ML19312C381

From kanterella
Jump to navigation Jump to search
Requests Extension of Provisional CPPR-33 Completion Date from 710228 to 710930
ML19312C381
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 02/19/1971
From: Willie Lee
DUKE POWER CO.
To: Morris P
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML19312C377 List:
References
NUDOCS 7912130908
Download: ML19312C381 (1)


Text

~

^

d Dunn Pownn GourAxv Pownn Burr.nssa. Box c170. GnAntorTu.N. G. cono O

s/

+

't /

..u..... c

- s

' 9,, s.9,

i, 7 c....m............

j

Q :'

\\

/

.%;,. '.,' K 9

R/

February 19, 1971

.. v i,{

- 1 Dr Peter A Morris, Director Division of Reactor Licensing Atomic Energy Commission

~

Washington, D C 20545 Re:

Oconee Nuclear Station - Unit 1 Docket lio 50-269 Provisional Construction Permit No CPPR-33

Dear Dr Morris:

We herewith apply for an extension of time for completion of Oconce Unit I as covered by Provisional Construction Permit No CPPR-33.

That permit calls for completion of the f acility by February 28, 1971. We have been delayed in completing the facility, principally because of late delivery of reactor systua components fran the supplier.

The original schedule specified jobsite delivery of major reactor system components by May 1,1969 Due to strikes and other difficut ties in the manuf acturer's shops, the reactor vessel did not arrive until February 6,1970, and other major reactor system components were also substantially late.

Further, af ter field assembly of the primary system, it was then necessary to remove pump casings and connecting piping for the substitution of different pumps. Some of the time lost by these events has been made up during construction, but the balance of tirre lost is reficcted in late completion of the f acility.

We ask for an extension of time to September 30, 1971, and please construe this letter as an " Application for Renewal of Construction Permit."

Your s very truly,

/s/ W S Lee W S Lee I

WSL/s