ML19308A011

From kanterella
Jump to navigation Jump to search

Relief Request I4R-63 Associated with the Fourth Inservice Inspection (ISI) Interval
ML19308A011
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/31/2019
From: David Helker
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML19308A011 (145)


Text

{{#Wiki_filter:200 Exelon Way ExelonGeneration Kennett Square. PA 19348 www exeloncorp com 10 CFR 50.55a October 31, 2019 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278

Subject:

Relief Request 14R-63 Associated with the Fourth lnservice Inspection (ISi) Interval In accordance with 10 CFR 50.55a, "Codes and standards," paragraph (g)(5)(iii), Exelon Generation Company, LLC (EGC), is requesting relief from the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for lnservice Inspection of Nuclear Power Plant Components." This relief request applies to the fourth 10-year interval lnservice Inspection (ISi) program, which concluded on December 31, 2018 for Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3. The fourth 10-year ISi interval complied with the ASME Boiler and Pressure Vessel Code, Section XI, 2001 Edition through 2003 Addenda. We request your review and approval by October 31, 2020. No commitments are contained in this letter. Should you have any questions concerning this letter, please contact Tom Loomis at (610) 765-5510. Sincerely, David P. Helker Senior Manager - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Attachment:

Relief Request 14R-63 cc: USNRC Region I, Regional Administrator USNRC Senior Resident Inspector, PBAPS USNRC Project Manager, PBAPS R. R. Janati, Pennsylvania Bureau of Radiation Protection D. A. Tancabel, State of Maryland

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                        --lnservice Inspection Impracticality--

Revision O (Page 1 of 15)

1. ASME Code Component(s) Affected Code Class: 1&3

Reference:

IWB-2500, Table IWB-2500-1, IWF-2500, Table IWF-2500-1, ASME Code Case N-460, ASME Code Case N-578-1, Table 1. Examination Category: 8-A, 8-D, F-A, R-A Item Number: 81.12, 81.30, 81.51, 83.90, F1.40, R1.11, R1.16, R1.20

Description:

Limited Examination Coverage Component Number: See Tables 14R-63.1 and 14R-63.2 for a list of Component ID's

2. Applicable Code Edition and Addenda

The Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3 fourth 10-year interval lnservice Inspection (ISi) program was based on the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code, Section XI, 2001 Edition through the 2003 Addenda. PBAPS, Units 2 and 3 maintains the responsibility to ensure examinations were performed in accordance with the requirements of ASME, Section XI, Appendix VIII, "Performance Demonstration for Ultrasonic Examination Systems," as amended and mandated by 10 CFR 50.55a and as modified by the Performance Demonstration Initiative (POI) program description. In the case of limited examinations, efforts were made to obtain additional examination coverage. Tables 14R-63.1 and 14R-63.2 identify if the examinations were performed in accordance with the requirements of ASME, Section XI, Appendix VIII.

3. Applicable Code Requirements The extent of examination requirement for Examination Category 8-A, Item Number 81 .12, 81 .30, and 81 .51, per Table IWB-2500-1, requires a volumetric examination of essentially 100% of the weld length or all weld repair areas.

The extent of examination requirement for Examination Category 8-D, Item Number 83.90, per Table IWB-2500-1, requires a volumetric examination of all nozzle-to-vessel welds. During the fourth interval, PBAPS, Units 2 and 3 was approved to use ASME Code Case N-702 by the NRC in a Safety Evaluation Report dated January 24, 2012 (ML112770217) through the submittal of Relief Request 14R-52. Following adoption of ASME Code Case N-613-1, PBAPS, Units 2 and 3 performed a volumetric examination using a reduced examination volume (A-8-C-D-E-F-G-H) of Figures 1, 2, and 3 of the Code Case in lieu of the previous examination volumes of ASME Section XI, Figure IWB-2500-7. The extent of examination requirement for Examination Category F-A, Item Number F1.40, per Table IWF-2500-1, requires a VT-3 visual examination of 100% of the supports. Note 3 in Table IWF-2500-1 states, for multiple components other than piping,

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                         --lnservice Inspection Impracticality--

Revision O (Page 2of15) within a system of similar design, function, and service, the supports of only one of the multiple components are required to be examined. The extent of examination requirement for Examination Category R-A, Item Numbers R1.11, R1.16, and R1.20, per Table 1 of ASME Code Case N-578-1, requires a volumetric examination of essentially 100% of the length of the Risk Informed lnservice Inspection (RI-ISi) weld. For the Examination Category R-A welds susceptible to lntergranular Stress Corrosion Cracking (IGSCC}, 5 welds for Unit 2 and 1 weld for Unit 3, the examination history shows satisfactory results for the fourth interval. PBAPS applied Hydrogen Water Chemistry control for the full duration of the fourth interval. PBAPS elected to utilize the Normal Water Chemistry inspection interval for the fourth interval inspection schedule. PBAPS, Units 2 and 3 adopted ASME Code Case N-460 ("Alternative Examination Coverage for Class 1 and Class 2 Welds, Section XI, Division 1"), which defines "essentially 100%" as greater than 90% coverage of the examination volume or surface area, as applicable. The 90% minimum coverage was applied to all surface and volumetric examinations required by ASME Section XI.

4. Impracticality of Compliance Pursuant to 10 CFR 50.55a(g)(5)(iii), relief is requested on the basis that conformance with these ASME Section XI Code requirements is impractical as conformance would require extensive structural modifications to the component or surrounding structure.

Due to the original design of these components, PBAPS is unable to satisfy the ASME Section XI requirements to perform a volumetric or visual examination to the extent required for welds and supports, greater than 90% of the volume and/or area, due to physical component configuration, interference from permanent plant equipment, single-sided access, etc. PBAPS would incur significant engineering, material, and installation costs to perform such modifications without a compensating increase in the level of quality and safety; therefore, relief is requested on the basis that the ASME Section XI requirements to examine these components are impractical. Component supports, Examination Category F-A, Item Number F1 .40, for the Emergency Service Water (ESW) system pumps are included in this relief. PBAPS, Units 2 and 3, share a common ESW header which has two ESW pumps. Each ESW pump is supported by one seismic restraint. A qualified VT-3 visual examination of the seismic restraints could not be performed due to the clarity of the water within the pump bays. It is possible to drain the pump bay, but if one pump is unavailable, the site is in a 7-day Action. If both pumps are inoperable, then the site must be in Mode 3 within 12 hours. PBAPS, Units 2 and 3 have not attempted to use the sluice gates for this examination because the sluice gates are not water-tight and there would be some leakage of river water. Also, by placing one of the pumps out of service, PBAPS could be forced to place both units into Mode 3 if the other subsystem became unavailable. A best effort inspection was performed for each seismic restraint during maintenance activities, which are listed in Table 14R-63.1 below. NOE summary sheets were not

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                         --lnservice Inspection Impracticality--

Revision O (Page 3of15) completed for any of the examinations performed since a qualified VT-3 visual examination was not performed. During outages, when situations were identified where coverage was an issue, PBAPS, Units 2 and 3 personnel reviewed the systems for alternatives. For the RI-ISi weld population, Examination Category R-A welds, submitted in this relief request, a case by case review was performed to determine whether additional or alternative welds could have been examined to supplement the reduced volumetric coverage examination. It was determined that there were no other welds to select that would have resulted in better coverage. This determination was made based on comparison of configurations, delta core damage frequency (CDF) values, the systems involved, and inspection history. Tables 14R-63.1 and 14R-63.2 provide a summary of the examination limitations for each component for which relief is requested. The tables also indicate the outage the component was examined, the coverage percentage obtained for each component, and other pertinent design information. These tables are the cumulative lists of the limited ASME Section XI examinations performed during the fourth ISi interval. Enclosures 1 and 2 provide coverage plots which were extracted from the non-destructive examination (NOE) summary sheets that detail the examination limitations. Based on the above explanation, PBAPS, Units 2 and 3 request relief to perform examinations without achieving ASME Section XI Code compliance coverage when that required coverage is impractical.

5. Burden Caused by Compliance ..

Compliance with the applicable ASME Section XI Code volumetric and visual examination requirements can only be accomplished by redesigning and refabricating the subject and/or surrounding components. Based on this, the ASME Section XI Code requirements are deemed impractical in accordance with 10 CFR 50.55a(g)(5)(iii).

6. Proposed Alternative and Basis for Use PBAPS, Units 2 and 3 has performed the ASME Section XI Code required examinations to the maximum extent practical (Code Coverage), or best effort, which are documented in Tables 14R-63.1 and 14R-63.2. Due to the physical interferences causing these limitations, there are no alternative examination techniques currently available to increase coverage. There were no cases in any of the listed examinations where the component's outside diameter surface features (i.e., weld crowns, weld shrinkage, surface roughness, etc.) could have been conditioned to obtain the required coverage without major modification to the components.

Periodic system pressure tests that include VT-2 visual examinations will continue to be performed in accordance with ASME Section XI, as well as, any applicable system pressure testing augmented examination programs. The absence of any observed leakage provides additional assurance that the structural integrity of the subject components will be maintained throughout the remainder of the interval.

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                        --lnservice Inspection Impracticality--

Revision 0 (Page 4 of 15) As a minimum, all components received the required volumetric or visual examination and will continue to be conducted to the maximum extent practical due to limited or lack of access as required by the ASME Section XI ISi Program, the RI-ISi Program, or other applicable augmented examination programs.

7. Duration of Proposed Alternative Relief is requested for the fourth 10-year ISi interval for PBAPS, Units 2 and 3 which concluded on December 31, 2018.
8. Precedents The following similar end-of-interval impracticality relief requests have been previously authorized by the NRC:

James A. FitzPatrick Nuclear Power Plant fourth ISi interval Relief Request 14R-22 was authorized in NRC Safety Evaluation Report dated June 21, 2019 (ADAMS Accession No. ML19135A444). Watts Bar Nuclear Plant, Unit 1 second ISi interval Relief Request 1-ISl-21 was authorized in NRC Safety Evaluation Report dated April 12, 2019 (ADAMS Accession No. ML19071A009). Limerick Generating Station, Units 1 and 2 third ISi interval Relief Request 13R-23 was authorized in NRC Safety Evaluation Report dated August 7, 2018 (ADAMS Accession No. ML18192C172).

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                              --lnservice Inspection Impracticality--

Revision O (Page 5of15) Table 14R-63.1 Peach Bottom Atomic Power Station, Unit 2 List of Components with Limited Examination Coverage NonnaI Exam Exam Appendix Component ID Component Operating (Summary Description Requirements Category I Outage Material of Diameter/ Exam Angle/ Actual VIII Conditions Remarks (Figure No.) Item Examined Construction Thickness Frequency I Mode Coverage Qualified Number) (System)' (Pressure I and Method Number Exam Temperature) Low Alloy The examination was limited due to RPV-V1A SC1 Vertical IW8-2500-2 251"/ 8-A Steel/ 1035 psig I 45* I Auto I Shear restrainer bracket and Jet Pump (PEA Seam Volumetric P2R21 6.125- 85.3% Yes 81 .12 Stainless Steel 551"F 70" I Auto I RL adapter ring. 800000) (RPV) (UT) 6.375" Cladding (Enc. 1 Pg. Nos. 2-4) The examinahon was limited from Low Alloy RPV-V3A SC3 Vertical IW8-2500-2 251"/ the ID surface due to Feedwater 8-A Steel I 1035 psig I 45* I Auto I Shear (PEA Seam Volumetric P2R21 6.125- 74.4% Yes spargers, Core Spray Internal Piping, 81 .12 Stainless Steel 551'F 70" I Auto I RL 800030) (RPV) (UT) 6.375" and Core Spray Piping bracket Cladding (Enc. 1 Pg. Nos. 5-8) The examination was limited from Low Alloy RPV-V38 SC3 Vertical IW8-2500-2 251 " / the ID surface due to Feedwater 8-A Steel/ 1035 psig I 45* I Auto I Shear (PEA Seam Volumetric P2R21 6.125- 71.8% Yes spargers, Core Spray Internal Piping, 81.12 Stainless Steel 551"F 70" I Auto I RL 800035) (RPV) (UT) 6.375" and Core Spray Piping bracket. Cladding (Enc. 1 Pg. Nos. 9*12) The examination was limited from Low Alloy RPV-V3C SC3 Vertical IW8-2500-2 251"/ the ID surface due to Feedwater 8-A Steel I 1035 ps1g I 45* I Auto I Shear (PEA Seam Volumetric P2R21 6.125- 73.2% Yes spargers, Core Spray Internal Piping, 81.12 Stainless Steel 551"F 70 " I Auto I RL 800040) (RPV) (UT) 6.375" and Core Spray Piping bracket Cladding (Enc. 1 Pg. Nos. 13*16) The examination was limited due to Low Alloy RPV-C6 SCSto IW8-2500-4 251 "/ guide rods, main steam plug 8-A Steel I 1035 psig I 45* I Auto I Shear (PEA Flange Volumetric P2R21 6.125- 86 .8% Yes hardware, and excessive weld 81.30 Stainless Steel 551'F 70" I Auto I RL 000600) (RPV) (UT) 6.375" beads. Cladding (Enc. 1 Pg. Nos. 17*19) Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                            -lnservice Inspection Impracticality--

Revision 0 (Page 6 of 15) Table 14R-63.1 Peach Bottom Atomic Power Station, Unit 2 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Requirements Category I Outage Material of Diameter/ Exam Angle/ Actual VIII (Summary Description Conditions Remarks (Figure No.) Item Examined Construction Thickness Frequency I Mode Coverage Qualified Number) (System)' (Pressure I and Method Number Exam Temperature) The exammabon was limited due to nozzle configuration and the Feedwater proximity of the instrumentation N4A IW8-2500-7 Nozzle to 8-0 Low Alloy 1035 psig I 60" / 3.0 I Long. nozzle. Essentially 100% coverage (PEA Volumetric P2R18 12" / 6.125" 47.7% Yes Vessel Weld 83.90 Steel 551"F 60" / 1.0 I Shear was achieved for inner radius 003250) (UT) (RPV) examination and bore examination for this nozzle. IEnc. 1 PQ. Nos. 20-231 The examination was limited due to Feedwater nozzle configuration. Essentially N48 IW8-2500-7 Nozzle to 8-0 Low Alloy 1035 psig I so*/ 3.0 I RL 100% coverage was achieved for (PEA Volumetnc P2R19 12* / 6.125" 38.5% Yes Vessel Weld 83.90 Steel 551"F 60" / 1.0 I Shear inner radius examination and bore 003300) (UT) (RPV) examination for this nozzle. (Enc. 1 Pg. Nos. 24-26) The examination was limited due to nozzle configuration. Essentially N4C FW Nozzle to IW8-2500-7 8-0 Low Alloy 1035 ps1g I 60"/ 3.0 I RL 100% coverage was achieved for (PEA Vessel Weld Volumetric P2R1B 12* / 6.125" 47.8% Yes 83.90 Steel 551"F 60"/ 1.0 I Shear inner radius examination and bore 003400) (RPV) (UT) examination for this nozzle. IEnc. 1 Pq. Nos. 27-291 The examination was limited due to nozzle configuration. Essentially N40 FWNozzleto IW8-2500-7 8-0 Low Alloy 1035 ps19 I 60"/ 3.0 I Long 100% coverage was achieved for (PEA Vessel Weld Volumetric P2R20 12" / 6.125" 73.6% Yes 83.90 Steel 551"F 55"/ 1.0 I Shear inner radius examination and bore 003500) (RPV) (UT) examination for this nozzle. IEnc. 1 Pg. Nos. 30-321 The examination was limited due to nozzle configuration. Essentially N4E FWNozzleto IW8-2500-7 8-0 Low Alloy 1035 psig I 60 "/ 3.0 I Long 100% coverage was achieved for (PEA Vessel Weld Volumetric P2R20 12" / 6.125" 73.6% Yes 83.90 Steel 551 ' F 55"/ 1.0 I Shear Inner radius examination and bore 003600) (RPV) (UT) examination for this nozzle. IEnc. 1 Pg. Nos. 33-351 Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                               --lnservice Inspection lmpra.:ticality--

Revision 0 (Page 7of15) Table 14R-63.1 Peach Bottom Atomic Power Station, Unit 2 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Requirements Category I Outage Material of Diameter/ Exam Angle/ Actual VIII (Summary Description Conditions Remarks (Figure No.) Item Examined Construction Thickness Frequency I Mode Coverage Qualified Number) (System)' (Pressure I and Method Number Exam Temperature) The examination was limited due to nozzle configuration. Essentially N4F FWNozzleto lW8-2500-7 8-D Low Alloy 1035 psig I 60"/ 3.0 I Long 100% coverage was achieved for (PEA Vessel Weld Volumetric P2R20 12* / 6.125" 73.6% Yes 83.90 Steel 551"F 55"/ 1.0 I Shear inner radius examination and bore 003700) (RPV} cun examination for this nozzle. (Enc. 1 Pa. Nos. 36-381 The examination was limited due to the proximity of an insulation support Core Spray Low Alloy N5A IW8-2500-7 bracket and nozzle configuration. Nozzle to 8-D Steel I 10" /6.125- 1035 psig I 60"/ 3.0 I Long. (PEA Volumetric P2R21 75.1% Yes Essentially 100% coverage was Vessel Weld 83 .90 Stainless Steel 6.375" 551°F 55"/ 1.0 I Shear 003800) (RPV} cun Cladding achieved for inner radius examination for this nozzle. IEnc.1 Pa. Nos. 39-411 The examination was limited due to nozzle configuration. Essentially 100% coverage was achieved for Control Rod Low Alloy inner radius examination for this N9 Drive Nozzle IW8-2500-7 60"/ 3.0 I Long nozzle. B-D Steel/ 6" / 6.125- 1035 ps1g I (PEA to Vessel Volumetric P2R20 40.6% Yes 83.90 Stainless Steel 6.375" 551°F 55"/ 1.0 I Shear 004000) Weld cun Cladding Examination coverage was indicated (RPV} on examination summary sheet, which is not Included in Enclosure 1.

