. Nameplate Facsimile

6. Inspei: tion Procedures 1 A. Radiography ll B. Liquid Penetrant a' C. Magnetic Particle i D. Ultrasonic E. Eddy Current ,

1

7. Inspection Records (certified) I A. Radiography (Including Legs, Maps, Spread Sheets, and Repairs)

B. Liquid Penetrant l C. Magnetic Particle  !

D. Ultrasonic 5l E. Dimensic al Check 3,

8. Test Records (certified)

- 1

Page 15 t

Part III Sec. 2.1 N-OQAM Revised 10/18/74

9. List of Records Maintained by Vendor 10.

Special Conditions or Requirements Concerning Materials or Methods Employed in A. Cleaning B.

I C.

Painting or Preserving Preparation for Shipment .

D. Storage '

11. Instruction Manuals E  :;

E E

E -

E I

I E .

--e -- , , - -

1 Pags 16 j

Part III Sec. 2.1 N-0QAM Revised .

2/14/79 -

ATTACHMENT 3 I

TO  : Supervisor, Power Stores Unit, Nuclear Plant 1

l FROM  : Power Plant Superiatendent, Nuclear Plant '

DATE  :

SUBJECT:

LOCAL CHANGE OF OPERATIONAL QA LEVEL ASSIGNMENT ANDf0R CHANGE TO MATERIAL OR SPARE PART DESCRIPTION Procurement Document No.:

Original Material

Description:

3 g!

l 1

New

Description:

PSC and Item No. Nuclear Item No.

Change QA Level From To Basis for Change B

Suggested Sources of Supply:

Submitted -

Section Supervisor Plant QA Statf Supervisor

  • Approved Power Plant Superintendent
  • Reviewed P PROD Quality Assurance Staff
  • Approved Chief, Nuclear Generation Branch
  • Completed Chief Storekeeper /Date C
  • Revision

, I

Page 17 Part III Sec. 2.1 I N-OQAM Revised 4/29/80 QUALITY ASSURANCE AND ENGINEERING CHANGE REQUEST

  • TO  : J. G. Dewease, Assistant Director (Operations), 727 EB-C FROM  : Edwin W. Mansfield, Supervisor, Power Stores Section, 425 401B-C DATE  :

SUBJECT:

QUALITY ASSURANCE AND/OR TECHNICAL REQUIREMENTS TIIC No. Initiating Location -

Related TlIC's Locations Involved Procurement Docucents I Comments:

I Technical and/or Quality Assurance Requirements:

. l Basis for Requirements:

l I Reviewed by NCO QA Staff, Division of Nuclear Power Approved by l- E g Assistant Director of Nuclear Power (Operations) ,

cc: Nuclear P ant Superintendents s

g .Revisi n S+<. vu

' JRC YGD ps = ' s.'

i

Ta I. Page 1 Part III Sec. 2.lA I N-0QAM Revised TENNESSEE VALLEY AUTHORITY OPERATIONAL QUALITY ASSURANCE MANUAL PART III, SECTION 2. lA I TITLE - PROCUREMENT OF SERVICES PURPOSE - This procedure delineates controls to be imposed on the procurement of services which are related to or which may af fect the CSSC of licensed nuclear power plants.

PROCEDURE

  • 1.0 Preparation and Handling of Procurement Documents Documents used in the procurement of services are prepared, reviewed, and handled the same as those used for procurement of materials, components, I and spare parts, except for purchase documents initiated by the central office for Levels IS and IIS services. Requisitions generated in the central office for Levels IS and IIS services shall be reviewed and approved by the P PROD Quality Assurance Staff for compliance with applicable I requirements prior to award of contract.

2.0 General Quality Assurance Requirements for the Procurement of Services Procurement documents for services shall contain detailed quality assurance requirements including as appropriate:

I (a) A copy of the cor tractor's quality assurance program which complies with the pectinent elements of 10 CFR 50, Appendix B.

I (b) Provisica that the contract perform services in accordance with TVA procedures or in accordance with their own procedures which have received TVA approval. .

I (c) Provision for TVA's right of access to the contractor's work, whether on site or off site, to perform, if necessary, quality -

assurance audits, inspections, and surveillances.

(d) Availability of contractor's quality assurance records for TVA review / approval (e.g. , qualification of personnel) ace transfer to TVA for retention (e.g. , material test reports).

(e) Lefinitive acceptance criteria to be used in e."aluating acceptability of the services provided.

