Text
-. __
i m
'O
)-
p-()
ee M
15 June 1977 g
CS-77-109 ca.........
3-0-3-a-2 Mr. Norman C. Moseley, Director Docket No. 50-302 Office of Inspection & Enforcement License No. DPR-72 U.S. Nuclear Regulatory Commission Ref: IE:II:GLT 230 Peachtree St., N.W., Suite 818 50-302/77-8 Atlanta, Georgia 30303
Dear Mr. Moseley:
We offer the following in response to the apparent item of Noncompliance noted in the referenced Inspection Report.
" Deviation-Radioactive Solid Waste Packaging System Contrary to FSAR Section 11.2.5, the radioactive solid wasta packaging system is not functional and is not capable of pro-cessing evaporator concentrates for off-site shipment in accordance wirn applicable regulations."
Corrective steps that are being/have been/will be/taken are as follows:
- A drum roller mixar will be purchased to make our present system operable.
- We are requesting a change be incorporated in the FSAR, Section 11.2.5.1, paragraph 2, to reflect the use of the drum roller mixer.
- We have completed a Cost Benefit Analysis on the use of the con-crate solidification system and at present, indications point out that our present system is not cost beneficial to operate, and does not conform to the ALARA philosophy.
- As long as it is available and economically feasible, we are going to utiliza an outside vendor to perform the solidification process for the Radwaste Program.
- We will establish an operating plan for the utilization of our in-plant solidification system to support our Radwaste management program as required.
8 8002270
,m q
Norman C. Moseley, Director Ref.: IE:II:GLT 50-302/77-8 Page 2 Full compliance is expected to be achieved by 1 October 1977.
4 We find no proprietary information in the Referenced Inspection Report.
Should you have any questions concerning this subject, we will be glad to discuss them with you.
Yours truly, La.?$-wa W. P. Stewart Director, Power Production DWP/rc
. leb W S
/v/NuclearPlantManager i
5 1
4
---,-*---v-
- *^-- --' " -