                                                                                                                                                    !Enc. 1 Pa. Nos. 42-441 Main                                                                                                                              The examination was limited due to Recirculation                                          Low Alloy                                                                       nozzle configuration. Essentially N1A                      IW8-2500-7                                                                        60" I 3.0 I Long .

Outlet Nozzle 8-D Steel/ 36" /6.125- 1035 psig I 100% coverage was achieved for (PEA Volumetric P2R18 60" I 1.0 I Shear 38.2% Yes to Vessel 83.90 Stainless Steel 6.375" 551"F inner radius examination for this 004100) Weld cun Cladding 70" I 1.0 I Shear nozzle. IRPV) !Enc. 1 Pa. Nos. 45-471 Main The examination was limited due to Recirculation Low Alloy nozzle configuration. Essentially N18 IW8-2500-7 60" I 3.0 I Long . Outlet Nozzle 8-D Steel/ 36" / 6.125- 1035 psig I 100% coverage was achieved for (PEA Volumetnc P2R21 55* I 1.0 I Shear 70.5% Yes to Vessel 83.90 Stainless Steel 6.375" 551°F inner radius examination for this 004200) Weld cun Cladding 70" I 1.0 I Shear nozzle. (RPV} {Enc. 1 Pg. Nos. 48-50) Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                              --lnservice Inspection Impracticality--

Revision 0 (Page 8 of 15) Table 14R-63.1 Peach Bottom Atomic Power Station, Unit 2 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Requirements Category I Outage Material of Diameter/ Exam Angle/ Actual VIII (Summary Description Conditions Remarks (Figure No.) Item Examined Construction Thickness Frequency I Mode Coverage Qualified Number) (System)' (Pressure I and Method Number Exam Temperature) Mam The examination was limited due to Recirculation Low Alloy nozzle configuration. Essentially N2A IW8-2500-7 Inlet Nozzle 8-D Steel/ 12* / 6.125- 1035 psig I 60" /3.0/ RL 100% coverage was achieved for (PEA Volumetric P2R19 47.8% Yes 004300) to Vessel 83.90 Stainless Steel 6.375" 551"F so* 11 .0 I Shear inner radius examination for this (UT) Weld Cladding nozzle. IRPVl (Enc. 1 Pg. Nos. 51-531 Main The examination was limited due to Recirculabon Low Alloy nozzle configuration. Essentially N20 IW8-2500-7 Inlet Nozzle 8-D Steel/ 12" / 6.125- 1035 psig I 60" / 3.0 I Long. 100% coverage was achieved for (PEA Volumetnc P2R21 74.3% Yes to Vessel 83.90 Stainless Steel 6.375" 551"F 55* / 1.0 I Shear inner radius examination for this 004600) (UT) Weld Cladding nozzle. (RPV) (Enc. 1 Pg. Nos. 54-56) Main The examinabon was limited due to Recirculation Low Alloy nozzle configurabon. Essentially N2F IW8-2500-7 Inlet Nozzle 8-D Steel/ 12" / S.125- 1035 psig I so* I 3.0 I Long 100% coverage was achieved for (PEA Volumetric P2R22 74.4% Yes to Vessel 83.90 Stainless Steel S.375" 551"F 55* / 1.0 I Shear inner radius examination for this 004800) (UT) Weld Cladding nozzle. (RPV) (Enc. 1 Pg. Nos. 57-59) The examinabon was limited due to Main Steam Low Alloy nozzle configurabon. Essentially N3A IWB-2500-7 so* / 3.0 / Long. Nozzle to 8-D Steel I 2S"/S.125- 1035 psig I 100% coverage was achieved for (PEA Volumetric P2R22 55* / 1.0 I Shear SB.7% Yes Vessel Weld 83.90 Stainless Steel S.375" 551"F inner radius examination for this 002900) (UT) 10* 11.o I Shear (RPV) Cladding nozzle. (Enc. 1 Pg. Nos. 60-62) The examinabon was limited due to Top Head nozzle configuration. Essentially CH-NA Spray Nozzle IW8-2500-7 B-D Low Alloy 1035 psig I S0" / 3.0 I RL 100% coverage was achieved for (PEA N6Ato Volumetric P2R18 6" /4" 53.7% Yes 83.90 Steel 551"F 45* / 1.0 I Shear inner radius examination for this 009400) Vessel Weld (UT) nozzle. (RPV) (Enc. 1 Pg. Nos. 63-65) Note: I. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                               --lnservice Inspection Impracticality-Revision O (Page 9of15)

Table 14R-63.1 Peach Bottom Atomic Power Station, Unit 2 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating (Summary Requirements Category I Outage Material of Diameter/ Exam Angle/ Actual VIII Description Conditions Remarks (Figure No.) Item Examined Construction Thickness Frequency I Mode Coverage Qualified Number) (System)' (Pressure I and Method Number Exam Temperature) The examination was limited due to Top Head nozzle configuration. Essentially CH-NB Vent Nozzle IWB-2500-7 B-D Low Alloy 1035 psig I 60" / 3.0 I RL 100% coverage was achieved for (PEA N7toVessel Volumetnc P2R18 4" / 4" 77.0% Yes B3.90 Steel 551"F 50* 11.o I Shear inner radius examination for this 009500) Weld (UT) nozzle. (RPV) (Enc. 1 Pg. Nos. 66-68) IWB*2500-8(c) 150-1170 psig 23-2Tl16-2 Reducer to IWB-2500-9, This examinahon was limited due to R-A 140 -140"F 45* I 5.0 I Shear (PEA Valve 10, & 11 P2R20 Carbon Steel 16" / 3/8" 76.5% Yes single sided access. R1 .11 (170"F max for 10* I 5.0 I Shear 312100) (HPCI) Volumetnc (Enc. 1 Pg. No. 69) shor1 term) (UT) The examinabon was limited due to IWB-2500-B(c) penetration configuration. Penetration 14-B-3 IWB-2500-9, 45" / 1.5 /Shear Pipe to R-A A376 TP304 0-289 ps1g I (PEA 10, & 11 P2R20 12* 10.688. 60" / 1.5 I Shear 50.0% Yes Examination coverage was indicated 169800) Penetration R1 .20 Stainless Steel Max 187.6"F 10* I 2.0 I Long Volumetric on examination summary sheet, (CS) (UT) which is not Included in Enclosure 1. IEnc. 1 P11. No. 701 The examination was limited due to IWB-2500-8(c) component configuration. 14-B-28 IWB-2500-9, P1peto Pipe R-A A376TP304 0-289 ps1g I 25"-70" I PA I Long (PEA 10, & 11 P2R19 12* 10.688. 70.5% Yes Examination coverage was indicated (CS) R1.20 Stainless Steel Max 187.6°F 35"-65" /PA I Shear 172805) Volumetric on examination summary sheet, (UT) which Is not Included in Enclosure 1. (Enc. 1 Pg. Nos. 71-741 Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                            --lnservice Inspection Impracticality--

Revision 0 (Page 10of15) Table 14R-63.1 Peach Bottom Atomic Power Station, Unit 2 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Requirements Category I Outage Material of Diameter/ Exam Angle/ Actual Viii (Summary Description Conditions Remarks (Figure No.) Item Examined Construction Thickness Frequency I Mode Coverage Qualified Number) (System)' (Pressure I and Method Number Exam Temperature) The examination was due to a complex geometry and configuration. IWB-2500-B(c) 45" I 2.25 I Shear Examination coverage was indicated 12-1-2 Valve to IWB-2500-9, R-A Dissimilar 200-240 psig I so* I 2.25 I Shear on examination summary sheet, (PEA Elbow 10, & 11 P2R18 Metal Wed 4" / 0.337" 39" /2.0/ RL 55.0% Yes which is not Included in Enclosure 1. R1.16 400-425"F 162400) (RWCU) Volumetric (CS/SS) 60" / 2.0 I RL (Enc. 1 Pg. Nos. 75-76) 1un 10* I 2.0 I Long. Note: This weld was cut out and replaced with IGSCC-resistant material durina the 2R21 outaae. Seismic Best effort examination was limited OAP57-SC IWF-1300-1 Restraint, F-A due to water visibility. Divers used (PEA Visual P2R22 N/A N/A N/A NIA 0.0% N/A underwater F1.40 touch and feel method to inspect. 656215) (VT-3) (ESW) No NOE report was created. Seismic Best effort examination was limited OBP57-SC IWF-1300-1 Restraint, F-A due to water visibility. Divers used (PEA Visual P2R20 N/A NIA NIA NIA 0.0% NIA underwater F1 .40 touch and feel method to inspect. 656220) (VT-3) (ESW) No NOE report was created. Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                              --lnservice Inspection Impracticality-Revision 0 (Page 11 of 15)

Table 14R-63.2 Peach Bottom Atomic Power Station, Unit 3 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Exam Angle/ Requirements Category I Outage Material of Diameter/ Actual VIII (Summary Description Conditions Frequency (MHz) I Remarks (Figure No.) Item Examined Construction Thickness Coverage Qualified Number) (System)' (Pressure I Mode and Method Number Exam Temperature) Low Alloy o* I Auto I Long The examination was limited due to the RPV-V1A SC1 Vertical IW8-2S00-2 2S1"/ 8-A Steel I 103S psig I 30* -so* I Auto I Long jet pump baffle plate and proximity of (PEA Seam Volumetnc P3R20 S.12S- 88.7% Yes 81 .12 Slainless Steel SS1°F 40* -so* I Auto I Shear the NB nozzle. 000800) (RPV) (UT) S.37S" Cladding so* -so* I Auto I Long (Enc. 2 Pg. Nos. 2 & 7) Low Alloy o* I Auto I Long RPV-V4A SC4 Vertical IW8-2500-2 2s1*1 The examinabon was limited due to 8-A Steel/ 103S psig I 30* -so* I Auto I Long (PEA Seam Volumetric P3R20 S.125- 83.S% Yes Feedwater and Core Spray spargers. 81 .12 Stainless Steel S51°F 40* -50' I Auto I Shear 001700) (RPV) (UT) S.375" (Enc. 2 Pg. Nos. 3 & 7) Cladding so* -80' I Auto I Long Low Alloy o* I Auto I Long RPV-V48 SC4 Vertical IW8-2500-2 251"/ The examination was limited due to 8-A Steel/ 1035 psig I 30' -so* I Auto I Long (PEA Seam Volumetric P3R20 S.125- 83.S% Yes Feedwater and Core Spray spargers. 81.12 Slainless Steel SS1°F 40* -so* I Auto I Shear 001800) (RPV) (UT) S.375" (Enc. 2 Pg. Nos. 4 & 7) Cladding so*-eo* I Auto I Long Low Alloy o* I Auto I Long RPV-V4C SC4 Vertical IWB-2500-2 2s1*1 The examinabon was limited due to 8-A Steel/ 103S psig I 30*-so* I Auto I Long (PEA Seam Volumetric P3R20 S.12S- 79.1% Yes Feedwater and Core Spray spargers. 81 .12 Stainless Steel 551°F 40*.50* I Auto I Shear 001900) (RPV) (UT) S.37S" (Enc. 2 Pg. Nos. 5 & 7) Cladding so* -80' I Auto I Long Low Alloy o* I Auto I Long RPV-CS SCSto IW8-2500-4 251"/ The examination was limited due to 8-A Steel/ 103S psig I 30° -so* I Auto I Long (PEA Flange Volumetnc P3R20 S.12S* 83.9% Yes proximity of the o* guide rod. 81.30 Stainless Steel 551°F 40* -so* I Auto I Shear OOOSOO) (RPV) (UT) S.375" (Enc. 2 Pg. No. 6 & 7) Cladding so*-so* I Auto I Long Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                              --lnservice Inspection Impracticality--

Revision 0 (Page 12of15) Table 14R-63.2 Peach Bottom Atomic Power Station, Unit 3 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Exam Angle/ Requirements Category I Outage Material of Diameter/ Actual VIII (Summary Description Conditions Frequency (MHz) I Remarks (Figure No.) Item Examined Construction Thickness Coverage Qualified Number) (System)' (Pressure I Mode and Method Number Exam Temperature) The examination was limited due to nozzle configuration. Essentially 100% N4C FWNozzleto IW8-2500-7 8-D Low Alloy 1035 psig I 60"/ 3.0 I Long. coverage was achieved for inner radius (PEA Vessel Weld Volumetric P3R19 12" / 6.125" 73.6% Yes 83 .90 Steel 551°F 55"/ 1.0 I Shear examination and bore examination for 003400) (RPV) (UT) this nozzle. IEnc. 2 Pa. Nos. 8 & 91 The examination was limited due to nozzle configuration. Essentially 100% N4D FW Nozzle to IW8-2500-7 8-D Low Alloy 1035 ps1g I 60"/ 3.0 I Long. coverage was achieved for inner radius (PEA Vessel Weld Volumetric P3R19 12* / 6.125" 73.6% Yes 83 .90 Steel 551°F 55"/ 1.0 I Shear examination and bore examination for 003500) (RPV) (UT) this nozzle. (Enc. 2 Pg. Nos. 10, 11, & 121 The examinabon was limited due to nozzle configuration. Essentially 100% N4E FWNozzleto IW8-2500-7 8-D Low Alloy 1035 ps1g I 60"/ 3.0 I RL coverage was achieved for inner radius (PEA Vessel Weld Volumetnc P3R17 12" / 6.125" 47.8% Yes 83.90 Steel 551°F 60"/ 1.0 I Shear examination and bore examination for 003600) (RPV) (UT) this nozzle. (Enc. 2 Pg. Nos. 13, 14, 15, 16, & 17) The examination was limited due to nozzle configuration. Essentially 100% N4F FWNozzleto IWB-2500-7 8-D Low Alloy 1035 ps1g I 60"/ 3.0 I RL coverage was achieved for inner radius (PEA Vessel Weld Volumetric P3R17 12" /6.125" 47.8% Yes 83.90 Steel 551°F 60"/ 1.0 I Shear examination and bore examination for 003700) (RPV) (UT) this nozzle. IEnc. 2 Pa. Nos. 18, 19, 20, 21, & 221 The examination was limited due to Main Steam Low Alloy N3A IW8-2500-7 60' I 3.0 I Long. nozzle configuration. Essentially 100% Nozzle to 8-D Steel/ 26" / 6.125- 1035 psig I (PEA Volumetnc P3R18 60" / 1.0 I Shear 32.6% Yes coverage was achieved for inner radius Vessel Weld 83.90 Stainless Steel 6.375" 551°F 002900) (UT) 70' / 1.0 I Shear examination for this nozzle. (RPV) Cladding (Enc. 2 Pg. Nos. 23, 24, & 25) Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                              --lnservice Inspection Impracticality--

Revision 0 (Page 13of15) Table 14R-63.2 Peach Bottom Atomic Power Station, Unit 3 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Exam Angle/ Requirements Category I Outage Material of Diameter/ Actual VIII (Summary Description Conditions Frequency (MHz) I Remarks (Figure No.) Item Examined Construction Thickness Coverage Qualified Number) (System)' (Pressure I Mode and Method Number Exam Temperature) The examination was limiled due to Feedwater nozzle configuration. Essentially 100% N4A IWB-2500-7 Nozzle to B-D Low Alloy 1035 psig I so*/ 3.0 I Long. coverage was achieved for inner radius (PEA Volumetric P3R18 12" /S .125" 38.1% Yes Vessel Weld 83.90 Steel 551°F so* 11 .0 I Shear examination and bore examination for 003250) (UT) (RPV) this nozzle. (Enc. 2 Pg. Nos. 26, 27, & 28) The examination was limited due to Feedwater nozzle configuration. Essentially 100% N48 IW8-2500-7 Nozzle to 8-D Low Alloy 1035 psig I so* I 3.0 I Long. coverage was achieved for inner radius (PEA Volumetric P3R1B 12" / S.125" 38.1% Yes Vessel Weld 83.90 Steel 551°F so*/ 1.0 I Shear examination and bore examination for 003300) (UT) (RPV) this nozzle. (Enc. 2 PQ. Nos. 29, 30, & 311 Main The examination was limited due to Recirculation Low Alloy N1A IW8-2500-7 60" I 3.0 I Long . nozzle configuration. Essentially 100% Outlet Nozzle B-D Steel/ 36" / 6.125- 1035 ps1g I (PEA Volumetnc P3R19 60" / 1.0 I Shear 64 .8% Yes coverage was achieved for inner radius to Vessel 83.90 Stainless Steel 6.375" 551°F 004100) (UT) 10* / 1.0 I Shear examination for this nozzle. Weld Cladding (Enc. 2 Pg. Nos. 32 & 33) IRPVl Recirculation The examination was limited due to Low Alloy N1B Outlet Nozzle IW8-2500-7 SO" I 3.0 I Long. nozzle configuralion. Essentially 100% B-D Steel I 36" / 6.125- 1035 psig I (PEA to Vessel Volumetric P3R18 so* 11 .0 I Shear 28.1% Yes coverage was achieved for inner radius 83.90 Stainless Steel 6.375" 551°F 004200) Weld (UT) 70" / 1.0 I Shear examinabon for this nozzle. Cladding (RPV) (Enc. 2 Pg. Nos. 34, 35, & 36) Main The examination was limited due to Recirculation Low Alloy N2C IWB-2500-7 nozzle configurabon. Essentially 100% Inlet Nozzle B-D Steel/ 12" / 6 125- 1035 psig I 60" I 3.0 I Long. (PEA Volumetnc P3R19 74.3% Yes coverage was achieved for inner radius to Vessel 83.90 Stainless Steel S.375" 551°F so* / 1.0 I Shear 004500) (UT) examinabon for this nozzle. Weld Cladding (Enc. 2 Pg. Nos. 37 & 38) (RPV) Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g)(5)(iii)