3.0 Assignment of Procurement Levels The purchase requisition preparer shall assign a procurement level for services being procured. Appropriate quality assurance requirements shall

hen be imposed based on the level assigned. These levels shall be one of the following: ,
  • Revision g 7./ v HSP o nlw

Pcg2 2 -

3 Part III Sec. 2.lA N-0QAM l Revised .

E 8/2/78 (a) Level IS--Level IS shall be assigned to services which affect the integrity of the reactor coolant pressure boundary. Procurement documents for such services shall contain or reference detailed specifications. Contractors providing such services shall be

  • required to provide and maintain a quality assurance program which addresses the pertinent elements of 10 CFR 50, Appendix B. The contractor's work shall be performed in accordance with detailed procedures which shall be approved by TVA prior to performance of the work. Only qualif,ied contractors (see paragraph 4.0) may be used to provide services which have been assigned level IS.

(b) Level IIS--Level IIS shall be assigned to CSSC-related services which will not affect the reactor coolant pressure boundary and cannot be subsequently verified by inspection or tests. Such services may be procured only from qualified contractors. The ,

contractor may be required to maintain a quality assurance program depending on the complexity and importance to safety of the services .

being provided.

(c) Level IIIS--Services may be assigned level IIIS if they are CSSC-related but do not involve the reactor coolant pressure boundary and if they are relatively simple, standardized services (such as machining a shaft) which may be adequately verified through acceptance inspections, tests, or reviews. Only services which have been evaluated and '

specifically permitted in advance may be assigned this level. '

Generally, special quality assurance requirements are not required for level IIIS services. No special investigations of the contractor's qualifications shall be required for level IIIS services. E g

(d) Level IVS--Level IVS shall be assigned to services which are related to the CSSC but which are deemed to have no safety-related implications.

This level shall require no special quality assurance requirements. l E

  • 4.0 Qualification of Prospective Contractors ~

Services assigned levels IS and IIS may be bought only from contractors -

whose qualifications have been evaluated and approved by the P PROD Quality Assurance Staff. This evaluation shall be based on the same kinds of informatior as described in DPM No. N76A10, Appendix 5, with one xception. This exception is that suppliers of level IIS services m..y be qualified based solely on TVA's or other users" past experiences with tre contractor. When this input is used, information concerning the source of the input and specific comments about the contractor's past performance shall be documented.

SUBMITTED h _ APPROVED ,

Chief / Nuclear Generation Branch Director of Power Production i

% Revision I

~

Page 1 Part III Sec. 2. 2 N-0QAM Revised 4/18/79 TENNESSEE VALLEY AUTHORITY OPERATIONAL QUALITY ASSURANCE MANUAL PART III, SECTION 2.2 E .

TITLE - RECEIPT INSPECTION, HANDLING, . AND STORACE OF MATERIALS , COMPONENTS.

AND SPARE PARTS SCOPE - The purpose of this procedure is to define the responsibility and to establish controls for receiving inspection, handling,,and storage of those materials, components, and spare parts procured for the critical structures, systems, and components (CSSC) identified in Appendix A of this manual. The controls described herein implement ANSI N45.2.2-1972 and are consistent with the scope of work to be -

performed and the importance of materials, components, and parts -

received, handled, and stored by P PROD for operation, maintenance, and modification of nuclear plants.

DEFINITIONS Item--For the purposes of this procedure, an item is considered as an " inventory item" and does not pertain to an " item" column of a purchase requisition. An item is any number of like units considered as one group or . int and having an identical purchase specification and/or part number. An item may be purchased, TVA fabricated, transferred from other TVA locations, or borrowed from other utilities.

PROCEDURE 1.0 Responsibility The Supervisor, Power Stores Unit, at the nuclear plant is responsil51e for the receipt inspection, handling, and storage of materials, components, I and spara parts purchased, borrowed from other utilities, transferred within TVA, or fabricated off site for use in the CSSC of nuclear plants. For techni-cal assistance in implementing the receipt, handling, and storage requirements, the appropriate section should be consulted.

The originator of the purchase request or his representative shall assist Power Stores in receipt inspection of materials assigned quality assurance Level I or Level II substituted items. He shall also specify any special handling or storage requirements applicable to materials, components, and spare parts.

The Supervisor, Plant Quality Assurance (QA) Staff, shall establish minimum qualification requirements for receipt inspectors and shall certify assigned personnel as aeeting these requirements.

