Forwards IE Insp Rept 50-302/78-01 on 780103-06 & Notice of Violation
ML19308D540
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/27/1978
From: Sutherland W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Stewart W
FLORIDA POWER CORP.
Shared Package
ML19308D530 List:
References
NUDOCS 8002280975
Download: ML19308D540 (2)


See also: IR 05000302/1978001

Text

A

'*,

,

_

- .

.- .

-

f.

-

lE FILE COPY

.

.) ,

  1. p *" "' 4 ,'o,

t

UNITED STATES

NUCLEAR REGULATORY COMMISSION

f N***f}-

'

/

g.

REctoN it

r

230 PE ACHTREE STREET, N.W. SUITE 1217

-

k

[

'

ATL ANTA. GEo AGf A 30303

"% , ,]'

"

1979

-

In Reply Refer To:

RII:SCE

50-302/78-1

Florida Power Corporation

Atta:

Mr. W. T. Stewart

Director of Power Production

P. O. Box 14042, Mail Stop C-4

St. Petersburg, Florida

33733

,

Centiremen:

This refers to the inspection conducted by Mr. S. C. Ewald of this

office on January 3-6, 1978, of activities authorized by NRC Operating

License No. DPR-72 for the Crystal River 3 facility, and to the discus-

sion of our findings held with Mr. G. P. Beatty at the conclusion of the

O

inspection.

.

The inspection was an examination of the activities conducted under your

license as they relate to radiation safety and to compliance with the

Commission's rules and regulations and the conditions of your license.

The inspection consisted of selective examinations of procedures and

the inspector. representative records, interviews with personnel, and observations by

We have examined actions you have taken with regard to previously

identified enforcement matters and unresolved items.

The status of

these items is discussed in the enclosed report.

During tt'

license appear to be in noncompliance with NRC requirements..nspection

This item

and references to pertinent requirements are listed in the Notice of

Violation enclosed herewith as Appendix A.

This notice is sent to you

pursuant to the provisions of Section 2.201 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201

requires you to submit to this office, within 20 days of your receipt of

this notice, a written statement or explanation in reply including:

(1)

corrective steps which have been taken by you, and the results achieved;

(2) corrective steps which will be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

Oh

'

eco, w- 975

.

'

. -

.

.-

=

-

-

_

.

4

-

4

  • '

~

JEh ::i G7c

.

m

Florida Power Corporation

-2-

_

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter

.

and the enclosed inspection report will be placed in the NRC's Public

Document Room.

If this report contains any information that you (or

your contractor) believe to be proprietary, it is necessary that you

make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is

claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained

in a separate part of the document.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

'

24 /

N

T. Sutherland, Chief

Fuel Facility and Materials

Safety Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-302/78-01