                                                               --lnservice Inspection Impracticality-Revision 0 (Page 14of15)

Table 14R-63.2 Peach Bottom Atomic Power Station, Unit 3 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Exam Angle/ Requirements Category I Outage Material of Diameter/ Actual VIII (Summary Description Conditions Frequency (MHz) I Remarks (Figure No.) Item Examined Construction Thickness Coverage Qualified Number) (System)' (Pressure I Mode and Method Number Exam Temperature) Recirculation The examination was limited due to Low Alloy N2D Inlet Nozzle IW8-2500-7 nozzle configuration. Essentially 100% 8-0 Steel I 12' / 6 .125- 1035 psig I 60" I 3.0 I Long. (PEA to Vessel Volumetric P3R18 40.6% Yes coverage was achieved for inner radius 83.90 Stainless Steel 6.375' 551"F so* / 1.0 I Shear 004600) Weld (UT) examination for this nozzle. Cladding (RPV) (Enc. 2 Pg. Nos. 39, 40, & 41) Main Recirculation The examination was limited due to Low Alloy N2F IW8-2500-7 nozzle configuration. Essentially 100% Inlet Nozzle 8-D Steel I 12" / 6.125- 1035 psig I 60" 13.0 I RL (PEA Volumetric P3R20 74.3% Yes coverage was achieved for inner radius to Vessel 83.90 Stainless Steel 6.375' 551"F 55* / 1.0 I Shear 004800) (UT) examination for this nozzle. Weld Cladding (Enc. 2 Pg. Nos. 42 & 43) (RPVl The examination was limited due to Core Spray Low Alloy N5A IW8-2500-7 nozzle configuration. Essentially 100% Nozzle to B-0 Steel I 10" /6 .125- 1035 psig I 60"/ 3.0 / Long. (PEA Volumetric P3R19 72.5% Yes coverage was achieved for inner radius Vessel Weld 83.90 Stainless Steel 6.375" 551'F 55"/ 1.0 I Shear 003800) (UT) examination for this nozzle. (RPV) Cladding (Enc. 2 Pg. Nos. 44 & 45) The examination was limited due to an Control Rod Low Alloy insulation bracket at 325" to 345", N9 Drive Nozzle IW8-2500-7 B-D Steel/ 6' / 6.125- 1035 psig I 60"/ 3.0 I RL W=4'. Essentially 100% coverage was (PEA to Vessel Volumetric P3R20 71.5% Yes 83.90 Stainless Steel 6.375" 551"F 55"/ 1.0 I Shear achieved for inner radius examination 004000) Weld (UT) Cladding for this nozzle. (RPV) (Enc. 2 Pg. Nos. 46, 47, & 48) The examination was limited due to IWB-2500-8(c) component configuration. Penetration 45" / 1.5 I Shear 14-8-3 IW8-2500-9, Pipe to R-A A376 TP304 0-289 psig I so* / 1.5 I Shear (PEA 10, & 11 P3R19 12" / 0.688" 75.0% Yes Examination coverage was indicated on Penetration R1 .20 Stainless Steel Max 187.6"F 70" / 1.5 /Shear 169800) Volumetric examination summary sheet, which is (CS) 70" /2.0/ RL (UT) not Included in Enclosure 2. (Enc. 2 Pg. No. 491 Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Attachment 10 CFR 50.55a Relief Request 14R-63 Proposed Alternative in Accordance with 10 CFR 50.55a(g}(5}(iii)

                                                               --lnservice Inspection Impracticality--

Revision 0 (Page 15of15) Table 14R-63.2 Peach Bottom Atomic Power Station, Unit 3 List of Components with Limited Examination Coverage Normal Exam Exam Appendix Component ID Component Operating Exam Angle/ (Summary Description Requirements Category I Outage Material of Diameter/ Actual VIII Conditions Frequency (MHz) I Remarks (Figure No.) Item Examined Construction Thickness Coverage Qualified Number) (System)1 (Pressure I Mode and Method Number Exam Temperature) IW8-2500-8(c) 12-l-2R IWB-2500-9, Dissimilar The examination was limited due to Valve to Pipe R-A P3R20 200-240 psig I 45" I 2.251 Shear (PEA 10, & 11 Metal Wed 4" / 0.33" 33.5% Yes component configuration. (RWCU) R1 .20 (PSI) 400-425"F 10* I 2.25 I Shear 162410) Volumetric (CS/SS) (Enc. 2 Pg. No. 50) (UT) Repair Weld Low Alloy o* / Long RPV-RW1 251"/ The examination was limited due to the Shell Course IW8-2500-1 & 8-A Steel/ 1035 ps1g I so* - ea* I Long (PEA P3R20 6.125- 78.1 Yes jet pump riser brace. 2 2 81 .51 Stainless Steel 551"F 40* - so* I Shear 000055) 6.375" (Enc. 2 Pg. Nos. 51, 52, & 53) (RPV) Cladding 30" - so* I Long Note:

1. The following systems and their abbreviations are listed here: Core Spray (CS), Emergency Service Water (ESW), Feedwater (FW), High Pressure Coolant Injection (HPCI), Reactor Water Clean-up (RWCU), and Reactor Pressure Vessel (RPV)

Enclosure 1 Peach Bottom Atomic Generating Station Unit 2 Fourth lnservice Inspection Interval Limited Coverage Non-Destructive Examination Coverage Plots

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots 8 HITACHI Peach Bottom Unit-2, P2R21 RPV-VlA Reference Drawings

                                                           -100*                                                                   .100*

r--------- St0--1-\;h~"

                                                                                  -;-.;;-cJ-Ul:"iquia~* ...-=- - - - - - - - - -1 Scann~r Side                                                             Scann~r Side
                                                          ,~ ,                                                                       ols
                                              ~          m "J

I

                                                         ~

I Q. Q fil Q I I

                                             ~
                                                         ~

L2J w

                                                                   ~
                                                                                                                        ~~~

GJ :*** GJ... Q

                                                          ~         Ctol G1 GJ G
                                                                                                                         ~~          ~1     :~J
                                                                                             'i.

4)8* zo*Az. 4~*1 i.s*1 I I Stltil Cou1n 1 CCW t' Sht'ICaunr 1 CW I I I Sui::~rmrnt4 laamVcl11me* 7i. 5~ tn Supplt>tnenl li (.am Vclume

  • 42 9 Sa In
       ~ T-Sc.onAthlc-""O"' ,.._SQ lo S4P-ScanAchie11rd.745q In Sb T-SC0t1Actucwd *4l9Sq In 56r SconAdlte'Vrd*llZ'Sq In II encl 010mrlcr al Range* 15 J 00 mcl1cs
       \lrnrl A.'rmulh'I
  • 119 mc:Msldtqrrr Nommol CIQd 1'
  • 0 1175 mc:hts Hrn I Ordi:rf'd Stoel T
  • 6 125 / 6 J 75 1nchn GE* 1111ACHI NUCLEAR ENERGY PEACH BOTTOM UNIT 2 SHELL COURSE I WELO RPV-VIA SCllLE. NONE DWG. PBZ-2016*04 REV 0 Cross Section of Achieved Coverage Head Down No Restrictions Report 800000 Weld RPV-V1A Page 8ol11 2 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e HITACHI Peach Bottom Unit-2, P2R21 RPV-VlA Reference Drawings

                                                              -100*                                                                            +10.0" r - - - - - - - - - - ..;;-:IV..
                                                                                             ~7"""-t*:-:   ..
                                                                                                 ~ ..... <$ ... :7'11*- - - - - -  -   -  -  -  I
                                                             .:*I 1 n~~
                                                 ;,,.J                    ~,, ..

QliJ-8 fOOl ITT f001

                                                                                                                                  ~

f001ITTf001

                                                                                                                                               ~ ~
                                              ~~~:.-t-       .:l*  ~     i:** 11
                                                                                                                                  ~ ~ ~
                                                                                                                                    ~.          ("~       ~8 I                                                                              I g rn a-:
                                                                       -e;J                                                       g rn                   -e;J
                                                             ~"~

Scanner Side (lq C*U Scanner Side

                                                                                                   <i.

4S'T I 10*1 I I ShrM Cau1u 1 CCl.Y t I ShrHCounr IC\'J II I I T fo;:p1rmrn1 :i E*am Vol1.1mr

  • 1'-5~ 111 5upplrmr-nt 6 E*om Volumr * .:.2 S Sq In St. l*SCOl"I Achot"~-ed .. 7 h 5~ In SloP-Scan#.chieve-d* 7t,,5q In UT*5tOflA(l-.e".~d*4195q Ir.

56 P-Scon Achorwd

  • 4l! Sq In
       \'n1cl O>Cltnelet at fbnqe *     ~51  OOm<:hn Vrurl ~*11nuUu. 1 H nchHldr~rr Nominal Ood T
  • O 1111751nchr\

M111 I Otdtrrd ShrU T .. 6 J25 / 6 l75 *n<ho GE* HITACHI NUCLEAR ENERGY PEACH UOTlOM UNIT 2 SHELL COURSE I WELD RPV*VIA SCALE: NONE DWG. PB2*2016-04 REV. 0 Cross Section of Achieved Coverage Head Up No Restrictions Report 800000 Weld RPV-V1A Page 9of11 3 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e HITACHI SP2000 RPV Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R21 Weld RPV-VlA (SCl Vertical Seam) CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 133.00 Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 50.30 Area Sq. in. Automated Automated Automated Automated 70" T-Scon CW (S4 NS) A 7.4 7.4 7.4% 23.50 0.6% 70° T-Scon CCW (S4 NS) A 7.4 7.4 7.4% 23.50 0.6% 45" T-Scon (S6 FV) A 42.9 42.9 85.3% 23.50 7.5% 70" P-Scon UP (S4 NS) A 7.4 7.4 7.4% 23.50 0.6% 70" P-Scon DN IS4 NS) A 7.4 7.4 7.4% 23.50 0.6% 45" P-Scon IS6 FV) A 42.9 42.9 85.3% 23.50 7.5% 70" T-Scon CW IS4 NS) B 7.4 7.4 7.4% 90.00 2.5% 70" T-Scon ccw (S4 NS) B 7.4 7.4 7.4% 90.00 2.5% 45* T-Scon (S6 FV) B 42.9 42.9 85.3% 90.00 28.9% 70" P-Scon UP (S4 NS) B 7.4 7.4 7.4% 90.00 2.5% 70" P-Scon DN (S4 NS) B 7.4 7.4 7.4% 90.00 2.5% 45" P-Scon (S6 FV) B 42.9 42.9 85.3% 90.00 28.9% 70" T-Scon CW (S4 NS) 70° T-Scon CCW (S4 NS) 45" T-Scon (56 FV) 70" P-Scon UP IS4 NSI 70" P-Scon ON IS4 NS) 45" P-Scon IS6 FVI

                                                                                                         % Totol Composite Coverage =   BS.3%

Rev 0 9/2']/QS Comments: A - Automated scanning was restricted due to Jet Pump #10 restrainer bracket from 235" TO 225". B - Automated scanning was restricted due Lo Jet Pump #10 adopter nng from 135" TO 125.5". Note - Rounding methods may affect calculated values. FV-Full volume. NS-Near Surface. Weld length in inches. Report 800000 Weld RPV-V1A Page4of11 4 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3A Reference Drawings 1o r:*

r -- -- -- ~-;;-.:=:::;::..-:- .- - - - - - - -- -*~n* I I

                                              ~-      -'      Srnnn~r        l\inr                                                      .--.... _.,    S:onn~r ~.ne
                                                     "*               ..I*           ....                                                       ** .        :.I:

1-,*~r CD GI r-:;:;t_ m I ****I Lef LJ!Qf L,2

                                                                  ~ 8~::
                                                                                                                                              ,!,         ~            ...

G-1

                                                 ~ Q                                 (1\J                                                  r:l           GI ~

r-=-- L2

                                                         ;I     _r:::i l....,QQJ 0                                                  G GJ B
                                                                                                                 ""C_.:* .~;~~-_:],.., *: *
                                                                     *"                                                                      ~RO           .......    *- *
                                                                                                .~Ill*
                                                                                                  ,.,,,_                                               ___:~1 1                                                                                                                                                                           ... ,~ . ""~
       --~~ =
                                                                     .-...'I          rOI y"' /
                                                                                          -....-)1' r
                                                                           \,           ----/-' L
                  ..... ,.,.;.,                                                 --~ //             i I

I 7'

                                                                                                                                          '* /
                                                                                                                                                                    ~--

[ /,><._,,  :

                ------                                                   / /              " *~I                    !

1 i1// ""'*"" It -

       ~ ...."'"'""nt"llt:fl'>\*'..... ~       * ~~ ....
       ~orpln*...nl   t i..,,..,'""'- ** :~~ . ,       In
       *1111 !Or11t1ili:t""'....d"'    *~1""
       'C.P.i;*1111A"9"'1'"*!'115flln
       !l.T   S~"'1*"""'111*        .. if::;gh HF     SlOO~:r-""'!I      * <\]f Sci  ~
       *ttlf'l~lft1tlf~*IH l.:.t -"r
       ""l"t:."l-'!'~-*1'rA1:JV-IJillooQ't"t"
       .. lllmf'C!Cl::H.Oll!'loont~
       .,_,,,.-.._... srw****ll\ 1           ~11\-P       ...

Gf* Hlr*Ctll NUCl(A~ CNC~Gv I PCAClllflJTIOMUNlll I StllllCClURSfl\YflORflVV.li\ I ~(Alf NONf I [)WG P0120lf'ilO I RIV II Cross Section of Achieved Coverage Heod Down Na Restrictions Rapoot 800030 W..ld RPV VJA P11ge7of 11 5 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3A Reference Drawings HlO" ____ - - - -_-;-.,:-;:*:i:;.~. - --- ----,
                                                                                                                                                     *IDO*

I

                                             ,--------~~~~~-

I I

                                                                                                                                        ~
                                                                                                                                                     ~l r.f.1-         u                                                                               8
                                                 ~~
                                                                                                                                                       "'I*
                                                              ~

El o~. fOOI L:.:..J 1!J ,.... ,

                                                                               ~*I (Oo*         '""

I tJ. L] .... f] .... ~ Ji1

                                           .....           s,onrwr 'i11Jt:       - -\_                                                           si:onnct51M
      -Lr. . ,. -.
        *- -~~~-~

1.ll"'A.1

                                                                                                                                                                 = -=-
                                                                                                                           *1'0"'
                                                                                                                                                      ""I
                                                                        *.'\       -   r/     I
                                                                                                              *r                       ' ,
                                                                                                                                                /

m*-, ');. / '  : )<~. .,_MN"Wj I

               -- --L< '"~                                                 /                                   '

I

                                                                                                                        -~--

I I /

                                                                                                                                                     ~---
       \..;'h*..*-1** '"'""""'* '"l!I          ~*
       ~-l'in .... 11.1_\_*~**IV'-t"'
       ~* **~(   .........,
       ~"""""'"""""'"'~
                                       ~~"'
       ~ .. r~.,.,_,,.,......, ** ,..,)oq"'

J<tP* kMA<tto-~"**1'Jll'fl

      \'nulC.~l**11lllcrwf**i~IC;)11'11h .. ,
      \'nut ........... 1r. ** :1tn::t>.*'Grll'-
      .,.-,1:J:tl , Qlll\""
      ..... ,"'..... ,..,5 .... i1.r.11~/f, ! ....... <***

GE tntACttl Nll!LFAR fNfRIW 1'£ ACH ROOOM UNl1 l SIUll fCJIUc.t lWl:UJRPV V~A SCALC NO~£ DWG. l'lll*IU16* IO RlV U Cross Section of Achieved Coverage Heod Up No Restrictions Report 800030 Wt.kl RPV-VJA Page a of 11 6 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots . ) HITACHI Peach Bottom Unit-2, P2R21 RPV-V3A Reference Drawings

                                                                         ~oo*                                       .,.._. ... .,,.                         -60 r - - -- --- - --..;;... ..                    ~       --~,-----1 I                                   -..  --,~*"        ..... ,. ......                t
                                                *-~~1.1                                                                             r~ 8~

LJ ~I LJ ti rn ~

                                                                                                                      -]':>('
                                                       ,....         * .. i           : .. 1
                                                                                                                                                           ~.             ~I S1..1tntttt1!111dt*      ~                                                                 SrnnnPr SIC1t>       -...,
                                                                                                                       )Jc.;.