For the administrative policy for storage of materials with natural aging a life, see DPM No. ,N7 7A2.

General Revision

P;g2 2 Part.III Sec. 2.2 N-0QAM Revised 4/18/79 2.0 Receipt Inspection 2.1 Shipping Damage Inspection--Preliminary visual inspection or examination shall be performed prior to unloading to determine if any damage occurred during shipping. Observations for unusual conditions shall include:

a. Fire--Charred paper, wood, or paint, indicating exposure to g fire or high temperature. W
b. Excessive Exposure--Weather-beaten, f rayed, rusted, or stained containers indicating prolonged exposure during transit.
c. En"ironmental Damage--Water or oil marks, damp conditions, dirty areas, or salt film (indicating exposure to sea water or winter road salt chemicals).
d. Tie-Down Failure--Shifted, broken, loose, or twisted shipping ties and worn material under ties, indicating improper blocking and tie down during shipment.
e. Rough Handling--Splintered, torn, or crushed containers indicating improper handling. Review of impact recording instrument readings.

2.2 Item Inspection--Unless the package marking prohibits unpacking or the package is designed for long-term unopened storage, the content of all shipments shall be visually inspected to verify that the specified packaging and shipping requirements have been maintained. When items are contained in transparent separate moisture-proof bags or envelopes, visual inspection without unpacking the contents is acceptable.

Documented statistical sampling methods may be used for like units considered as one group or lot and having an identical purchase speci-fication and/or part number. Care shall be taken to avoid contamina-tion of the items during inspection. The inspections shall be performed

~

in an area equivalent to the storage requirement for the item.

The originator of the purchase request or his representative shall _

l assist Power Stores in performing the following inspections, as appropriate, for Level I items or Level II substituted items:

a. Identification and Markings--All materials, components, and spare parts for the CSSC received by the Power Stores Unit shall be checked against the packing list or shipping ticket by part number, tags, stampings, markings, etc. Also, the part number, tags, stampings, or markings shall agree with the TVA purchase contract or work order authorizing procurement.
b. Protective Covers and Seals--Visual inspection to assure that covers and seals meet their intended function.
c. Coatings and Preservatives--Verification tb*t coatings and preservatives are applied in tecordance with specifications, a purchase contract, or manufacturer's instructions.

General Revision

Paga 3 Part III Sec. 2.2 E N-OQAM Revised 4/18/79

d. Inert Gas Blankg--Verification that the inert gas blanket pressure is within the acceptable limits.
e. Desiccant--Verification that the desiccant is nct saturated, as indicated through the use of humidity indicators.
f. Physical Damage--Visual inspection to assure that parts of items are not broken, cracked, missing, deformed, or misaligned and (when I practical) that rotating parts turn without binding. Accessible internal and external areas shall be free of detrimental gouges, dents, scratches, and burns.
g. Cleanness--Visual inspection to assure that accessible internal and external areas are within the specification requirements I for dirt, soil, mill scale, weld splatter, oil, grease, or stains. If inspection for cleanness was performed prior to sealing and shipping and inspection upon receipt indicates .

that there has been no penetration of the sealed boundary, then inspection for internal cleanness is optional.

h. Dimensions--Random visual inspection to assure that important E dimensions conform with drawings and specifications. Examples are: base plate mounting holes, overall external size, and configuration and orientation of parts.
i. k' eld Preparations--Random verification that weld preparations

, are in accordance with applicable drawings and specifications.

j. Lubricants and Oils--Verification of presence of proper lubricants and oils, if required, by either specification, purchase contracts, or manuf acturers' instructions.
k. Electrical Insulation--Performance of insulation resistance tests for rotating electrical equipment (e. g. , motors and generator.s),

control cable, and power cable to ensure conformance with speci-fications. (An acceptable alternative for cable is to impose administrative controls which assure that the cable will be testet at installation and prior to use.)

1. Special Inspections--k' hen receiving inspection in addition to that required above is required, the originator of the purchase

. request or designated representative shall prepare appropriate inspection instructions including acceptance criteria which shall be attached to the receipt inspection document package.

E Ceneral Revision u

E E

. 1 f, !

