ML19309D605

From kanterella
Jump to navigation Jump to search
Ack Receipt of Requesting Extension of IE Bulletin 79-01B Data Submittal Date.Requests 24-h Notification of Any Deviation from Understanding That Response to Items 1,2, & 3 Will Be Submitted by 800317
ML19309D605
Person / Time
Site: Pilgrim
Issue date: 03/14/1980
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Andognini G
BOSTON EDISON CO.
References
IEB-79-01B, IEB-79-1B, NUDOCS 8004110008
Download: ML19309D605 (1)


Text

Ib UNITED STATES

/

NUCLEAR REGULATORY CoMMisslON

[

REGION I

),g g j '

'f MING OF PRUS$1 A, PENN5YLV ANIA 19406 g

631 PARK AVENUE

  1. \\,,.. /

MM i 4 ISy Docket tio. 50-293 Boston Edison Company M/C Nuclear ATTN: Mr. G. Carl Andognini, Manager Nuclear Operations Department 800 Boylston Street Boston, Massachusetts 02199 Gentlemen:

NRC review of your letter dated March 4,1980, from fir. G. Carl Andognini, re-questing an extension of the 79-01B data submittal date has been completed.

It is our understanding that the following will be accomplished:

a.79-01B, Items 1, 2 and 3: The 45 day response, due on the above items will be submitted by March 17, 1980.

If our understanding of your planned actions described above is not in accordance with your actual plans and actions being implemented, please contact this office by telephone and in writing within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of receipt of this letter.

Sincerely, L

o Boyce H. Grier

" Director cc:

P. J. McGuire, Pilgrim Station Manager 8004110 0 0 3