1111'<**1

                                                                                                                                                                                         =-=---=--1
         .I.
            "=--"-~--=--=--~~-=o-                                                       ,a-           ;C:'"                              .;~~,. ...'" "'"

4~*1r.-

                                                                    .*1**                                                 I                                                 .. ,
                                                                                                                                                 %.-~~*
                                                                                           ' ""<:'.)'i
                                                                                                                                                                                        ---=--

I

                                                                              '*, -----/ i
                                                                                   '>( :                                               -                      -..... /
                                                                                      /

I . '

              """~**'"
                                                                                                                                                                                                     ~""]"~

L *--------- *----- ,.* /

                                                                                                \._I
                                                                                                    *~

I I I

//.

I ___

                                                                                                                                                                           '~....* . _ _ _ _ _
          ~,      .... ,.,,,.,__.,.... . ..'"°-1"'
          ""'r11n- ..... 1.cm\'""""'"'*
                                                 .,,s.:; ..

s.11.-.r...1-J., ... ,.,~ .. ~.

          ~r-:..anAc...,.,...... 1*1t.t'.qlft
          \tlHl)AA.i-*""'4t*>q'"'
          ~ *" \:11111.lt ... ....r. "~~"
          \*Of'l~W*Olll:llfl~"'."\lC':I"':"**

v.,,,.,,.,._,"-' *I !,.,.....,.l1.rr..,. 1ro,......i0..St o l\!!lil'J,.~l ... t l"l"' IU' ISfttfU"'ll.tlJ)/,)15...-:"C'l hi

  • HllAClt!NllfllARl:Nl:ltftV f.'iAlHltOt10MUN111 SHEil C°OUASE JWFIOHPV VlA SCA1E* Nc)N[ 0WG Pll2 lPlCi JO RCV O Cross Section of Achieved Coverage Head Up Limited by a Core Spray Brockel Re11011 000030 Wt!ld RPV*V3A 1>age 9or t I 7 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI SP2000 RPV Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R21 Weld RPV-V3A (SC3 Vertical Seam)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 133.00 Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 50.30 Area Sq. in. Automated Automated Automated Automated 70" T*Scan CW 154 N51 A 74 7.4 7.4% 94.50 2.6% 70"T*Scan CCWl54 NSI A 111 7.4 7.4% 94.50 2.6% 45* T-Scon 156 f\11 A 42.9 42.9 85.3% 94.50 30.3% 70" P* Scan UP 154 NSI A 7.4 7q 74% 94.50 2.6% 70' P-5con DN 154 NS) A 7.4 7.4 7.4% 94 .SO 26% 115* P-5can 156 FVI A 42.9 112.9 853% 94.50 30.3% 70" T-Scan CWl54 NSI B 7.4 74 74% 4.50 0.1% 70° T-Scan CCW 154 NSI B 7.4 7.2 7.2% 4,50 0.1% 45" T-Scun{S6 FVJ B 42.9 42.9 BS.3% 4.50 1.4% 70" P-Scan UP 154 NSI B 7.11 6.6 6.6% 450 0.1% 70" P-Scan DN (54 NSI B 7" 74 7.4% 4.50 01% 45* P-5con 156 FVI B 429 42.9 85.3% 4.50 1.4% 70" f-ScanCWIS4 NSI 70" T-Sc:an CCW 154 NSI 45" T-5can 156 FVI 70" P-Scan UP (S4 NSI 70" P-Scan DN (54 NSI 45* P-Scan (56 FVI

                                                                                                          % Tolal Composite Coverage =  711.4%

r.4..0fJl.'JJj; Comments A- Automated scanning was restricted due to prox1rnity or FeedwotP.r Sporgers and Core Spray Piping. B Automated scanning was restrrcted due to prax1m1ty of o Core Spray bracket. Note Rounding methods moy affect calculated valut?S FV-Full volume. NS-Near Surl<Jr.P.. Weld lenglh 1n inches Report 800030 Weld RPV-V3A Pago4or11 a of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3B Reference Drawings iur.*

r------- - - -- .. -----, *lOO I

                                           .--...__1           '

I Sc0Ml:1:il(fc: --\..._J I

                                                                                                                                                  ~onr"1 s.dc
                                                     .,.      .I,                                                                          ..          +        .

I~ QJ Q' Gr rn- Q a ~~~

                                                      '        I
                                                        '      L-Q GI l ~l         Q                                                                        GJ Q G r'"'"'-" '" .     -----=-=-=--------- . . ~-
                                                              .  **.. ~~;I I

ze.,~

                                                                       ,"v/'1 **-- t ---: -.....,)<//

I . , , .. I

                                                                                                                        ~15(=~-
                                                                                                                                       ,,,-r I

4,"

                                                                                                                                                     -r=--- ~
                                                                                                                                                              ~

____=J**~*~~

                                                                                                                                                                         -==---      -1 l   ----
                                               -----:_/ __ -
                                                                      ,,,,"~
                                                                             /'\
                                                                                         *\

I I I I I I I J/_ I I /

       ! * ..-r1r"'"'"l-ci-nv.... -.,,       ~. , ...
       ~.1     ......... , *._ \ ' 4..... ;.1,;.1**
       ~* T S: 11011'.:"'t.1t"'* 04i:i to'l kf'.icl!lr\Atln***
  • 14!.'ll"
       ~ s ~-":'*r        ........ t,}11..,
       ~--,* ~OnAtN ......         al!li4 Ill
       \'fU~""1r-IP1glfl.,...,.*nlt.1""'I.#~
       *'HUIA.VJ1 .. '1tollll""'!V'/*lf'*

tf.......,.~dl*C11 7~"',_*

       !'4~   IU.ll**t11J"'"t1 *~J1!/lJl\-.Cl* *1 GF* UllAl.111 NLl(l[AH [N(H(IV                        I    f'[A(lll*OnlJMUNIT 1               I  Sfl[Ll CllVR5( JW(LC\NP\l*\13U   I       SCALl NCJN[     I OWCi. *'Ul*lOJCt*ll I  NEY 0 Cross Section of Achieved Coverage Head Down No Restrictions Repon 800035 Weld RPV-V3B                                                                  Page 7 0111 9 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3B Reference Drawings I

I - - - - - - - - - - _-;,, **~***;-* - - - - - - - - - - -~ 1 I I i I

                                                                   ,1.            .....
                                                 ~~~   .

LJ 8~~ LfJ... m~

                                                   =                                                                                                  ..     ...

ri {;,J Ll

                                                                                  ,--\_....I*

1-o1! SJ JOOl JOl 1-;;J L;J

                                                                                                                                                    ~
                                                           !lc11nn1*1 ':1llt>
                                                                                                                   't
                                                                                                               .. .,1 ,       ~~~f,:     * ~ *1         -~"'- ~               ---=

1-===."'-""=-~~-= l i;I*~

                                                                  .5.,
                                                                       .,__           ___.><~

l'tr"

                                                                                               ..;*1-T.
                                                                                                      --- I I
                                                                                                                        ---..JX.'>.
                                                                                                                        .~-~     ,

I /

                                                                                                                                                  /
                                                                                                                                                                            ,N11l"""'1~JlW
                                                                          '-,'.           /,        I               ,             I           *

[.*.,_,.'" /

                                                                                "A
                                                                                  -./

I I I I'

                                                                                                                                 'I I/
                                                                                                                                       /       ' ,'*
            ---- - - - - L.*' __ '\'                                                         _..::J                                 /_
         ~1n*tt*-;( ...,.., ... ,:.,.**    ,..;*l'I**
~lftf'fll*l""""vlll..il~*:..!SiQ'"
         .~1       l::arl*:t- *.-s.  ~4!.1111
         .4 r      ~t ... A:"':VTC - ~ .. SC ,..
         ~*I \lonAr"°'".,..... "'" \4 '"

HP)LOl'Alt~*fl.l,'<I'"'

        \.'**u>lrl.oumr1 ... 1:1n,,.q..;~1 or.nc.1*1
        \ ... U' .... ~"*' """~ldt~*-
        .. """""Oc~T**Ulrs .... tw1
        - . l t';Mn~r .... f.,fiii'~/IJJ\-1-rl r.£    tlltA(hlN\XtrARtNFfUiY                                   PfACHBOnOM11N1I}                     SttfllCoUkS(JWELDANVl8                   SCM£ NCltlt      UWG ru1101t. ll         HCV 0 Cross Section of Achieved Coveroge Heod Up No Restrictions Repo1I 800035 Weld RPV* V30                                                                Pa~e8 0111 10 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3B Reference Drawings rnc* ..,... ...._ --,
  • ltW I -~.~ * *..,.* '** '"'" I I I o ro ~. :

I I

                                                      ~ ~*h ~:~,
                                                      ~                o             oo                                       fOOlm                    oo L;J                ~:           :.~

I

                                                                                                                              ~ ~                       ~~ .

I GJ u g L:] 1~ 0 J-

                                                         * .,           . ., ;        .,..                                       , -.          '"    ~   -,. I
                                                                  ~lUllllCf S*llt'    ('"'"L__*                                          SLannrr S*de     --
        ==----                                                            "                       . ., ,. , .I.,.,.. , , ,.

I*-"-"'" =:.,;, x

                          ~                                                                                                      ;~..,.                                      ~--
                                                                        *,             1'1         *G11i.                                   :tTll"      * .,-
                                                                                                                                                                  ~----=--      ----
                                                   --*-=:.::*..
                                                                                ' .:y.__ ____ --=--1  t             --- ' --                    '         '

I '""~'" ""J-. l II ' )I (

                                                                                /'\ I
I / /11*,' , *
                                                                          /                     *,1
                                                                                                  ~l I / I "                1 -- --~--
                                                                                                                                                                              ---~-

I

      !;.1:1.*t.,,.,.\.lott1"1Y.J.,,. ..          , ...,,.,
       ;..ac;.1,,.......11l~***u... .., ... ,fo~ii          ...

J:.1'-!:71 ....--.,,,.,~,1*

       '41>$~A: ........ . .. ,,~,~ ....
       ~.,, ~'""      .... ,.....r'i.t.:'~ ...

1**1tCll"'""'...wd**l**11 ...

       *'"'"~'""'~* ~ :01'lfl-'lt ...
       ~*--r..1 .......... :n1 .. 11*.,,,.,.....,....~
      .,.,.,..o.1-01u)ll'ICflf1
      't~ IO.i!nd~t.,1nl~ll:t--

GE HITA(HINU:"lfhRENFRtW I ,.,AC** an"OM IJNIT, 1 ~**ru (CUJQ'iE l wnu "Y \1.3~-r- SCA*C* NONE I l1Wfj l'l12 i'OJb ,

  • I RlV a Cross Section of Achieved Coverage Head Up Limited by a Core Spray Brocket Report 800035 Wold RPV-V3B Page 9ol 11 11 of 76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI SP2000 RPV Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R21 Weld RPV-V3B (SC3 Vertical Seam)

COOE CROSS-SECTIONAL AREA TOTALCOOECOVERAGE Percent Weld length = 133.00 Required Exam Area Scanned of Area Weld Length Percent EKom Volume = 50.lD Area Sq. in. Automated Automated Automated Automated 70' T-Scan CWIS4 NS) A 7.4 7.4 7.11% 92.90 2.6% 70'T-Scan CCW 154 NSI A 7.4 7/1 7.4% 9290 26% 45' T-Scan 156 fVJ A 42.9 112.9 85.3'11> 92.90 29.8% 70' P*Scan UP 154 N51 A 7.4 7.4 7.4% 92.90 2.6% 70' P*S<:un ON (54 N51 A 7.4 74 74% 92.90 2.6% 1,5* P-5con 156 fVI A 429 42.9 853% 9290 29.8% 70' T-Scon CW 154 NSI 8 7,4 74 7.4% 2.70 0.1% 10' T-5can CCW(54 NSI 8 7.4 S.7 5.7% 2.10 0.1% 45' T-Scan 156 FVl B 42.9 42.9 85.3% 2 70 0.9% 70' P-5can UP (54 NSI B 7.4 4.7 4.7% 2.70 00% 70' P-Scon DN (54 NSI B 74 74 74% 2.70 0.1% 45' P-Scon 156 FVI B 429 4?9 853% 2.70 0.9% 70' T-Scan CW (54 NSI 70' T-Scon CCW 154 NSI 45' T-Scon 156 FVI 70' P-Scan UP (54 NSI 70" P-Scan ON 154 NSI 45' P-5con 156 fVI

                                                                                                      % Total Composite Coverage ~   71.8%
                                                                                                                                                   .. (io v ""'"~

Comments. A Automated scanning was restricted due to proximity of Feedwoter 5porgers and Core Spray P1p1ng. 8 Automated scanning was rest11cted due lo prox1m1ty of a Core Spray brockel Nole Rounding melhods may affect calculated volues FV-Full velum~ . NS*Neor Surloce Weld length 1n inches Repotl 800035 Weld RPV-V3B Page~ 0111 12 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots (. HITACHI Peach Bottom Unit-2, P2R21 RPV-V3C Reference Drawings IU\* -***-*--- -J~u* I - - - - - - - - - -,. "-c-* ..*. "*:; .- - - - - - - - - - -, I I

                                                 -~'

Slonr.l*1 Sit.Ir 'Aonnt'f ~ti~

                                                                   *h                                                                                               .1.       "*

f*"J I .. ~. L

                                                                ~r I

rJ

                                                                                  ..-                                                                @I~~~ ~I
                                                       .~.
                                                                                                                                                     ~I r\. ~.I Gl
                                                           .        L                ...
                                                   ~I[~                          GJ Q           ~I               (;l                                                                  Q Q.. GJ      _ :       ...

f '.

          -"'----~-=..--==----.~-::--

1"'1**"'" rl,,\'

                                                                  . *.*~
                                                           ---=--~~~~~*'!:]

I

                                                                            \
                                                                                           ,/
                                                                                                     ,.111..
                                                                                              ,. . . . . . _~

I

                                                                                                                   -   o~rl.t
                                                                                                                        ~l t -- ~_,::

t:01

                                                                                                                                    . ~ __ _:!_'---=-==--===--='-!

1-** ......... - - * -

                                                                                                                                                             ---;.;;:=.---
                                                                                                                                                             ,/

I -

                                                                               / ..
                                                            - --..::..:__ *__ '\., i
                                                                                     *~...
  • I I

I I i

                                                                                                                          '          1 I

I

                                                                                                                                                    "'-**/
                                                                                                                                                      / .

i/ /.-./ ",~---~~---- J

                                                                                                                                                                                          !*-*'..:~ .... J(\*.....

__.__ *j

        -'*'"~1*.11****1'~'"              Ir.: *. ,.
          .,_pf,>Un*"t:i*c..,'.:'--**.'""*l~,
         .... ,, it***~,.. ..  ~.:.  -.. ;,, ..,
. .. I' :.~an "r"'""~o. ~ ... ~ll "'

5~1*~~-* ......... J.*lt~;i ...

        !1rt,.,..1111-1*4t,:.a~
        \~('.o;- ......        ""'"l"*l\1.-c .. :*-
        \~i.ctMJ****llh.,; 1,irt~ltr1/JN'r.:

11amrt~Cb.1' .c IHi':....rf'I-, Uf>l'>t1.Lr-W1tl,..,f**l1i,*1"\..._1 .... GI 1ur11C1t1 NUCltAf.I: rNffi(,y I 1'11\llll!OlllJMllt:ll} I ~l&lllCtJU~l 1\YllORW-VJl I ~c.:t.LL NONl I O\VG PR;' ~Olfi 1;o I R(V fl Cross Section of Achieved Coverage Heod Down No Restrictions Repoll 800040 Wela RPV-VJC Pagtt 7 of11 13 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3C Reference Drawings
                                                                    )!}fl*                             "' 0   II I                              *lQ!J r---------~~--~-~-- - - ------,
                                                   ..             ,,.I         ..                                                                    I I'll 1wi l___::_f l_Lf I~

fOl 0 ~} l] rEJ ED LJ

                                                ~
                                                   *.                  *      .,i ~

m [)El

                                                                                                                                   .:**~          *.  ~          ..,.

1':1 Cl ~CJ f'.:-1 [':::. J

                                                          '.ictJ11ne1 S.dr    r._ .                    .  ~

Scnnnf'r 511Jt~ ,-.:-. I r= [

                                  ~-
                                            --==.,.-

I

                                                                        "**    ~
                                                                                ,:\ .

