ML19319B500
| ML19319B500 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 10/10/1975 |
| From: | Fiorelli G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Roe L TOLEDO EDISON CO. |
| Shared Package | |
| ML19319B452 | List: |
| References | |
| NUDOCS 8001220912 | |
| Download: ML19319B500 (2) | |
See also: IR 05000346/1975017
Text
- - -
- -
-.- -
-
. _ -
.
.
.
.
O
-
"
.
. py%
,
,
- .
,
.
.
.
.- 'e
'
i
UNITED STATES
'
i
NUCLEAR REGULATORY COMMISSION
'
REGION lli
i
GLEN ELLYN, ILLINOIS 60137
OCT 10 1975
Toledo Edison Company
Docket No. 50-346
ATTN: Mr. Lowell Roe
Vice President, Power
.
Edison Plaza
300 Madison Avenue
Toledo, Ohio
43652
.
Gentlement
This refers to the inspection conducted by Messrs. R. Martin
and R. Knop of this office on September 9,10,11, and 23,
1975, of activities at Davis-Besse Unit 1 Construction Site
authorized by NRC Construction Permit No. CPPR-80 and to the
discussion of our findings with Mr. J. Evans and others of
your st2ff at the conclusion of the inspection.
A copy of our report of this inspection is enclosed and identi-
fios the areas
====4n=d during the inspection. Within these
areas, the inspection consisted of a selective er==4 nation of
procedt.res and representative records, interviews with plant
personnel, and observations by the inspectors.
During this inspection, it was found that certain of your
activities appear to be in noncompliance with NRC requirements.
The items and reference to the pertinent requirements are
listed under Enforcement Action in the Summary of Findings
section of the enclosed inspection report.
This notice is sent to you pursuant to the provisions of
Section 2.201 of the NRC's " Rules of Practice," Part 2
Title 10, Code of Federal Regulations. Section 2.201 requires
you to submit to this office within twenty days of your
receipt of this notice, a written statement or explanation
in reply, 4=a1=d4=g:
(1) corrective steps which have been
taken by you, and the results achieved; (2) corrective steps
which will be taken to avoid further items of noncompliance;
and (3) the date when full compliance will be achieved.
l
8001eso9/2
..
-
-.
.
--
_
-
.
.
..
.
.
.
.
,
.
.
-
,
'
.-
'
.
-
.
OCT 10 1975
Toledo Edison Company
-2-
Prior to the conclusion of the inspection, the inspectors
determined that corrective action had been taken with respect
to item of noncompliance B and that measures have been taken
with respect to this item of noncompliance to assure that a
similar, future noncompliance will be avoided. Consequently,
your reply need not address that specific item, and we have
.
no further questions regarding that item of noncompliance at
j
this tian.
Certain other activities identified during this inspection
appear to be deviations from conunitments which you have made
in previous correspondence with the Commission. The items
are identified under other Significant Findings in the
Summaary of Findings section of the enclosed inspection report.
-
Please advise us in writing within twenty days of the cor-
-
rective action you have taken or plan to taka, showing the
estimated date of completion, with regard to these deviations.
In. accordance with Section 2.790 of the NRC's " Rules of
Practice," Part 2, Title 10, Code of Federal Regulations, a
copy of this notice, the enclosed inspection report, and your
response to this notice will be placed in the NRC's Public
Document Room. If this report contains any information that
you or your contractors believe to be proprietary, it is
necessary that you make a written application to this office,
within twenty days of your receipt of this notice, to with-
hold such information from public disclosure. Any such
application must include a full statement of the reasons for
which it is claimad that the information is proprietary, and
should be prepared so the proprietary information identified
'
in the application is contained in a separate part of the
document. Unless we receive an application to withhold in-
'
formation or are otherwise contacted within the specified
time period, the written material identified in this para-
graph will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we
will be glad to discuss them with you.
Sincerely yours,
Gaston Fiore111, Chisf
Reactor Operations Branch
i
Encloss*rst
bec w/ encl:
j
IE Int..tetion Report
No. u50-346/75-17
Local PDR
'
U. Young Park, Nuclear
Engineer