Responds to NRC Re Violations Noted in IE Insp Rept 50-302/77-17.Corrective Actions:Compliance Engineer Instructed to Assure ROs Reported to Region 2 Immediately Upon Learning of Occurences.No Proprietary Info
ML19317G163
Person / Time
Site: Crystal River 
Issue date: 11/15/1977
From: Stewart W
FLORIDA POWER CORP.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19317G158 List:
References
CS-77-249, NUDOCS 8002280753
Download: ML19317G163 (2)


Text

.

Dh Q::.%

~

[Gfp p(R%9 m.

~' rt i PR L -

UA Q' [Q e

Florida 15 November 1977 ggg 3-0-3-a-2 c a.,o. u.a.

CS-77-249 Mr. J. P. O'Reilly, Director Docket No. 50-302 Office of Inspection & Enforcement License No. DPR-72 U.S. Nuclear Regulatory Commission Ref:

RII:RHW 230 Peachtree St. N.W., Suite 818 50-302/77-17 Atlanta, GA 30303

Dear Mr. O'Reilly:

We offer the following in response to the two deficiencies noted in the referenced Inspection Report.

h A.

The late 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> report resulted from a misunderstanding

\\

as to who was to call in the report to Region II.

Sub-sequent to this occurrence the Compliance Engineer has been charged by the Nuclear Plant Manager to, either assure that a call has been made to Region II or to make the telephone report himself. He shall do this immediately upon becoming apprized of such an occurrence. 'Ihis will preclude further lapses of this type. This action has been completed as of this date.

B.

As noted in Licensee Event Report 77-ll6E, calculations were made and it was determined from them that the release rate represented.005% of the maximum allowable instantaneous release rate; therefore, no further action was required with regard to this event.

Corrective steps have been taken to avoid further noncom-pliances. - We have installed interlocks which will terminate the gaseous release upon failure of gaseous monitoring sample systems. This modification was completed on 25 October 1977.

Also, all Operations personnel have been instructed by written memorandum to review and comply with all abnormal procedural requirements.

The above actions were completed as of 25 October 1977.

O 8002280 7 8 )

General Office 3201 Tnerty fourin s:reet soutn. P O Ocx 14042. St Petersburg. Dornu 337 E N /St.E SLS L-4 u.c d

. _. }1r *

,3 Mr. J. P. O'Reilly Ref: RII:RHW 50-302/77-17 2

Page 2 If there are further questions on this response, please contact us.

We find.no proprietary information in the referenced Inspection Report.

l Very truly ycurs,

.bD j-W. P. Stewart Director, Power Production IMP /rc

/1#

pre / Nuclear Plant Manager