I

                                                                                        -*~..
                                                                           ", ~
  • r
  • f'><

lC' lf~ o

                                                                                                       .~\~;:

I '\'(11' I

                                                                                                                                  .J t
                                                                                                                              '?<-.
                                                                                                                                    '=-/~
                                                                                                                                           /

I ~ -

                                                                                                                                                                            ~Mh~*   .. l<W-
                                                                          ,* / \          I                1'              I/               *.,
                                                  -*--...:__        /

_ _ -*~---' I I _____L I /

                                                                                                                                  ~---          '*                       -

1 u.1r*t""-.4*l*Tt* 1:1. ~ * '

  • 1 **

i"l'f'-"'***-v*.. ~ *,.. ...,,,\'I'"

       ~ -T~t!:l'IAffU~~.         4'.1" P*** '* o n .._-... ~ *G* h   ;~..,
       ~*l*U*"~""to.#lf - *f"ll..a'"'
       ' 61'.5:oro4t.t-*.-.J~**"'!Q       ...
      "'Ht.rit;<DT..-lt"l4!1 .. r>qP*/\J l,, J -    I*""
      "J~M ~""'..     °"'
  • I n *olro--4/~fl fltn\nall""ns f
  • C. llH **h*;.
      "-'. nraeor*l""           1..1,*\14Jn ... ,.,,

G[ lllTA(lllNUCL£MCNtllC.'i j 11cAu1uor10MuN1r1 I s11L1LOillfiS1JwtLOkP'VVJC I SCALF. NOM j owr, rn."70l6t? J ~cv o Cross Section of Achieved Coverage Head Up No Reslncl1ons Report 800040 Vll<!kl RPV-VJC Page o 0111 14 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval limited Coverage NOE Coverage Plots

  • HITACHI Peach Bottom Unit-2, P2R21 RPV-V3C Reference Drawings
                                                               .ioo*                                      . _........            *J,**
                                                                ;--- - -- - -_ -.:~*"?:'..-..:. ;... :.:..~l-I                                                                   I I                                                                  I e)ruo                                                     [}lbl]

[!.) L!J L!J I

                                                                                                             ~l l!.J l!l                        I l~l {!.J i::. J                                           (1 0. 0 Stunnt!I SHJ\*      .-, _                         -it            5, 1111fll:'I 5wJ~   r'--'

r =--

                 -~~~,~,
      -~'"'..,.\V
                                                        -==---===--~
                                                                   \.
                                                                     \,
                                                                        \.\.
                                                                             ,/
                                                                        ../\.,_ ~~
                                                                                  *. /
                                                                                  .:..~~.--
                                                                                       /'-L-I 7

10 ff' I I

                                                                                                            ,,,"°'I..,

I

                                                                                                                         - - .,=7
                                                                                                                        ~-..,,*
                                                                                                                                   ....1*,.
                                                                                                                         ~---' /--..
                                                                                                                               '-./I
                                                                                                                                ./'~I
                                                                                                                                         ~-
                                                                                                                                        !I'
                                                                                                                                                    '~-
                                                                                                                                                                ~

1-~

                                                                                                                                                                                    '"**Ce... ,*1t\\'-f r -                                                         /' /
                                                                                     .,_1   I
                                                                                                                , ./ 1 I          /
                 ------                                -----  /J'                         .
                                                                                        *, 1                    ,/
                                                                                                                       ;                I   _ " ::::_...       --- - -

1 l ~lffflr"ll~t*~\.: ..........  ; .. ~q"'

        * .....~;*-liflC't'~-..... ,.,~.-
       ~*I._,,,,,,. ,.,~       l'O* l*l".;  l~*I  n 1*P5r-J""""rlf                t*f,..,. ....

l'f*S*IS'l4:tl*-'**~lio~tn

u. r lrlWl"'"'*.<'CI .... ~-.i~* 111 Virn..tU.-1C"lflf-21:*l~l.:.O"'C...-1
       *:n:*11V-.ll'l\*ll'l4'rt..\lt1,.,.H
       ._~Chdt              .. 011;,...,,,n
       ~,._.. lfp ...      \t .... t**ll\,*J*\*oo.~

GL llllA(lll NUCllAM lNllU1V j l'fAfH HIHlOr"' mut 1 J c;t-1H1. r.nuASr l WCLO Rf'V vJC I s .. Mt uoNE J uwr* .,"' ,..ou>> 11 I Fi.tv u Cross Section of Achieved Coverage Head Up L1m1ted by Core Spray P1p1ng to Woll Cleoronce RepDfl 8CXJU.40 Wuld HPV-VJC PagoYof11 15 of76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI SP2000 RPV Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R21 Weld RPV-V3C (SC3 Vertical Seam)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length e 133.00 Required Exam Area Scanned af Area Weld Length Percent EMom Volume= S0.30 Area Sq. In. Automated Automated Automated Automated 70" T-Scon CW 154 NSI A 7.4 7.11 74% 85.90 2.4% 70" T-Scan CON 154 NSI A 74 7.4 74% 85.90 2.4% 45*r-scon 156 FVJ A 429 42.9 85.3% 8590 Z7.5% 70" P-Scon UP 154 NSJ A 7.4 7.4 7.4% 85.90 2.4% 10* P*Scon ON 154 NS) A 7.4 7.4 7.4% 8590 24% 11s* P-Scon IS6 FVI A 429 429 85.3% 85.90 275% 70"T*Scon CWIS4 NSI B 7.4 7.4 7.4% 1190 03% 70" T*Scan CCW 154 NSI B 74 51 5.1% 11.90 0.2% 45" T-Scon 156 FVl B 42.9 42.4 84.3% 1190 38% 70" P-Scon UP 154 NSI B 7.4 74 74% 1190 0.3% 70' P-Scon ON 154 NS) B 74 4.0 4.0% 11.90 02% 45' P-Scon 156 FVJ B 4?.9 429 85.3% 1190 38% 70' T-Scon ON 154 NSJ 70" T-Scon CCW 154 NSI 45* T-5con 156 FVI 70" P-Scon UP 154 NSJ 70" P-Scon ON 154 NSI 45' P*Scon 156 FVJ

                                                                                                        % Total Composite Coverage -   732%

lo~ ~ 0 J l,Jj\, ~ Comments. A Automated scanning was restricted due to the proximity or Feedwoter Spargers and Core Spray p1p1ng. H

  • Autoonoted scanning was restricted due lo the proxurnty or Cori! S!)fay bracket.

Nole - Rounding methods may affect calculated values FV *Full volume. NS-Near Surroce Weld length on inches Reporl 800040 Weld RPV* V3C Page 4 0111 16 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots - HITACHI Peach Bottom Unit-2, P2R21 RPV-C6 Reference Drawings

                                                               .90*

kDrr...,'\w h: n

                                                                                               - .... ;;(WC-l't.10:*~*- - - - - - -
                                                                                                                                  ~
                                                                                                                                                 .-11.0*
                                                                                                                                            ~~~-+-~~~~~-

[] t.. ..... *... ,

                                                                                                                                    ~
                                                              ~

CJ QJ [] ctJ 1+/-1 :~~ ctJ ~ I 1111J fJ g ..:i

                                                                           ~ , .. .
                                                                                                                                                 ~a*"'         t*t.l Ii
                                                       "'rt                                                                                              *tS"T I

Shel!(o.>1u58tlow RanlJt' uopc* Supptcm,nl i. ham \lolumt" 8 S4 Sq In Supplemrnt Ii £-om VDl&Jmr:: 5197 Sq In Sl T*St on Athtt'~~d

  • 8 Sti Sq l'1 St. P*Ston Achltvtd
  • 8 St. Sq In Si T*Ston Ath~*1cd
  • Sl 91 Sq In 56 P-Scan Ach.rwd
  • 51 !11 Sq lrt Vesul Oiarnctrt ct flanqr
  • 25 LOO 1ntht'\

VC'\ul .\l'n'luth1

  • i l 9 incric./"'gt'H flomonol Clad r
  • o Hl7S irx:tws Mrf\ /Ol'dfftdSht'W 1 .. 6 U!i/6J7S*nchc's GE* HITACHI NUCLEAR ENERGY PEACH BOTIOM UNIT 2 SHEl.L S TO FLANGE WELO RPV*C6 SCALE: NONE OWG. P62-2016* 19 REV 0 Cross Section of Achieved Coverage Head CW No Restrictions Report 000600 Weld RPV-C6 Page 9ol13 17 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e HITACHI Peach Bottom Unit-2, P2R21 RPV-C6 Reference Drawings

                                                                .90*                                                         .. 110*

r- - - - - - - - -;-. ;;;~:::~::.:~r- - - - - -/-----------'-------.. e

                                                                                                                    ,.,                    u ...

8 CTb [] ( ~ 9 . f9

                                                                                                                    ~
                                                                                                                    ,..          ..       LJ LJ C1**~
                                                              ~'"'
                                                                        ~t .. ~                                      I I
                                                                                                                    ~ ~                 tJ I

I

                                                  ~ ;1*!
                                                             -bl..
                                                                        -(]

(t1l Ct-!

                                                                                                                                "'~

Scanner Side Scanner Side

                                                                                             <i           -~ . .-

45*7 I S~'t Course 5 ilrl::w flangC'Uppct Supplrmrnl 4 E11om Vclumr" 1154 Sq *n Suppltmrnt 6 f.ram \.'clumr .. 5197 So rn Sl 1*5tan Athi~td

  • 8 S.. Sq In S4 P*Scan Ach~1rd
  • 8 54 Sq In S6T SconAch1rwdaSl9TSq In 56 P Scan Achieved* 52.97 Sq In Vrnrl OIClmrter o\ flonQt'
  • 151 00 11'\Chc' Veuel Mmutm = Z 19 1r.tMsldr9fu HDmOnail CIDdT
  • D Jl75 ON:hH "41n I Ordrrl'd Shd T .. 6 125 / 6 J 75 .ncnr~

GE HITACHI NUCLEAR ENERGY PEACH BOTIOM UNIT 2 SHELL S TO ftANGE WELD RPV*C6 SCALE. NONE DWG. PBz.2016-19 REV 0 Cross Section of Achieved Coverage Head CCW No Restrictions Report 000600 Weld RPV-C6 Page 10of13 18 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e HITACHI SP2000 RPV Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R21 Weld RPV-C6 (SCS - Flange) COOE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 788.50 Required Exam Area Scanned of Areo Weld Length Percent Exam Volume = 61.51 Area Sq. in. Automated Automated Automated Automated 70° T-Scon CW {S4 NS) A 8.5 8.5 6.9% 684.25 3.0% 70° T-Scon CCW (S4 NS) A 8.5 8.5 6.9% 684.25 3.0% 45°T-Scon156 FV) A 53.0 53.0 86.1% 684.25 37.4% 70° P-Scon UP (S4 NS) A 8.5 8.5 6.9% 684.25 3.0% 70° P-5con DN IS4 NS) A 8.5 8.5 6.9% 684.25 3.0% 45° P-5con IS6 FVJ A 53.0 53.0 86.1% 684.25 37.4% 70° T-Scon CW (54 NS) 70° T-Scon CCW IS4 NS) 45° T-Scon (S6 FV) 70° P-Scon UP IS4 NS) 70° P-Scon DN IS4 NS) 45° P-Scon (56 FVJ 70° T-Scon CW IS4 NS) 70" T-Scan CCW IS4 NS) 45° T-Scon (S6 FV) 70° P-Scan UP 154 NS) 70° P-Scon DN IS4 NSI 45° P-Scon IS6 FV)

                                                                                                        % Total Composite Coverage=   86.8%

Rev O 9/lJ/O'J Comments: A - Automated scanning was limited by Guide Rods. Mainsteam Plug Hardware, and Excessive Weld beads. Note - Rounding methods may affect calculated values. FV-Full volume. NS-Near Surface. Weld length 1n inches. Report 000600 Weld RPV-C6 Page 5of13 19 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots "tJ CD Peach Bottom Unit-2 QI n

r OJ 0

Feedwater N4 Nozzle ff N4A (PEA-2-003250) 3 c

 ~                                                                   60°T NS Exam Volume = 2.8 Sq. In.

N I 60°T FV Exam Volume = 44.1 Sq. In. N 0 60°T 54(Inner15% T) Exam Volume= 9.3 Sq. In. 0

                          <t                                         60°T NS Coverage achieved = 2.8 Sq. In.

60°T FV Coverage achieved = 33.2 Sq. In.

§.=~

I 60°T 54(Inner15% T) Coverage achieved= 9.3 Sq. In.

~~,.              /
                    / --

~ffeiz / 'C.:I~ I

       ~    I I
 ~\

60°T Ii - - - - - - I 1 I "tJ' QI cc CD I I 1~ I I I I a I ro -------! 20 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  -0 Cl>

Q) g. Peach Bottom Unit-2 CD 0 Feedwater N4 Nozzle g N4A (PEA-2-003250) 3 c

 ~                                                                           60"T NS Exam Volume = 2.8 Sq. In.

N I 60"T FV Exam Volume = 44.1 Sq. In. N 0

 .....                                                                       60"T S4(Inner15% T) Exam Volume= 9.3 Sq. In.

0 er. 60"T FV Coverage achieved= 31.7 Sq. In. 60"T S4 (Inner 15% T) Coverage achieved = 6.3 Sq. In.

 ~~t:i) i                 ,,.,...

Q. I m /

 ~~:c                /
 ~~if              /
 '(,)~ii:        I                                60" T-Scan restricted due to the proximity of N11A nozzle I
       ~      I                                                                       60"T
  \~         It------                                                                   I
                                           ----~
       ~

1 I ~ tl Cl> I I lat) I I I g, ro-21 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  -0 CD Ill 0

Peach Bottom Unit-2

  ~

CD 0 Feedwater N4 Nozzle s3 N4A (PEA-2-003250) c

  ~

N = 60°T NS Exam Volume 2.8 Sq. In. N

                                                                                                         =

60°T FV Exam Volume 44.1 Sq. In. 0

 ......                                                                       60°T S4(Inner15% T) Exam Volume= 9.3 Sq. In.

0 ct 60°P NS Coverage Achieved = 2.5 Sq. In. 60°P FV Coverage Achieved = 22.4 Sq. In. 60°P & NN (Inner 15% T) Coverage Achieved= 9.3 Sq. In. I!! i= (j) i5. I m /

~~ :J:                 /

.!.cS'* / 1'> :-4 Q_ I <.> ~ i!: I

       =!I      I                                                                 so*p It - - - - - -

I

  ~\
~~              1                                       I co CD        -0   I                                        I

~ I I I I a I I

                                      -------1 lo 22 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots "O

D -

0 n

   =r-        A                HITACHI                                                        Reactor Pressur~ Vessel CD 0

s3 W' Coverage Calculat1on Sheet c

i
   ~

N 0 0 Peach Bottom Unit-2 P2R18 N4 - Feedwater Nozzle N4A (PEA-2-003250) ' COOE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 83.2 Areo Sq. In. Manual Manual Manual Manual 60" T-Scan {S6 NSI A 29.8 2.8 3.496 351 1.696 60" T-Scon {S6 FVI A 44.1 33.2 39.996 351 19.5% 60° T-Scon (S4 UCJ A 9.3 9.3 11.296 351 5.496 60° P-Scan IS6 NSI A 29.8 2.5 3.0% 351 1.5% 60" P-Scan (S6 FVJ A 44.1 22.4 26.996 351 13.196 60° P-Scan & NN (S4 UCI A 9.3 9.3 11.296 351 S.4% 60" T-Scan (S6 NSI B 29.8 2.8 3.496 9 0.096 60° T-Scan (S6 FVJ B 44.1 31.7 38.196 9 0.596 60" T-5can {S4 UCI B 9.3 6.3 7.696 9 0.196 60° P-Scan {S6 NSI B 29.8 2.5 3.096 9 0.096 60° P-Scan (S6 FVJ B 44.l 22.4 26.996 9 0.396 60° P-Scan & NN IS4 UCI B 9.3 9.3 11.296 9 0.196 60° T-Scon 156 NSJ 60" T-Scan IS6 FVI 60° T-Scan (S4 UCJ 60° P-Scan IS6 NS) 60" P-Scon (56 FVJ 60" P-Scan & N/V IS4 UC) ~  % Total Composite Coverage= 47.7%

)
D R<v.O 912l/115 Comments: A - Manual scanning was restricted, due to nozzle configuration. Wade F. Miller
?..
    °'   B- Manual 60° T-Scan restricted due to the proximity of the NllA nozzle.                                                             GE Hitachi          ~

l.eYal Ill-RT, UT, MT, FT 71/8JZl'lo

     '6  Note - Rounding methods may affect calculated values. UC* Underclod, FV-Full volume, NS-Near Surface. Weld length in degrees.       and VT-1,2,3 23 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots "lJ CD m g. Peach Bottom Unit-2 ID 0 Feedwater N4 Nozzle 53 N4B (PEA-2-003300) c:::> N 60"T NS Exam Volume= 18.0 Sq. In. I = 60"T FV Exam Volume 19.8 Sq. In. 0 N N 60"T S4 (Inner 15% T) Exam Volume= 4.3 Sq. In. I

        "      <t                                         60"T NS Coverage achieved = 0.3 Sq. In.

