A
'*,
,
_
- .
.- .
-
f.
-
lE FILE COPY
.
.) ,
- p *" "' 4 ,'o,
t
UNITED STATES
NUCLEAR REGULATORY COMMISSION
f N***f}-
'
/
g.
REctoN it
r
230 PE ACHTREE STREET, N.W. SUITE 1217
-
k
[
'
ATL ANTA. GEo AGf A 30303
"% , ,]'
- "
1979
-
In Reply Refer To:
RII:SCE
50-302/78-1
Florida Power Corporation
Atta:
Mr. W. T. Stewart
Director of Power Production
P. O. Box 14042, Mail Stop C-4
St. Petersburg, Florida
33733
,
Centiremen:
This refers to the inspection conducted by Mr. S. C. Ewald of this
office on January 3-6, 1978, of activities authorized by NRC Operating
License No. DPR-72 for the Crystal River 3 facility, and to the discus-
sion of our findings held with Mr. G. P. Beatty at the conclusion of the
O
inspection.
.
The inspection was an examination of the activities conducted under your
license as they relate to radiation safety and to compliance with the
Commission's rules and regulations and the conditions of your license.
The inspection consisted of selective examinations of procedures and
the inspector. representative records, interviews with personnel, and observations by
We have examined actions you have taken with regard to previously
identified enforcement matters and unresolved items.
The status of
these items is discussed in the enclosed report.
During tt'
license appear to be in noncompliance with NRC requirements..nspection
This item
and references to pertinent requirements are listed in the Notice of
Violation enclosed herewith as Appendix A.
This notice is sent to you
pursuant to the provisions of Section 2.201 of the NRC's " Rules of
Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201
requires you to submit to this office, within 20 days of your receipt of
this notice, a written statement or explanation in reply including:
(1)
corrective steps which have been taken by you, and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance;
and (3) the date when full compliance will be achieved.
Oh
'
eco, w- 975
.
'
. -
.
.-
=
-
-
_
.
4
-
4
- '
~
JEh ::i G7c
.
m
Florida Power Corporation
-2-
_
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter
.
and the enclosed inspection report will be placed in the NRC's Public
Document Room.
If this report contains any information that you (or
your contractor) believe to be proprietary, it is necessary that you
make a written application within 20 days to this office to withhold
such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is
claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained
in a separate part of the document.
If we do not hear from you in this
regard within the specified period, the report will be placed in the
Public Document Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
'
24 /
N
T. Sutherland, Chief
Fuel Facility and Materials
Safety Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-302/78-01
cc w/ enc 1:
Mr. G. P. Beatty, Jr.
Nucicar Plant Superintendent
P. O. Box 1228
,
Crystal River, Florida 32629
,