Pags 4 Part III Sec. 2.2 N-OQAM Revised 4/18/79 2.3 Verification of Certifications and Documentation--For Level I .

items or Level II substituted items, the originator of the purchase '

request or his representative shall assist Power Stores in review and verification of manufacturing documentation and material I certifications of physical properties as follows.

a. Manufacturing Documentation--Assurance that the item received was fabricated, tested, and inspected prior to shipment in accordance with applicable code, specification, purchase contract, and/or drawings. .
b. Physical Properties--Assurance that physical prope rties conform to the specified requirements and that chemical and physical test reports, if required, meet the requirements. I 1

2.4 Receipt Inspection Documentation--Attachment 1 shall be used to i perf orm and document the extent of the inspections performed in l paragraphs 2.1, 2.2, and 2. 3 above. However, it may be modified to  :

include additional requirements or procedures which are plant unique. I It is only necessary to fill out one copy of Attachment 1 for any P'.ven shipment. For example, the inspection of several items can be ,

documented on one form.

2.5 Acceptable Shipment--An acceptable shipment consists of: (1) the specified number of items as outlined on the bill of lading and (2) the completed receipt inspection including documentation as noted in paragraph 2.4 above.

A shipment may be accepted where approved shortage or substitutions have been made by the vendor. For replacement parts or components, where the originator of a purchase request or a designated representative can ascertain (by vendor certification or other means) that the replace-ment part or component is functionally equal to the original part or component, the replacement can be accepted for use based on recommenda-tions of the cognizant engineer and concurrence of the plant QA Staff.

2.6 Unacceptable Shipment--Delivery of materials, components, and spare -

parts pertaining to the CSSC that show apparent damage shall not be accepted until a thorough inspection reveals the condition of .

packaged materials, components, ar.d spare parts and appropriate notes filed with the common carrier. I Materials, components, and spare parts for the CSSC may be accepte'd based on the results of the inspection and the remaining requirements of this procedure.

Items shall not be placed in stock until receipt inspection has proved them to be acceptable. Materials, components, and spare parts for the CSSC considered to be defective or which do not have complete documen-tation shall be handled as nonconforming material in accordance with 00AM Part III, Section 7.1. An exception will be on fabricated fuel 4 and core components in which a Site Fuel Discrepancy Report will be '

initiated.

1 General Revision

Page 5 Part III Sec. 2.2 N-OQAM Revised 4/18/79 3.0 Handling 3.1 Routine Handling Requirements--Items shall be handled in accordance j

a with good handling practices to minimize damage and preserve the quality of the item a Ad container. General handling practices shall be established and as a minimum address the following.

a. Observe handling precautions upon receipt, as outlined on outer packaging of materials received.
b. Avoid unnecessary handling and protect any machined surfaces.
c. Refer to plant safety requirements concerning handling of chemicals or compressed gases and other potentially hazardous materials and observe precautions on labeling. j I ,
d. Avoid leaning, propping, or stacking materials or equipment in  ; ,

unstable configurations.

e. Avoid unnecessary handling of materials while in storage to minimize the possibility of damage or distortion.
f. Observe handling of materials with a known shelf life to such an extent that old stock is withdrawn first. Such items would E include but not de ti=ited to certain eiectronic co=9onents ^ad a rubber products, batteries, and paints.

g.' Rigging that is frayed, worn, or otherwise deteriorated shall not be used.

I

h. Equipment and rigging shall be kept clean and free of contaminants that are detrimental to the material being handled.
i. Rigging items such as hooks, shackles, and turnbuckles that ,

appear to have yielded or are distorted shall not be used.

j. Hoisting equipment shall not be loaded beyond its rated load -

except for test purposes.

k. Carbon steel rigging equipment shall not come in direct contact with stainless steel except when attached to lif ting lugs, eyes, or pads in order to avoid surface damage.
1. All austenitic stainless steel and nickel base alloy materials shall be handled in such a manner that they are not in contact with lead, zinc, copper, mercury, or other low-melting-point I alloys or halogenated material.
m. Any defective, contaminated, or overloaded hoisting equipment shall be segregated and shall not be used.

C Ceneral Revision

P(g3 6 Prrt III Sec. 2. 2 N-OQAM Revised -

l M

4/18/79  ;

3.2 Special Handling Requirements--Detailed handling instructions l and procedures shall be prepared for all items that require E special handling instructions because of weight, size, suscep-tibility to shock damage, hign nil ductility transition temperatures, or any other conditions that warrant special instructions. Such instructions or procedures shall be made available prior to the time the item is to be handled and shall give weights, sling locations, balance points, methods of sttachment, maximum hoist line speeds and other pertinent features to be considered as necessary for safe handling.

