ML19317G173
| ML19317G173 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 06/26/1978 |
| From: | Long F NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Stewart W FLORIDA POWER CORP. |
| Shared Package | |
| ML19317G174 | List: |
| References | |
| NUDOCS 8002280805 | |
| Download: ML19317G173 (2) | |
See also: IR 05000302/1978015
Text
-
.-
,
.
, ..
.
.
. - . . . . . . .
'
q
'
.
f<T
(p >" "8G 9[o,,
t
0
UNITED STATES
NUCLEAR REGULATORY COMMISSION
,,
REGloN ll
(
{g *g
g
e
- ,
aE
230 PEACHTREE STREET, N.W. sulTE 1217
gp g
ATLANTA, GEORGIA 30303
.
JUN t 6 W78
In Reply Refer To:
~
j
N[@
RII:PTB
50-302/78-15
.=
.
Florida Power Ccrporation
Attn:
Mr. W. P. Stewart, Director
Power Production
P. O. Box 14042, Mail Stop C-4
St. Petersburg, Florida
33733
Gentlemen:
This refers to the inspection conducted by Mr. P. T. Burnett of this office
on May 22-26, 1978, of activities authorized by NRC License No. DPR-72 for
the Crystal River Unit 3 facility, and to the discussion of our findings
held with Mr. G. P. Beatty at the conclusion of the inspection.
'j
Areas examined during the inspection and our findings are discussed in the
H
'
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews
with personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were
disclosed.
One new unresolved item resulted from this inspection and is discussed in
the enclosed report.
This item will be examined during subsequent
'
inspections.
In the course of the exit interview plant management made a commitment to
add the missile shield crane to the preventive maintenance program for
cranes. Management also made the commitment to review ANSI B30.2.0-1976 for
applicability to all cranes engaged in handling radioactive material or in
'
carrying loads over fuel. ANSI B30.2-1976 is a safety standard for overhead
traveling cranes. The results of the review will be discussed with plant
management during a forthcoming inspection.
l
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations, a copy of this' letter and the
enclosed inspection report will be placed in the NRC's Public Document Room.
If this report contains any information that you (or your contractor)
O)
believe to be proprietary, it is necessary that you make a written
(
application within 20 days to this office to withhold
v
8 0 02 280 DS
P
.
~-
..
-- ..
~
.
_.
.
/
<
Florida Power Corporation
-2-
JUN 2 6 EUB
such information from public disclosure.
Any such application must
include a full statement of the reasons on the basis of which it is
claimed that the information is proprietary, and should be prepared
-
so that prcprietary information identified in the application is
contained in a separate part of the document.
If we do not hear
from yoG in this regard within the specified period, the report
will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
3
,
_
s
(3a-
-
F. J. Long, Chief
Reactor Operations and
Nuclear Support Branch
Enclosure:
Inspection Report No. 50-302/78-15
.
cc w/ encl:
Mr. G. P. Beatty, Jr.
<
Nuclear Plant Superintendent
P. O. Box 1228
Crystal River, Florida
32629
.
%