Monthly Operating Rept for Feb 1977
ML19317E593
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 03/10/1977
From: Bare L
DUKE POWER CO.
To:
Shared Package
ML19317E588 List:
References
NUDOCS 7912180796
Download: ML19317E593 (3)


Text

_ _ _ _ _ _ _ _ _

f)

U UNd Oconen Unit 2' DATE 3/10/77 DOCKET NO. 50-270 PREPARED BY L. J. Bare OPERATING STATUS

1. REPORTING PERIOD: February 1 THROUGH February 28. 1977 GROSS HOURS IN REPORTING PERIOD: 672.00
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2568 NET CAPABILITY (MWe-Net): 860
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY):(MWe-Net)
4. REASONS FOR RESTRICTION (IF ANY)

This Month Year to Date Cumulative

5. NUMBER OF HOURS THE REACTOR WAS CRITICAL 672.0 1416.0 15643.0
6. REACTOR RESERVE SHUTDOWN HOURS
7. HOURS GENERATOR ON-LINE 672.0 1416.0 15181.5
8. - -

UNIT RESERVE SHUTDOWN HOURS

9. GROSS THERMAL ENERGY GENERATED (MWH)1718647 3634968 36396230
10. GROSS ELECTRICAL ENERGY GENERATED 583750 1236740 12392346 (MWH)
11. NET ELECTRICAL ENERGY GENERATED 559817 1186177 11770300 (mm)
12. REACTOR SERVICE FACTOR 100.0 100.0 72.10
13. REACTOR AVAILABILITY FACTOR 100.0 100.0 70.46
14. UNIT SERVICE FACTOR 100.0 100.0 69.97
15. UNIT AVAILABILITY FACTOR 100.0 100.0 69.97
16. UNIT CAPACITY FACTOR (Using Net 96.87 97.41 63.08 Capability)
17. UNIT CAPACITY FACTOR (Using Design Mwe) 93.92 94.44 61.16
18. UNIT FORCED OUTAGE RATE O O 23.6
19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE & DURATION OF EACH:)

Refueling - July 17, 1977 - 6 weeks

20. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

REACTOR SERVICE FACTOR = HOURS EEACTOR WAS CRTTICAL X 100 110VRS IN REPORTING PERIOD REACTOR AVAILABIL11Y TACTOR = HOUitS REACT 0n L'AS AVAILABLE TO OPERATE Il0URS IN REPORTING PERIOD

-UNIT SERVICE TACTO:; ^= H0lfrS GEEERATOR ON LINE yg3 HOURS IN REPORTING PERIOD INIT AVAILABILITY FACTOR = 110URS ITNTT WAS AVA11 ADLE TO Gr*:ERATE X 10U HOURS IN REPohTING PERIOD UNIT CAPACITY FACTOR = NET ELECTRICAL POWER GENERATED

[ t C pability or Design ( 15 REPUA.T' L.

p) . I U UNIT FORCED OUTACE RATE e FOP.CED OUTAGE HOURS X 00 HOURS CENEPaTOR ON 1.INE + TORCED OUTAGE HOURS

DOCKET NO. 50-270 UNIT oconee Unit 2 DATE 3/10/77 AVERAGE DAILY UNIT POWER LEVEL MONTH February, 1977 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net) DAY (MWe-net) 842 830 1 17 841 832 2 18 3 838 gg 832 841 833 4 20 5 840 21 832 832 6 22 7 829 23 832 834 '

8 24 9 836 25 832 832 10 26 11 831 27 835 831 834 12 28 13 825 29 14 30 15 832 31 833 16 DAILY UNrr POWER LEVEL FORM INSTRUCTIONS On this form, list the average daily unit power level in MWe-net for each day m the reporting month.

Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that by using maximum dependable capacity I'or the net electrical rating of the unit. there may be in easions when the daily average power level exceeds the IUO's line (or the restricted power lesel kne). In such c.ises, the average daily unit power output shee: should be footnoted to explain 'he apparent anomaly.

D CKET NO. 50-270 Oconee Unit 2 UNIT SPUTDOWNS UNIT NAMli

. DKi l;. 3/10/77 REPORT MONTil February, 1977 TYPE METHOD OF F FORCED DURATION SHUTTING DOWN NO. DATE S SCHEDULED (HOURS) REASON (O THE REACTOR (2) CORRECTIVE ACTIONS / COMMENTS (1) REASON (2) METilOD A EQUIPMENT F AILURE (EXPLAIN) 1-MAI9AL B- MAINT. OR TEST. 2-MANUAL j C- REl'UELING SCR AM D-REGULAIORY RESTRICTION 3 - A UT OM A TIC ,

E-OPERATOR TRAINING AND SCR AM LICENSE EXAMIN A110N 4-Other F- ADMINIST R ATIVE G- OPE R AllON AL ERROR (EXPLAIN) li-0TilLR lt % PLAIN)

SUMMARY

No outages this month.