As a matter of routine the vendor normally specifies the need for any applicable special handling procedures or requirements.

However, the originator of the purchase request shall evaluate the need for and specify, as applicable, any additional special l handling procedures or requirements at the time of receipt W inspection for Level I items. These procedures and requirements shall identify, as applicable, the need for special visual and nondestructive examinations and dynamic load tests for equipment and rigging such as cranes, forklifts, and cables. The results of special tests and inspections shall be documented.

4.0 Storage 4.1 Storage Faciliev--The facility in which CSSC items are stored shall be maintained so that stored items are not subject to damage or deterioration. The following controls shall be imposed as a minimum: ,

a. The temperature in the permanent storage facility shall be main-tained between 40 F and 140 F.
b. Items which are not sensitive to environmental conditions may be l stored outdoors or in temporary storage facilities. ,
c. Access to the storage area shall be controlled and limited to designated personnel. -

l

d. The storage area shc11 be cleaned as required to avoid the g accumulation of trash, discarded packaging materials, and other detrimental soil, Ei
e. Food and drink may not be used or stored in storage facilities' except in designated areas.
f. Rodents shall be controlled by examining packages at receiving inspection and by periodically surveying the storage area. l If these surveys indicate rodent infestation, an eradication '

program shall be implemented expeditiously.

4.2 Packaging and Storage Environment--The Power Stores Unit shall detern.hac the adequacy of and provide packaging of materials, 8 components, and spare parts for storage. Storage conditions shall be adequate to ninimize the possibility of damage or lowering of quality due to corrosion, contamination, deterioration, or General Revision

Paga 7 Part III Sec. 2.2 E N-0QAM Revised 4/18/79 physical damage while an item is in storage.

During receipt inspection the originator of the purchase reon+1t or his representative shall identify those Level I items that require a special protective environment. or care during storage to prevent deterioration. Power Stores shall identify those Level II, III, and IV items that require a special protective environment or care; however, technical assistance shall be I provided by the originator of the purchase request or his represen-tative, if required. As,a minimum the following shall be considered.

a. Caps and plugs shall be used to seal openings in items having sensitive internal sarfaces and to protect threads and weld end preparations.

Covers removed for internal access at any time for any reason .

shall be immediately replaced and resealed after completion of the purpose for removal.

b. Temporary preservatives shall be left intact curing storage.

Should reapplication of preservatives be required at the site, only those previously approved shall be used.

c. Items pressurized with inert gas shall be monitored at .ch a frequency as to ensure that the gas pressure is maintait ed within specified limits during storage. Desiccant humidity indicators shall also be monitored and desiccants shall be changed or reprocessed when specified.
d. Instrumentation racks shall be energized as specified by the manufacturer.

Space heaters enclosed in electrical items shall be energized as specified by the manufacturer.

e. Rotating electrical equipment shall be given insulation resistance E tests when required by special storage procedures. _

g f. The shaf ts of rotating equipment shall be rotated on a periodic g basis. The degree of turn shall be established so that the parts receive a coating of lubrication where applicable and so that the shaf t does r.ot corre to rest in the previous pssition.

(90 deg. and 450 deg. rotations are examples.) -

g. Desiccants shall be r2 generated or replaced as necessary in accordance with the mar.ufacturers' suggestions or special plant I instructions.
h. Other maintenance requirements specified by the manufacturer's instruction for the item shall be performed.

Special requirements for protective environment or care during ,

storage shall be documented on Attachment 1 (items V and VI) as applicable. The Power Stores Unit shall be responsible for 1 I

implementing these requirements.

I 1

E Ceneral Revision L

r.

Pc32 8 Part 111 Sec. 2.2 N-0QAM Revised '

4/18/79 4.3 Insect, Rodent, and Animal Control--Prior to placing materials, components, and spare parts in storage, packages and crates shall be inspected for insect, rodent, and animal infestation.

Care shall be exercised to prevent the entrance of rodents, insects, or other animals into storage areas or equipment to minimize possible contamination and mechanical damage to stored materials.