60"T FV Coverage achieved= 16.4 Sq. In.

            ~.                                            60"T S4(Inner15% T) Coverage achieved= 4.3 Sq. In.

I I I I I I I 60"T I I I--

"C DI        I               I IQ CD        I               I I

14' I 0 ICC __ _, I 24 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots i] CD ID g. Peach Bottom Unit-2 m Feedwater N4 Nozzle

=

0 0 3 N4B (PEA-2-003300) c

J N

60"T NS Exam Volume = 18.0 Sq. In.

                                                                                     =

60"T FV Exam Volume 19.8 Sq. In* N 0 N 60"T S4 (Inner 15% T) Exam Volume =4.3 Sq. In. I "- = 60"P NS Coverage Achieved O Sq. In.

                <t                                                                         =

60°P FV Coverage Achieved 7.1 Sq. In.

             ~   I 60°P & NN (Inner 15% T) Coverage Achieved= 4.3 Sq. In.

I I I I I I I I I--

-0 D>         I (Q

CD I 1~ I I a I 1~ r-25 of76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots "U m n Peach Bottom 2 - 2R 19

T Weld RPV-N4B-NV Feedwater N4B (PEA-2-003300) i 3

Fall 2012 I\) l\l CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE

~                                                                                    Percent CD Weld Length = 360.      Required Exam    Area Scanned        of Area       Weld length      Percent Exam Volume= 42.1          Area Sq.In.       Manual           Manual           Manual        Manual 60" NS T-Scan    I A             18.0            0.3              0.7%            360            0.4%

60" S6 T -Scan I A 19.8 16.4 39.0% 360 19.5% so* S4 T-Scan I A 4.3 4.3 10.2% 360 5.1% 60° NS P*Scan A 18.0 0.0 0.0% 360 0.0% 60" S6 P-Scan A 19.8 7.1 16.9% 360 8.4% 60" 54/IRS Scan A 4.3 4.3 10.2% 360 5.1% 60" NS T -Scan 60" S6 T -Scan 60" 54 ~scan 60" NS P-Scan 60" 86 P-Scan so0 s4/IRS Scan I I I I

                                                                                    % Total Composite Coverage =     38.5%
~

cc CD Commerits: A* Si:anning limited due-to noille contlguration. I~g_ r Note

  • Rounding methods may affect calculated values.

26 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots "1J (l) D> 0 Peach Bottom Unit-2

 ':r ID 0

Feedwater N4 Nozzle 6' N4C (PEA-2-003400) 3 c S: 60"T NS Exam Volume = 2.8 Sq. In. N I 60"T FV Exam Volume = 44.1 Sq. In. N 0 60"T S4(Inner15% T) Exam Volume= 9.3 Sq. In. 0 I '\. ct 60"T NS Coverage achieved = 2.8 Sq. In. 60"T FV Coverage achieved = 33.2 Sq. In. 60"T 54(Inner15% T) Coverage achieved= 9.3 Sq. In.

                  /
                     / ---
               /

I I I 60"T It - - - - - - I "1J D> 1 I co (l) I I I f-a I I I I Wade F. Miller GEHltachl

                               -------I joe                                                                                                 Level 111-RT, lJT, MT, PT and\lf..
                                                                                                       ~          'lfzr,/?_o IC 27 of76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

 \1 QI m

0 Peach Bottom Unit-2

 ;;J" OJ 0

Feedwater N4 Nozzle

 ~

0 N4C (PEA-2-003400) 3 c N N

  .                                                                        60"T NS Exam Volume = 2.8 Sq. In.

60"T FV Exam Volume = 44.1 Sq. In . 0

 ~

60"T S4(Inner15% T) Exam Volume= 9.3 Sq . In. 0 I "'- = ct 60"P NS Coverage Achieved 2.5 Sq. In.

                                                                                                            =

60"P FV Coverage Achieved 22.4 Sq. In. 60"P & NN (Inner 15% T) Coverage Achieved= 9.3 Sq. In .

                      /
                   /
                /

I I I 60"P Ii - - - - - - I

\1 Q)       1                                           I

<O I Wade F. Miller ID I GEHitachl 1~ I I Level 111-RT, UT, MT, PT ______ ,I I I and VT-1.2,3 a I

                                                                                                         ~           ?/u/cb,,a loet 28 of76

Unit2 Peach Bottom Atomic Generating Station Fourth 151 Interval Limited Coverage NOE Coverage Plots

   ~

n Reactor Pressure Vessel Coverage I

   ~

gi HITACHI 8 Calculation Sheet 3 c::::>

  ~                                                                        Peach Bottom Unit-2 P2R18
 *"'                                                                           N4 - Feedwater Nozzle 8

0 N4C (PEA-2-003400) CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Areo Weld Length Percent Exam Volume = 83.2 AreoSq.ln. Manual Manual Manual Manual 60" T-Scon (56 NSI A 29.8 2.8 3.4% 360 1.7% 60" T-Scon (56 FVI A 44.1 33.2 39.9% 360 20.0% 60" T-Scon (54 UCI A 9.3 9.3 11.2% 360 5.6% 60" P-Scon 156 NS) A 29.B 2.5 3.0% 360 1.5% 60" P-5con 156 FVI A 44.1 22.4 26.9% 360 13.5% 60° P-Scon & NN 154 UCI A 9.3 9.3 11.2% 360 56% 60" T-Scon {56 N51 60" T-Scon 156 FVI 60" T-Scon 154 UCI 60" P-Scon (56 NSI 60" P-Scon 156 FVI 60° P-Scon & NfV (54 UC) 60" T-Scon (56 NSI 60" T-Scon 156 FVI 60" T-Scan 154 UCI 60" P-Scon (56 NSI 60° P-Scon (56 FVI 60° P-Scon & NN 154 UCI

-0                                                                                                              % Total CompoSJte Coverage=        47.8%

a IQ '.,_ ..J r- ***** Rev. 0 9123/0S 111 rs. Comments: A - Monuol scanning was restricted. due to nozzle configuration. GEHltachl Level 111-RT, UT. MT, PT and Vf-1,2,3 ~ Note - RoundinQ methods moy affect calculated values. UC-Underclod. FV-Full volume. NS-Near Surface. Weld length in degr~ u1fw.. VI l:Z/'21l10

                                                                                                                                             ~.l~"A-kt
                                                                                                                                                 ~IP
                                                                                                                                                         ~.+Ml!!C 29 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots 0

  • HITACHI RPV Scan Plan Peach Bottom Unit-2 N4 - Feedwater Nozzle N4D (PEA-2-003soo)

Inner 15%TS5 EumVolume=4.3 Sq. In. ea* 54 Exam Volume =4.3 Sq. an. so* 58 Eum Volume* 37.3 Sq. In. Inner 15%T 55 Exam Volume Achieved= 4.3 Sq. In. ao- 5" Exam V°'ume Achieved * .C.3 Sq. In. so* 58 Exam Volume Achieved

  • 15.3 Sq. In.

ct D.O" Examinallon wilume l.a.w. Code ca.. N-613-1 Cl~nllal examln.tlon of the oulerl5%T ii not required l.a.w. Ille 2001 Edlllon WI 2003 Addenda. Mid""' Near 111rlilee T-scan nol - - due lo

  • O" 14.0" 60"T 8D'T N4 Nozzle to Shell Scan Limits at Top Dead Center

{)~,r ~ ,/ p 30 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots u v

  • HITACHI RPV Scan Plan Peach Bottom Unit-2 N4 - Feedwater Nozzle N4D (PEA-2-003500) ct 0.0" 15.3" llO"T N4 Nozzle to Shell Scan Limits at 90° I 270°
                                                                                         ~~'       -; oFi?

31 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots G 0 0

  • HITACHI Manual RPV Nozzle Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R20, 2014 N40 N4D (PEA-2-003500)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area of Area Length Percent Exam Volume = 41.6 Area Sq. in. Scanned Scanned Scanned Scanned 60" T-Scan IS61 A 37.3 lS.3 36.8% 360 18.4% 60" T-Scan {S41 A 4.3 4.3 10.3% 360 S.2% IRS P-Scon 1551 A 4.3 4.3 100.0% 360 S0.0% 60" T-Scan {561 60° T-Scan {541 IRS P-Scan !SS) 60" T-Scan {S61 60" T-5can {S4) IRS P-Scan 15Sl I 60°T-5can156) 60" T-Scan {S4) IRS P-Scan ISS) 60" T-Scan IS6) 60" T-Scan IS4) IRS 1-'-Scon !SSJ

                                                                                                   % Total Composite Coverage=        73.6%

Rev 0 9/20/]J Comments: A - Manual scanning was restricted due to the nozzle configuration. Note - This coverage calculation is valid for ASME Section XI. 2001 Edition w/ 2003 Addenda, 2004 Edition w/ No Addenda and the 2007 Edition w/ 2008 Addenda Note - Rounding methods may affect calculated values. S6 - Supplement 6, S4 - Supplement 4, SS Supplement - S. Weld length in degrees. 32 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots e HITACHI 0 RPV Scan Plan u Peach Bottom Unit-2 N4 - Feedwater Nozzle N4E (PEA-2-003soo) IMer 15%T 55 Exam VokJme

  • 4.3 Sq. In.

60 54 E*am votume

  • 4.J Sq. In.

so* 56 Exam Volume* 37.3 Sq. In. Inner 15%T SS Exam V<mme Acnieved,.. 4.3 Sq. In, 60' 54 Exam Volume Acl1ffNed - 4.3 Sq. In. so* S6 Exam VoUne Achieved a 15.3 Sq. In. It Euminatk>n voUne l.a.w. Code Case N-613-1 Cin:umtemitiol ....,.._,DI Ille DUlef BS'Y.T o.o* is nae rvqujrad l.a.w. the 2001 Edilfon w/ 2003 Addenda. Near surface T *&can not required due lo weJd cap restrictk>n. ii 4 o* 14.0" 60 T 60'T I - I N4 Nozzle to Shell Scan Limits at Top Dead Center flite,e :5 ar5l 33 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots v Q Q

  • HITACHI RPV Scan Plan Peach Bottom Unit-2 N4 - Feedwater Nozzle N4E (PEA-2-003500) ct a a*

II

                            ,l I '

I ';" 1s.3*

                          .r I                                        60"T J,
                                                                                  ~

N4 Nozzle to Shell Scon Limits at 90" / 270"

                                                                                                    ,/}~ ~J?

34 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

      \._,)
  • HITACHI Manual RPV Nozzle Examination Coverage Calculation Sheet Peach Bottom Unit-2, P2R20, 2014 N4E N4E (PEA-2-003500)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area of Area Length Percent Exam Volume= 41.6 Area Sq.in. Scanned Scanned Scanned Scanned 60" T-Scon (56) A 37.3 15.3 36.8% 360 18.4% 60" T-Scon (54) A 4.3 4.3 10.3% 360 S.2% IRS P-Scon ISSl A 4.3 4.3 100.0% 360 S0.0% 60" T-Scon (S6) 60° T-Scon (S4) IRS P-Scon ISSJ 60° T-Scon (56) 60° T- Scon (S4) IRS P-Scon ISSl 60° T-Scon (56) 60° T-Scon (54) IRS P-Scon !SSJ 60" T-Scon (S6) 60" T-Scon (54) IRS P-Scon (SS) I

                                                                                                   % Total Composite Coverage=        73.6%

i1ev a 91ZO/l.3 Comments: A - Manual scanning was restricted due to the nozzle configuration. Note - This coverage calculation is valid for ASME Section XI. 2001 Edition w/ 2003 Addenda. 2004 Edition w/ No Addenda and the 2007 Edition w/ 2008 Addenda Note - Rounding methods may affect calculated values. 56 - Supplement 6. 54 - Supplement 4, SS Supplement - S. Weld length in degrees. 35 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots v

  -.                                                       0                                                                              0

\, I HITACHI RPV Scan Plan

  ~

Peach Bottom Unit-2 N4 - Feedwater Nozzle N4F (PEA-2-003700) Inner 15%T 55 Exam Volume= 4.3 Sq. In. 50* 54 Exam Volume = 4.3 Sq. In. 60' 56 Exam Volume= 37.3 Sq. In. Inner 15%T 55 Exam v~umeAchteved = 4.3 Sq. In. 60' 54 Exam Volume Achieved = 4.3 Sq. In. 60' 56 ExamVokJme Achieved= 15.3 Sq. In. ct Exammalion vok.ime l.a.w. Coda Case N-61~1 Clrcumferl!nlial examlnatlon of the outer 85%T a.a* Is nol requk'ed l.a.w Iha 2001 Edllion wl 2003 Addendil. Near surface T..scan not req~ due lo weld cap restriction. 4.o* 14.a' 6a'T 6D'T N4 Nozzle to Shell Scan Limits at Top Dead Center Mtecr 0~r.P 36 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots c* 0 I

       ) HITACHI                             RPV Scan Plan Peach Bottom Unit-2 N4 - Feedwater Nozzle N4F (PEA-2-003700)
                                 't 0.0" 15 J" 60"1 N4 Nozzle to Shell Scan Limits at 90° I 270°
                                                                                                  ~re,,.- 7 cJ rF 37 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots v 0 0 Manual RPV Nozzle Examination

  • HITACHI Coverage Calculation Sheet Peach Bottom Unit-2, P2R20, 2014 N4F N4F (PEA-2-003700)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area of Area Length Percent Exam Volume= 41.6 Area Sq. in. Scanned Scanned scanned Scanned 60" T-Scan (S6l I A 37.3 15.3 36.8% 360 18.4% 60"T-Scan (S41 I A 4.3 4.3 10.3% 360 5.2% IRS P-Scan 1ss1 I A 4.3 4.3 100.0% 360 50.0% 60" T-Scon (S61 60°T-Scon (S41 IRS P-Scon (SSI 60° T-Scon (S61 I 60° T-Scon {S41 I IRS P-Scon (SSI I 60° T-Scon (S61 60" T-Scon {S41 IRS P-Scan (SSI 60° T-Scan {SGI 60°T-Scon (S4l IRS P-Scon ISSI

                                                                                                   % Total Composite Coverage=        73.6%

R@11 0 9/ZO/U Comments: A - Manual scanning was restricted due to the nozzle c6nfigurat1on. Note - This coverage calculation is valid for ASME Section XI. 2001 Edition w/ 2003 Addenda. 2004 Edition w/ No Addenda and the 2007 Edition w/ 2008 Addendol Note - Rounding methods may affect calculated values. S6 - Supplement 6, S4 - Supplement 4, SS Supplement - 5. Weld length in degrees. 38 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots (. HITACHI RPV Scan Plan g. m 5!. ~ Peach Bottom Unit-2 dl N5 - Core Spray Nozzle N5A (PEA-2-003800) ~ 1nne1 lS'tiT 55 f1eomVolume~ 4.7 Sq. In

                                                               &o* S4 Eicom Volume= 4 7 Sq. In 60" S6 bom Volume* 39.7 Sq. In.

loner IS'llTS5 EAOm VolumeAchtev..-d

  • 4.7 Sq. In 60" 51, t.om Volumt llclueved
  • 4.7 Sq. In.

60'" 56 ENom Volume Achieved* 17.6 Sq. In Ewam1nohon volume 1.c.w. Code Cose N*61l*l Circymferenual e1itom1not1on or the ouler 85'6 T

                                       <t                      15 not roqu*ed 1.0.w. the 2001 Edluon w/ ZDOJ llrtdendn Nr'Dr 5urfoce f~tonnol rrquu~ due toweki cop r~stric11on 40                                                 lh'.i' 60'1'                                              60'1' 1P

~~ lS () NS Nozzle to Shell Scan L1m1Ls at Top Dead Center ~ .......

'      ':Q_

~o 39 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI RPV Scan Plan
..g.
-a     ~-

m 0 Peach Bottom Unit-2 5

..,3                                                     NS - Core Spray Nozzle                                   N5A (PEA-2-003800)
;E                                                       1nntr IS% T SS E.<om Volume
  • 4.7 SQ. 111.
~

60" S* fl<am Volume= 4. 7 Sq. In. 60" S6 fxcm Volum*

  • 39.7 Sil In 1nnl!f 15%T 55 El<am VolumeAchlM!d* 4.1 SQ In.

so* St. EJcam Vohun! Achieved., 11.7 Sq 111 60" 56 u.om Volume Acluvod

  • 17.6 Sq. In.

borntnalt0t1 votume 1.0 .w Code Case N*61 ]-1 Cwrumferenual eJCOrmnobon ~me- outt"r 8S'6iT

                                 <t                      1s not required 1.0.w. lhe 2001 Ed*tlDfl w/ 2001 Addendu Near surface T*scan not requirl!d due 10 "Neid cap res.tnct1on.

