ML19312E693

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-460/80-04 & 50-513/80-04 on 800301-31 & Notice of Deviation
ML19312E693
Person / Time
Site: Washington Public Power Supply System
Issue date: 04/15/1980
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Strand N
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML19312E684 List:
References
NUDOCS 8006090409
Download: ML19312E693 (2)


See also: IR 05000460/1980004

Text

._

m-

4 9DK.

- .v ,f. m,

UNITED STATES

"

! \\*

NUCLEAR REGULATORY COMMISSION

o

$ /-

.$

REGION V

o,

1990 N. CALIFORNI A BOULEVARD

% ,,,,

SUITE 202, WALNUT CREEK PLAZA

WALNUT CREEK, CALIFORNI A 94596

APR 151980

Docket Nos. 50-460

--

..

h

'^ ~ -

! [p

50-513

,-

L I v..~. v&, 7,ij&,

,

Washington Public Power Supply System

P. O. Box 968

Richland, Washington 99352

Attention: Mr. N. O. Strand

Managing Director

Gentelmen:

Subject: NRC Inspection at Washington Nuclear Projects 1 and 4

This refers to the inspection conducted by Mr. A. Toth of this office

during the period of March 1-31, 1980 of activities authorized by NRC

Construction Permit Nos. CPPR-134 and -174, and to the discussion of

our findings held by Mr. Toth with Mr. T. Houchins and other members of

your staff on March 10, 24 and 31, 1980.

Areas examined during this inspection are described in the enclosed

!

inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records,

interviews with personnel, and observations by the inspector.

Based on the results of this inspection, it appears that one of your

activities deviated from one of your commitments in the Preliminary Safety

Analysis Report, as set forth in the Notice of Deviation, enclosed herewith

as Appendix A.

Your written response to this letter should address the

corrective actions taken with respect to this deviation concerning the

specification of weld filler metal used in reactor coolant pressure

boundary pipe welds.

Your response should be submitted to this office

within thirty (30) days of your receipt of this Notice.

,

In accordance with Section 2.790 of the NRC's " Rules if Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room.

If this report contains any infonnation that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within thirty (30) days of the date of this letter,

,3 3006090V01

.. _-

_-

'

.. .-

.

.

.

.

f

APR 15 EGO

N. O. Strand

-2-

i

requesting that such information be withheld from public disclosure.

The application must include a full statement of the reasons why it is

claimed that the information is proprietary. The application should be

prepared so that any proprietary information identified is contained in

!

an enclosure to the application, since the application without the enclosure

will also be placed in the Public Document Room.

If we do not hear from

you in this regard within the specified period, the report will be placed

in the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

f

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

E.nclosures:

A.

Notice of Deviation

B.

IE Inspection Report

Nos. 50-460/80-04

50-513/80-04

cc w/o enclosure 8:

M. E. Witherspoon, Division Manager

Quality Assurance, WPPSS

J. P. Thomas, Project Manager, WPPSS

l

1

4

I

-

r

-

,