4.4 Storage Methods--Storage methods shall comply with the following requirements.

a. Ready Accesr to Stored Items--All items shall be stored in such a manner as to permit ready access for inspection or maintenance without excessive handling to minimize risk of damage.
b. Arrangement of Items--Items stacked for storage shall be E' I arranged so that racks, cribbing, or crates are bearing the -

f ull weight without distortion of the item.

c. Storage of Ha zardous Material--Hazardous chemicals, paints ,

solvents, and other materials of a like nature shall be stored in well-ventilated areas which are not in close proximity to important nuclear plant it e ms .

d. Coverings- 'Jeatherproof covering, when used for long-term outdoor storage, shall be a flame-resistant type of sheeting or tarpaulins. They shall be placed so as to provide drainage and to ensure air circulation to minimize condensation. They shall be tied down to prevent moisture from entering laps and l co protect the coverings from wind damage. M
e. Identification for Storaae--The Power Stores Unit shall establish an identification system whereby the association <

between any CSSC material, component, or spare part and its ,

quality assurance documentation is maintained. As a minimum, this system shall include the MAMS TVA Item Identification Code (TIIC); the receipt date (for QA Level I and II items); and -

applicable manufacturer's heat, lot, or individual serial number. All items or their containers shall be plainly marked in a manner which is not deleterious to the item and so that j they are easily identified without excessive handling or l unnecessary opening of crates and boxes. Tags or other identifying I media shall be of material which will retain the marking, withstand weathering deterioration, and other normal storage and handline effects.

4.5 Storage Outside the Permanent Storage Facility--Items which are not I sensitive to environmental conditions may be stored in temporary storage f acilities such as Butler buildings or outdoors. Outdoor storage areas shall be marked and designated for storage, well drained, and gravel covered or paved. Items stored outdoors shall be placed ,

on cribbing or equivalent to allow air circulation and to avoid t rapping water.

l General Revision

Page 9 Pa rt III Sec. 2.2 E '

N-OQAM Revised 4/18/79 4.6 Control of Nonconforming Items - Tagging--Nonconforming materials, parts, or components shall be controlled and tagged in accordance with requirements of Part III, Section 7.1, of this manual.

5.0 Survevs Periodic surveys of the materials, parts, or components storage facilities shall be performed by the plant QA Staff to verify that the requirements I of paragraphs 4.1, 4.2, 4. 3, and 4.4 are being effectively implemented.

The plant QA Staff shall ensure that proper documentation accompanies safety-related materials, parts, and components by surveillance of receipt activities and do,umentation of the Power Stores Unit.

The results of surveys performed by the plant QA Staff shall be documented. ,

SUBMITTED , APPROVED <

Chief. uclear Generation Branch DirptorofPowerProduction E At taciimen t : 4-/r-79 Materials Receipt Inspection Report E

E E General Revision ,

E .

E I

E .

9 Peg? 10 Part III Sec. 2. 2 Pr0QAM Revised E

M 4/18/79 ATTACHMENT 1 MATERIALS RECEIPT INSPECTION REPORT Date Contract No.

Other Procurement Document No. Item No.

Ce rtif ying Document No. ,

Environmental Control Required for Delivery? Yes No Receipt Inspection I. Visual Inspection for Shipping Damage (prior to unloading)

a. Fire or high temperature Yes No
b. Excessive exposure Yes No
c. Environmental damage (water, oil, dirt, sea water, road salt, etc.) Yes No
d. Container tie-down failure Yes No
e. Rough handling Yes No
f. Other - Define Yes No
g. If sections a through I were answered with a "yes," did it have an adverse effect on the subject material? Yes No Define II. Item Inspection Unless the package or other logic prohibits, each item shall be individually inspected. When items are contained in trans-parent separate envelopes o'r bags, inspection may be perf orted -

without unpacking the item. Documented statistical sampling methods may be used for like units considered as one group or -

lot and having an identical purchase specification sad /or part number.

ARE THE 70LLOWING CONDITIONS ACCEPTABLE?

a. Markings and Identification Yes No
b. Protective Covers and Seals Yes No N/A
c. Coatings and Preservatives Yes No N/A
d. Inert Gas Blanket Yes No N/A
e. Desiccant Yes No N/A
f. Physical Damage Yes No
g. Cleanness Yes No N/A
h. Dimensions - Define Yes No N/A
1. Weld Preparations (random verification) Yes No N/A
j. Lubricants and Oils Yes No N/A
k. Electrical Insulation - Define Yes No N/A Jeneral Revision

,*1 Page 11 Part III Sec. 2. 2 i E N-OQAM Revised 4/18/79 ATTACHMENT 1 (continued)