I 1,.0* 60"T I 1&.s-OO"T i~ iS'~ NS Nozzle to Shell Scan Limits ot 90° and 270° ~~ ~(); 40 of76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

     @jJ HITACHI
      **~'I Manual RPV Examination Coverage Calculation Sheet Peach Bottom Unit 2 I P2R21 N5A (Noz-RPV)                              NSA (PEA-2-003800)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exom Area Scanned of Arne Wald Length Percent Exam Volume = 44.4 Area Sq. In. Automated Automated Automated Automated so* T-Scan rss NSI A 18.9 0.3 0.7% 340 0 .3%. 60" T-Scan (56 FVJ A 22.8 17 3 390% 340 18.4% 60" T-Scan !S4J A 4.7 4.7 10.6~~ 340 5. 0~~ IA:> P-Scan (MJ A 4.7 4.f 1U0.U% 340 47.<!% 60" T-Scan 156 NS\ B 16.9 0.3 0.7% 20 o.oi* so* T-Scan (56 t-VJ B 22.B 173 39.0% 20 1.1% so* T-Scan (54) B 4.7 4.2 9.5% 20 0.3'%

                  '""' t'-::>can (<>"          B                4. 7              4.7        100.0%              20                   2.8",(,

60' T-Scan !56 NSl 60' T-Scan (56 t-VJ so* T-Scan (54) IRS P*::.can (54) 60" T-Scan 156 NSI 60' T*Scan 156 FVl 60° T-Scan !S4l

                 '""' t-'-::;can (S4J
                                                                                            % Tolal Composite Coverage"              75.1~*

q,..,....., ,1 Ill IC\ I I Comments: A

  • manual scanning was limited due 10 the nozzJe conligurallon.

B - Manual 60" T*scan was restncted due to lhe prox1m1ly of Iha 1nsulallon suppon ring. Examination vOlume is in accordance wilh Code Case N-613-1 Note - Rounding melhocls may allecl calculaled values. UC-Underclad. FV*Full volume. NS-Near Surface. Weld lenglh In degrees . fJA<<<: /0 of /0 f/ *1*ll. lfl!} 41 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots v 0 fl' HITACHI RPV Scan Plan Peach Bottom Unit-2 N9 - CRDH Nozzle N9 (PEA-2-004000) Inner 15%T 55 Exam Volume =4.3 Sq. In 60° 54 Exam Volume = 4.3 Sq. In. eo* 56 Exam Volume= 31.3 Sq. In. Inner 15%T 55 Exam VOiume Achieved= 4.3 Sq. In. 60" $4 Exam Volume Achieved= 4.3 Sq. In eo* 56 Exam Volume Achieved= 15.3 Sq. In, Examinallcn volume 1 aw Code case ~13-1 Cira.wnfentnllal ennunabon DI the oulllr 85%T ct IS nol requl!ed 1a w. the 2001 Edillon w/ 2003 Addenda DD" Near surface T-scan not requred due to weld cap restnctlon 13 5" 6D"T 6D"T N9 Nozzle to Shell Scan Limits at Top Dead Center {)(¢.. 7 o(q 42 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots w v

  • HITACHI RPV Scan Plan Peach Bottom Unit-2 N9 - CRDH Nozzle N9 (PEA-2-004000) ct 00" 60"T 15.2" 60"1' N9 Nozzle to Shell Scan Limits at 90" I 270" A~p f2 ()r er 43 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual Nozzle to Shell Exam Plan Plant and Unit ID: Peach Bottom Unit-3 Component N9 (PEA-2-004000) Outage: 2R20 Cal. Block: See Project Level Ill Procedures: Examination: GEH-UT-300 Sizing: GEH-UT-304 Examination: GEH-UT-311 Sizing: GEH-UT-309 Extents: Examiner: Analyst: Examine 360". See attached Inner Radius Reauirements sheet for details. N/A N/A 60° Radial Scan S4 60" Radial Scan S6 Full Volume 55" N/V Scan SS CW/CCW Limitations: Scanning will be limited due to the nozzle configuration. Previous Results: See Project Level Ill Comments: Examination volume i.a.w. Code Case N-613-1. Circumferential examination of the outer 85%T volume is not required i.a.w. the 2001 Edition w/ 2003 Addenda. Near surface radial scan is not applicable due to the weld cap configuration.

                                                                                                   \1w
                                                             ~,,~,.

5ofC/ ) Chris Minor 10/23/14 /cJ.Z<NV Prepared By: Date: RfiefedBy\ ,--.... Dote: I t , / 4 ~~

                                                                    <::.:::.-] Sf EvNJ to *Z'f-ZDI        / Yf;t1 t/x l'<f 44 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

     "'Q
    ~
D
    ~

C>> g 0 3 c:

J
    ~

Peach Bottom Unit-2 N 0 0 RECIRCULATION OUTLET N..tA - -- .. --* 60" NS EXMn Volune

  • 5& 6 Sq. In so* FV E.xa'n VOllne .. SJO Sq_In.

lrl'Mlr 15%T W"Tl Volume* 1t.6 Sq. h. 60" NS T-ScM...::"'tWd* <I .I Sq In 00" FV T..sc.i ~ctunlld i:: 40.1 Sq h

                               /
                                    <t                          lnnor 15%T~~* 11.&SQ.ln.
                             /

I I t=oa. i ~ 'I i!. ;- I'll CD I

~~i:-n                I I

.i.J.£l~~

<.I      ~      -

I I

         ~      ..,

(I) I 60"T I i1 I r-----

  "O                                                               I Col                1 IQ                                                                 I QI
                ~    I I                                             I 14\             a    I                                             I
 -~

0

                                        --------4 I

45 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots II

  ~

ga

 ~

c:

 ~
 ~
 ~
 .....                                                              Peach Bottom Unit-2 0

RECIRCULATION OUTLET N1A 60" NS £um V~ * ~. b ~ 111 60" FV E 116m VOlul'l\9 .. 5..J D SQ Ii "1nvr 15'4T E,ca1r. VN'nl

  • U ~So In
          \                                                        60" NS P.scM\     ~
  • U 60" F\/ P*Scan ~
  • Z2..'J SQ. 11'1.
                                                                                                      ~. Ill.
             ~*                                                    ,,..., '5>'-T S.:an ~
  • n .e SQ II\

i=~i i ~

    ~~l:n
   'N~ i::
   *~~ <l    -*
             ~
       ~
          ~\               I t--   - --
""C m

co

~
          -- \

N

                  \

I I I I

                    ~-~---

I~ 0 I 0 I 2.. --------1 ~ 46 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots l I c a 81 HITACHI Reactor Pressure Vessel Coverage Calculation Sheet j.. Peach Bottom Unit-2 P2R18

  ~

0 Nl- Recirculation Outlet NozzJe N1A CCJCJfOI~* ~AMA TOTAL Wut c:oV.tKA1GI: Pttunl WIUl*"idU J60. Reql.llf*d ENom N.o5'°nn.d <it~eo Wtldl.e"9Ch P~t EllOmYol1.1ne* 121.2 Al*Sq. In. Manuol Honuol Monual Monual 61)* I *Sci>'\ IS6 NSI

  • Sb6 111 3~ JOO  :~

W" l*Sccn IS6 fV I fir 1-S;;;in 154 UC 60° P.Sco- *S6 NSI s; 116

                                                                                         '5~6 ii.)
01i in l JJI~

861{ le'* 300 JOO

                                                                                                                                                }60 1659' 4 l'i!.

1*~ f:iJ" P*S.:::t1 ISO FVJ

                              <<r P-~on 0. HI~' i::..a UO J..                  S3"
16 18'~

9~"' 360 jlJO ,_

                                                                                                                                                                ~~
                                                                   "                     11" 6~* f*Scori 156 NSI W° J *Sc<: II :56 fVl 60'" t *Sc~ IS<< UC!

bO" P*SCO'I tS6 ~ 60" P-Scen IS6 P.il W P S<on &. NN !SA I.Ct o~ l*Scon IS& N~ 60" '*Scctl ~ fV)

                                  .:q T*<;c;ontS4 ~O 60" P-S<..cn 1$6 t>$1
                                  ~ P.Sc~ IS6 f'\11 c.v- P* 5 con ~ NI 11 cs.r. I.Cl
                                                                                                                         'If. r()(O (.Omp::)S&~Cor.'tt~
  • Ja..,.,.

l <;~T~b A. M;Jl",.O KQ-..nin11Win1ntl9't~. j.Jf' le no.&.'W<:cnlig.ifOKW" u1~r1.c. I= lAill..:i.t GEHl&adll

                                                                                                                                                                                   ,._ t '-l l ~
'°
~

lAYel 11-R'I'. LIT. MT. 1-'T

                                                                                                                                                           .mVJ:.i~ ~

...0 'I~:<

  • IQ.irod 11c.1 *~u-acs 1001 oi'te1 colo;:~&e:j .Q11,;cs UC *\,;nGCftlod. f\**f I.I *JOlvm(', NS*t~ SU1ioct w~ lc'lir:h ,~ dC'Jlec!
                                                                                                                                                                       ..  ~,
                                                                                                                                                                               'f/tJ/loJo
                                                                                                                                                          ~\~rt*_                 -1.,
                                                                                                                                                             ~'"11=--=v* --                      y:
                                                                                                                                                                         ;,.-,:;:~ (     Ari.

47 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

         ~~)
          ~I HITACHI                            RPV Scan Plan
  ~
  ~

m

  !?.
  ~

m

  ~

Peach Bottom Unit-2 N1 - Recirc Outlet Nozzle N1B (PEA-2-004200) Inner 15%TS5 EJ1Dm Volume= 6.3 Sq. In. 60' 54 Exam Volume = 6.3 Sg. In. 60' S6 Ellam Volume= 55.3 :>q. In. Inner 15".!.T 55 Exam Volume Achieved = 6.3 Sq. In. eo* S4 Exam Votumo Achieved= 6.3 Sq. In. 50" SS Ellam Volume Achieved= 19.4 Sq. In. Examination volume l.a.w. Code Case N-613-1 Clrcumlerenllal examination o( the outer 85%T

                                           ~                   Is not requited l.a.w. the 2001 Edition w/ 2003 Addenda Near sUllaee T-scan not tequlred due to weld cap
                                            *,                 resllk:tlon.

ij u* 16. 1" 60"T 60"T I

                                          *,i
xJ J~

Nl Nozzle to Shell Scan Limits at Top Dead Center

!.!I .......

,£- ~ 48 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom Unit-2 N1 - Recirc Outlet Nozzle N1B (PEA-2-004200> Inner 15%T S5 Exam Volume= 6.3 Sq. In.

                                                                           =

60° S4 Exam Volume 6.3 Sq. In. 60" S6 Exam Volume= 51.9 Sq. In. Inner 15%T S5 Exam Volume Achieved = 6.3 Sq. In. 60" S4 Exam Volume Achieved = 6.3 Sq. In. 60" S6 Exam Volume Achieved= 17.6 Sq. In. Examination volume l.a.w. Code case ~13-1 Circumferential examination of the outer 85%T I& not required l.a.w. the 2001 Edition wl 2003 Addenda. Near surface T-1>C8n not required due ID ~ cap re&trictk>n.

                                                                                                         ~'6 5Jotll 49 of76

Unit2 Peach Bottom Atomic Generating Station Fourth 151 Interval Limited Coverage NOE Coverage Plots

   .)           HITACHI                                                   Manual RPV Examination Coverage Calculation Sheet Peach Bottom Unit 2 I P2R21 N1 B (Noz-RPV)                               N18 (PEA-2-004200)

CODE CROSS-SECTIONAL AREA TOT AL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 58.2 Area Sq. in. Automated Automated Automated Automated SO" T*Scan (SS NS> A 27.3 0.0 O . O~*a 380 0.0% 60" T*Scan CSS FVI A 24.S 17.6 30.2% 360 15.1~~ 60" T*5can IS4l A 6.3 6.3 10.8% 3SO 5.4% IH::> l"*::>can (54) A 6.3 6.3 100.0% 360 50.0% SO" T-5can !SS NS} 60" T-5can 156 FVl 60" T-Scan IS4l IH::> l"*:Scan (S4) so* T*Scan (56 NS! so* T*Scan ISG FVl so* T-Scan (54) IRS P-Scan (S4) so* T*Scan 1ss NS) 60° T-5can (56 FV) 60" T*Scan 1541 IRS P-Scan (S4)

                                                                                          "lo Total Composite Coverage=     70.5~.

Hl'Ydl"fl 111'1 !111 ' Comments: A

  • manual scanning was h1T11led due to the nozzle conligurabon.

Examination volume ts tn accordance w1lh Code Case N*G I 3-1 Nole* Rounding melhods may affect calculated values. UC*Underclad, FV-Full volume. NS-Near Surface. Weld length in degrees.

                                                                                                                            '1.1..to I I   of { I 50 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots

""D ID m

Peach Bottom Unit-2 0

r tD Recirc Inlet N2 Nozzle
~                                                                           N2A (PEA-2-004300) 3 c
i 60° NS Exam Volume= 19.4 Sq. In.

~ = 60° FV Exam Volume 28.2 Sq. In. N 60° (Inner 15% T) Exam Volume= 6.0 Sq. In. 0 N so* NS T-Scan achieved =2.2 Sq. In. 60° FV T-Scan achieved = 25.1 Sq. In. 60° (Inner 15% T) T-Scan achieved= 6.0 Sq. In. ct I I I I I I 60°T 60°T l I L_ "'ti I I ~ I I ID I 1~ I I a -----l 1~ 51 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

~

Ill Peach Bottom Unit-2 0

r DJ 0

Recirc Inlet N2 Nozzle g N2A (PEA-2-004300) 3 c:

J so* NS Exam Volume =19.4 Sq. In.

so* FV Exam Volume =28.2 Sq. In.

~                                                                          so* (Inner 15% T) Exam Volume= 6.0 Sq. In.

N 0 N so* NS P-Scan achieved =0.8 Sq. In. so* FV P-Scan achieved= 11.1 Sq. In. Inner 15%T Scan achieved= S.7 Sq. In. it I I I I I I so*p so*p so*p I I I I I L-I

~

IO CD I I 1~ I I a L-1~ 52 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots ID l'l

 =i-Peachbottom 2 - 2A19 0"                                                                                                          N2A (PEA-2-004300)

Weld RPV-N2A-NV Recirculation Inlet

 ~                                                                      Fall 2012 3

I\) I\) CODE CROSS*SECTIONAL AREA - - - -TOTAL CODE COVERAGE

 ~                                                                                      Percent U>

Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume= 53.6 Area Sq. In. Manual Manual Manual Manual 60" NS T*Scan I A 19.4 2.2 4.1% 360 2.1% ao* S6 T-Scan I A 28.2 25.1 46.8% 360 23.4% 60" S4 T *Scan I A 6.0 6.0 11.2'YD 360 5.6% 60° NS P--5can A 19.4 0.8 1.5% 360 0.7% 60" 56 P-Scan A 28.2 11.1 20.7% 360 10.4% so* S411AS Scan A 6.0 6.0 11.2% 360 5.6'l'D so* NS T -Scan so* 56 T-Scan so* S4 T-Scan 60" NS P~Scan so* 56 P-Scan S0"54/IRS Scan

                                                                                       % Total Composite Coverage "'    47.8%

lID -

 .,., IComments: A - Scanning limited due to nozzle configuration
  • la loc Note
  • Rounding methods may affect calculated values.

53 of 76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots lf J!1 HITACHI RPV Scan Plan "ti ~- ~ <D !l. c 3 N Peach Bottom Unit-2 "ti <D N2 - Recirc Inlet Nozzle N2D (PEA-2-004soo) ~ lnnar 15%T 65 Exam Voluma 2 4.3 Sq. In.

                                                                 &D" S4 E*am Volume= 4.3 Sq. In.
                                                                 &D" SB E1om Volume= 36.3 Sq. In.

IMur 15%T SS Exam Volume Achieved = 4.3 Sq. In. 60" S4 E*om Volume Achieved= 4.3 Sq. In. GO* S6 U*m Votum* Athhtvtrd

  • 15.4 Sq, ln.
                               <t                                Ellamln&Uon voiuma l.a.w COCla C.&o N-613-1 Clrcumforanltaf exem~ of lho outer 86%T o.o*                              II nol llq1M'11d 1.1.w. 1111 2001 Edfflon WI 200J Addenda.

Nttat surf..ce T-sCB11 11ol mqulred due to weld cap restrlcUon . 4 .0- 14.0"

                                             &D"T                                             &O'T p

1~ ~ --0 N2 Nozzle to Shell Scan Limits at Top Dead Center ~ 54 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots QI n m 0 s3

    "'"lJ HITACHI 11 RPV Scan Plan Peach Bottom Unit-2 N2 - Recirc Inlet Nozzle m                  '    \                                                                               N20 (PEA-2-004600)

I

    ~                         \
                                \
                                   \

rt o.o* I' ""' ~.