1. Special Inspections? Define Yes No N/A
m. If sections a through I were answered with E a "no," did it have an adverse effect on the subject material? Define Yes No N/A III. Verification of Documentation Requirements
a. Does material conform to purchase documents? Yes No Exceptions _-
b. Do material certifications conform to Yes No N/A purchase documents and applicable speci-E fications? Exceptions
c. Other documentation requirements? Yes No N/A Define l

j IV. Packages are free of insects, rodents, or M animals? Yes No V. Special handling requirements apply? Yes No I Define -

l VI. Special protective environment or care during B storage is required? Yes No Define ,

I E l I

Ceneral Revision

,P1go 12 E W

Part III Sec. 2.2 N-OQAM g

Revised 4/18/79 E,

l 1

ATTACliMLNT 1 (continued)  !

APPROVAL / DISAPPROVAL l

Receipt Inspection (Approval) Item Nos. l (Disapproval) Item Nos.  !

For Receipt of Level I, II, III, and IV (Circle one) Items.

- 1

/ / / l Receiving Clerk Date Originator of Purchase Date Supervisor, Date Request or his repres.

(Level I and II substi-Power Stores or his rep.

S E

tute items only) N l NCI Tag No.

Shipping Ticket No. , If Required B

l E 1 E l

General Revision

I.

Page 1 I Part III Sec. 2.3 N-0QAM Revised 10/25/78 TENNESSEE VALLEY AUTHORITY OPERATIONAL QUALITY ASSURANCE MANUAT T PART III, SECTION 2.3 TITLE - ISSUING OF MATERIALS, COMPONENTS, AND SPARE PARTS I SCOPE - The purpose of this procedure is to define the responsibility and to establish controls in the issuing of materials, components, and spare parts for the CSSC for TVA's nuclear plants as identified in Appendix A, Part I, of this manual.

PROCEDURE .

I*

1.0 Responsibility The Power Stores Unit supervisor is responsible for the issue of materials, components, and spare parts for use in the CSSC of the nuclear plants and I for the transfer of materials, components, and spare parts to other locations within or external to TVA.

  • 2.0 Issue of Materials, Components, and Spare Parts for In-Plant Use

~

The Power Stores Unit supervisor shall establish methods to ensure that the issue of all materials, components, and spare parts for use in the I CSSC is properly documented, the storeroom inventory updated, and re-quisitions initiated for replacement spares if necessary. These methods shall inclu.ie recording the MAMS TVA Item Identification Code (TIIC);

applicable manufacturer's heat, lot, or individual serial number on I the 575 form. For QA Level I and II items, the receipt date shall also be included.

The requisitioning supervisor shall be responsible for specifying on P the 575 form the applicable work authorization document--i.e., maintenanc,e request number, maintenance instruction number, etc.- for which the item or part is requisitioned. Items or materials which are requested for general plant uce such as welding materials or hook-up wire shall stats "For General Plant Use" on the 575 form. Materials which are issued for general plant use shall be controlled, installed, and traceability maintained in accordance with established plant procedures.

Power storeroom personnel shall be re.4ponsible for verifying that the appropriate information is included on the 575 form prior to issuing the requested materials or items.

It is the responsibility of the user of the materials, components, or spare parts to verify correct identity before installation.

f

  • Revision b h 0

9 P:tg2 2

"'Ptrt 111 Sec. 2.3 N-0QAM Revised 10/25/78 3.0 Transfer of Materials, Components, and Spare Parts The Power Stores Unit supervisor shall set up procedures to transfer materials, components, or spare parts and establish packaging requirements for shipments to other locations within or external to TVA. These pro-cedures shall ensure that the transfers are properly documented, including proper accounting, and that the storeroom inventory is updated and re-

~

quisitions initiated for replacement spares if necessary. All quality assurance documents, or certified copies of the documents associated with /

the materials, components, or spare parts shall be transferred with the items.

The plant superintendent shall authorize the transfer of all material, 'g components, or spare parts.

4.0 Retention of Documents It shall be the responsibility of the plant Power Stores Unit to maintain all documentaticn obtained in the procurement of materials, components, l' 9

and spare parts throughout their service life. Documentation concerned with installaticn and service life shall be maintained by the appropriate plant section.

1 SUBMITTED -

@'l h APPROVED ./

Director of Power Production cge,sueleaVce46rationBranch I

~

I

~L q

l I

I I

.