                     ~I
                                                                                                                              ~~

[t,~-~----------~ ------1

                                                                        \
                                                                          '                                                  154" I'             i "/'!'
                                                               ..--/- ' / -I1                                        ~--------- -------
                                                                   'I / I,                                       ---

J-t,.--' I I -

                                            /       *            { I                                      --

1

                                         / - ' ::<I' I
  • I .--
                                                 ~-I JI-                                        -                                            --
                     \
                                                                                 ~--~---
                       \ .-' .* .-                I     1 I -I      1     -.,rI   .------ - - -
                          "'=~=-=,-~---~-=~~
                       '\,,                     I I               IL                                           _

p fi 1~

---{)

N2 Nozzle to Shell Scan Limits at 90° and 270° (>I ~ 55 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual RPV Examination (. ) HITACHI

       ~-                                                            Coverage Calculation Sheet Peach Bottom Unit 2 / P2R21 N2D (Noz-RPV)                                N2D (PEA-2-004600)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length= 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 40.6 Area Sa.In. Complete 60" T*5can 156 NS! A 16.5 0.1 0.2% 360 0.1% 60" T-5can (56 FV) A 19.8 15.3 37.7% 360 18.8% so* T-Scan (541 A 4.3 4.3 10 . 6~0 360 5.3% IHS !-'-Scan 1"'4) A 4.3 4 .3 100.0% so.ll'lo so* T-Scan 156 NSl so* T-5can 156 FV> 60" T*Scan (S4l IRS P-Scan (S4J 60" T-Scan (56 NS) so* T-Scan rss FVl 60° T-Scan IS4l IRS P-Scan (S4) so* T-Scan !SB NS! 60" T-Scan IS6 FVl so* T-Scan IS4l IHS P-scan (54)

                                                                                          % Tolal Composile Coverage=         74.3%

f\vY1H*:J 1(1'10JI] Comments: A - manual scanning was lirniled due lo Iha noZ2le conhgura~on . Examination volume 1s m accordance with Code Case N-613*1 Nole - Roundmo methods may aflecl calculaled values. UC-Underclad, FV-Full volume, NS-Near Surface. Weld lenolh in deorees. {)<..6 q or q lt*3*Ksl@ 56 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots G u

  • HITACHI RPV Scan Plan Peach Bottom Unit-2 N2 - Recirc Inlet Nozzle N2F (PEA-2-004soo)

Inner 15%T 55 Exam Volume= 4.3 Sq. In 50* 54 Exam Volum* = 4.3 Sq. In.

                                                           &0* 56 ExM1 Volume = 36.3 Sq. In.

Inner 15%T 55 Exam Volume Achieved* 4.3 Sq. In. 50* 54 Exem Volume Achieved = 4.3 Sq. In. 50* S6 Exam Volume Ach&eved ~ 15... Sq. In. ct. Exanunation volume i.a.w. Code Case N~13-1 Cira.omlerenlial examinalion cl lhe outer 85%T o.a* is nol requored l.a.w. lhe 2001 Edilian wl 2003 Addenda. Near surface T-oan nol Jequired due lo ....id cap resmdion. 14.0-6o*T N2 Nozzle to Shell Scan Limits at Top Dead Center 57 of76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots v 0 0

  • HITACHI RPV Scan Plan Peach Bottom Unit-2 N2 - Recirc Inlet Nozzle N2F (PEA-2-004800) ct o.o*

N2 Nozzle to Shell Scan Limits at 90° and 270° 58 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi lnteival Limited Coverage NOE Coverage Plots G ()

  • HITACHI Manual RPV Examination Coverage Calculation Sheet Peach Bottom Unit 2 I P2R22 N2F (Noz-RPV) N2F (PEA-2-004800)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exom Areo Scanned of Area Weld Length Percent Exam Volume = 40.6 Area Sq.in. Automated Automated Automated Automated 60° T-Scon (S6 NS) A 16.5 0.1 0.2% 360 0.1% 60"T-Scan IS6 FVI A 19.8 15.4 37.9% 360 19.0% 60" T-Scan IS4) A 4.3 4.3 10.6%. 360 S.3% IRS P-Scan (S41 A 4.3 4.3 100.0% 360 S0.0% 60" T-Scan IS6 NS( 60" T-Scan (S6 FVI 60" T-Scan (S41 IRS P-Scan (541 60" T-Scan (S6 NS) 60" T-Scan IS6 FVl 60° T-Scon IS41 IRS P-Scan IS4) 60" T-Scan IS6 NSI 60" T-Scan IS6 FVI 60" T-Scan (541 IRS P-Scan (S41

                                                                                                     % Total Composite Coverage=    74.4%

ANMCI 10/JQ/I] Comments: A - manual scanning was limited due to the nozzle configuration. Exam1nat1on volume 1s in occardonce with Code Cose N-613-1. Note - Rounding methods may affect calculated values. UC-Underclad. FV-Full volume. NS-Near Surface. Weld length in degrees. 59 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots (,---:J G ~ ( . HITACHI RPV Scan Plan Peach Bottom Unit-2 N3 - Main Steam Nozzle N3A (PEA-2-002900) Cf_ ....,. 15'tllTS$&9mV'Oiume* &JSQ In.

                                                    ~ 54 El.Im Voll.me. 4.l Sq. Sn.

0 0- w sa Eqm VoUn9

  • so l Sea. 1n I IMsr 15'41T S5 EAam Yoh.nm AdffvMS =4 ) SQ In ao* S4 &am Velum* AdMG:vN = 4 l Sq In I ISO" S6 E..an VdulM AchlewMI
  • 12 3 Sq tn I &anirwtianwaume1ew CedlC....N.alJ..l I CllC&dletential uamnatmn allhll autof 15'!1.T I

1t nDll ~ 1 *w N 2001 Edillanw/2003 ~ I No* Wfface T sc.in nat 19qUfed duo ta w9ld cap 0 I I I I 5 O" 14 O" I 60"T 60'T I I I I I i--- 1 I I N3 Nozzle to Shell Scan Limits at Top Dead Center P:eac: 7 or 10 60 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots u "

  • HITACHI RPV Scan Plan
                         ~~     I      ,          Peach Bottom Unit-2
I I' N3 - Main Steam Nozzle N3A (PEA-2-002900)
I I' I I I '
I I

I I I r-- 1&0* 1 60"T I I I I I N3 Nozzle to Shell Scan Limits ot 90° and 270° 144.c ~or lo 61 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots L- 0

  • HITACHI Manual RPV Examination Coverage Calculation Sheet Peach Bottom Unit 2 / P2R22 N3A (Noz-RPV) N3A (PEA-2-002900)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 45.4 Area Sq. In. Automated Automated Automated Automated 60" T-Scan IS6 NSI A 21.3 0.0 0.0% 360 0.0% 60" T-Scon IS6 FVI A 19.8 12.7 28.0% 360 14.0% 60° T-Scon IS4) A 4.3 4.3 9.S% 360 4.7% IRS P-Scan IS4l A 4.3 4.3 100.0% 360 50.0% 60" T-5con 156 NS) 60° T-Scon IS6 FVI 60" T-Scon IS4l IRS P-Scon IS4l 60° T-Scan IS6 NS) 60° T-Scan IS6 FVl 60" T-Scan 1541 IRS P-Scon 154) 60° T-Scon IS6 NS) 60° T-5con IS6 FV) 60" T-5con (54l IRS P-Scon (S4l

                                                                                                     % Total Composite Coverage=      68.7%

RNGrd 10/IDIU Comments: A - monuol scanning was limited due to the nozzle configuration. EKommat1on volume is in accordance with Code Cose N-613-1. Note - Rounding methods may affect calculated values. UC-Underclod, FV-Full volume. NS-Near Surface. Weld length in degrees. ~(...;:: 5af ia 62 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots "ll

'1)
~
;;r g I                                                        Peach Bottom 2

[lJ I 3 c

> I Top Head Spray N6A Nozzle

~ I CH-NA (PEA-2-009400) N 0 0 II 60°T NS Exam Area = 12.5 sq. in . 60°T FV Exam Area= 19.0 sq. in. II 60°T Inner 15%T Exam Area= NIA 60°T NS Exam Area = 2.3 sq. in. II

                         /
                           /

60°T FV Exam Area= 16.9 sq. in. 60°T Inner 15%T Exam Area = NIA II I 60"T NS 60"T NS II 60"T I* I II I

"ll DI cg 11*,.\  I      i     ;E I     ~=Cl)~

a ~~ ~ C1> I oe ~\;.. c ;' :n

      ~ ~~~:s:
      -('a    s: = -*
             .:-1

() "'IJ CD

         -    -f   ...

a 63 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

~

Ill 0

T Ill 0
i 0

3 Peach Bottom 2 c

l Top Head Spray N6A Nozzle

~ CH-NA (PEA-2-009400)

~

0 60°P NS Exam Area= 12.5 sq. in. 60°P FV Exam Area= 19.0 sq. in. 60°P Inner 15%T Exam Area :: NIA so*p NS Exam Area = 1.8 sq. in. I

                                /
                                  /  -                            60°P FV Exam Area= 12.4 sq. in.

60°P Inner 15%T Exam Area = NIA 50*p NS so*p "ti II> <O CD r-1~ i ~

              ~ EQS>>

a 1~ l a.*rna.

              ~~:c(I)
              ..!.cif:TI
       ~ °j\):il'i :::>"
    .........
  • z:::::..
                  ~
                          =

(I)

    ~             '.!I ..,

0 64 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots i c

  ~

g. 7 eI HITACHI Reactor Pressure Vessel Coverage Peach Bottom Unit-2 P2R18 Calculation Sheet 0 N6A-Top Head Spray Nozzle CH-NA (PEA-2-009400) CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld length Percent Exam Volume = 31.l Area Sa. In. Manual Manual Manual Manual 60" T-Scon 156 NSI A 12.l 2.3 7.4% 360 3.7% 60" T-Scan 156 FVI A 19 16.9 54.3% 360 272% 60" T-Scan 154 UC) A 0 0 0.0% 360 0.0% 60" P-Scan (S6 NS) A 12.1 1.8 5.8% 360 2.9% 60" P-Scan IS6 FVJ A 19 12.4 39.9% 360 199% 60" P-Scan & NN l54 UCI A 0 0 0.0% 360 0.0% 60" T-Scan 156 NSI 60"T-Scan(56 FVI 60" T-Scan 154 UC! 60" P-Scan (56 NS) 60° P-Scan 156 FVI 60" P-Scan & NfV 154 UC) 60" T-Scan (56 NS) 60" T-Scan (S6 FVI 60" T-Scan (54 UC) 60" P-Scan IS6 NSI 60" P-Scan (56 FVI 60" P-Scan & NN 154 UCI "8 IC

                                                                                                            % Total Campa51te Coverage=

53.7%

                                                                                                                                                     . *- ****-* Rov. 09/llll>

Comments: A - Manual scanning was restricted. due ta nozzle configuration. GE Hitachi ~ l..:r Na coverage daimed far the 54 UC scans due to the non-dad ID surface a Level Ill-RT, UT. MT, PTI ~ M and VT-1,2,3 q l0o Note - Rounding methods may affect calculated values. UC-Underclad, FV-Full volume. NS-Near Surface. Weld length in decrees

                                                                                                                                     'U,,~b.t
                                                                                                                                        ~h"~      ~'t!>c<

65 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

 "'O ID Q) n
T CD
 ~

Peach Bottom 2 3 c:::> TOP HEAD VENT N7 CH-NB (PEA-2-009500)

~                                               60"T NS Exam Area = 11 .9 sq. in.

N 0 _. 60°T FV Exam Area = 23.8 sq. in. 0 60°T Inner 15%T Exam Area = NIA 60°T NS Exam Area= 4.7 sq. in. 60"T FV Exam Area = 23.0 sq. in. 60°T Inner 15%T Exam Area= NIA 60"T NS 60"T ~ "'O ID I 1~ a loo Wade F. Miller uM GEHttachl Level Ill-RT, UT, MT, PT ~2. IOQ Wade F. Miller GE Hitachi ~ LeVel Ill-FIT, UT, MT, PT and Vf-1,2,3 9/°lb/QJ/0 67 of76

Unit 2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e

  "D 11) 0 n
r Reactor Pressure Vessel Coverage gi HITACHI s3 Calculation Sheet c
J
 ~                                                                        Peach Bottom Unit-2 P2Rl8
~

N 0

 ......                                                                   N7 - Top Head Vent Nozzle 0

CH-NB (PEA-2-009500) CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 35.7 Area Sq. In. Manual Manual Manual Manual 60° T-Scon IS6 NS) A 11.9 4.7 13.2% 360 6.6% 60° T-Scon (S6 FVJ A 23.8 23.4 65.5% 360 32.8% 60° T-Scon (S4 UCl A 0 0 . 0.0% 360 0.0% 60° P-Scon IS6 NS) A 11.9 4.6 12.9% 360 6.4% 60° P-Scon IS6 FVJ A 23.8 22.3 62.5% 360 31.2% 60° P-Scon & N/V IS4 UCI A 0 0 0.0% 360 0.0% 60° T-Scon (S6 NSI 60° T-Scon (S6 FVl 60° T-Scon (S4 UC) 60° P-Scon (S6 NSl 60° P-Scon (56 FVl 60° P-Scon & N/V (54 UC! 60" T-Scon (S6 NS! 60° T-Scon (56 FVJ 60° T-Scan (S4 UC! 60° P-Scan (56 NS) q,o* P-Scan (S6 FVI 60° P-Scon & N/V (S4 UC)

                                                                                                                % Total Composite Coverage=             77.0%

l \Al... ..., ... C lAill ..... Rev. 0 9/Zl/OS rs. Comments: A - Manual scanning was restricted, due to nozzle configuration. No coverage claimed for the 54 UC scans due to the non-clod ID surface GE Hitachi Level Ill-RT, UT, MT, PT /~~ and VT-1,2,3 'f v#' lDQ Note - Rounding methods may affect calculated values. UC-Underclad. FV-Full volume, NS-Near Surface. Weld length in degrees (l ~-"'* ~r:: \)

                                                                                                                                                                 ~

68 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots _v -_ *---- ~- fiJ 1 HITACHI Wall Thickness Profile Sheet I Site: Pro1ect: PeachBottomAtomicPowerStotlon PZR20 unit ~ Summary No.: 312100 System: Pasillon o* 90' HPC/ 180' 270' Component ID Number: 23-2Tl16-2

                                                                                                                            ~12                       ~--14 l    0.450"    NIA         NIA       NIA IT1                                        ~

Crown Height Flush 2 0.420" NIA NIA NIA Crown Width: y: Reducer Valve 3 0.420" NIA NIA NIA UPST Component DNST Component Nommol Diameter. 16.0" 4 NIA NIA NIA NIA Weld Length: 51.0" 5 0.930" NIA NIA NIA FLOW ....

                                                                                                    -+S:~
                                                                                            ~ ~+c;_~,.)

11s* T

                                                                                    \

0=--

i.
  • Re.d.u. r.ct- VA Lve FLOW 1.o;N 1 .:13-:lTil"-.;1.

o ozs- rJ*1*5S4sr:::. Atc:1"AC ~~.; i..J:+u 7ct* ~ cnz

                                               ,..,,,, ,~o             (J*J:s_ ~,..,~ w.=tt~ 45jJ.::

1

  • J5
                                                        ~~

lj""

                                                                                                              - S<f'%

I S~c.) 7,;) -= ?1~.5% ~~~ .;rAB_ Initials: Jack Relsewitz Drawn by;

                                  !1 Level:

10/?512014 Date:

                                                                         ~:JIL_ RSJ~--<:t .£~.£2 Level:      Date:       ;  Review:

J-l-"--S"-=-1 Date: ~

                                                                                                                                                      ~                      libkt Date:

Poge ~ of 2 69 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots (.l

           -- u HITACHI                                    Wall Thickness Profile Sheet u             Site:

Pro1ect Peach Bottom Atomic Power Stotion

                                                                                                                       ~

Unit: ~ Summary No.: 169800

                                                                                                                      ~~14 System:                 cs Component ID Number. 14-8-3 Pos1t1on     o*      oo*     180"      270" 1       0.64"    NIA      NIA       NIA     Crown Height               Flush m m : rn                                    Cfil 2       0.65"    NIA      NIA       NIA Crown Width:                l.l"
                                                                                                                   !?JR!                                     PeMtration l       0.73"    NIA      NIA       NIA UPST Component                                DNST Component Nominal Diameter.          12.0" 4        NIA     NIA      NIA       NIA Weld Length:               ~

s NIA NIA NIA NIA FLOW-- fL.Oc..J .......

                                                                                                  /
                                                                          -'\? ~~~

r I '\

                                                                                                                              -      _J_

C:,O lrnt1ols: Chad Olson Drown by: IL Level. 10/25/2014 Dote: IVZ'i *ty Dote:

                                                                                                                                              ~

ANll Review: I~ Dote: Poge  !! of § 70 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots r-HITACHI II Wall Thickness Profile Sheet 11 Site: ProJect find! Boqom fm! Unit l I Reportl\IO.:

                                                                                                                                                         ~

{;

                                                                                                                              ~                       14rn SJ15lent                    g                     I Paslliol'I I   fl'  I   90"  I l8fl' I      Z70"  I Component ID Number. 14-8-ZIOM I                                  rn l     I 0.72"  I NIA I NIA I NIA I               Crown Height:                  flush m

l I O.IW I NIA I NIA I NIA I Crown Width: A.!: l 1 o.n* 1 NIA I NIA I H/A I  !!K fie!. UPST C0111K>nent DHST component Nominal Diameter: gQ: 4 I 0.69" I NIA I NIA I H/A I Weld Length: .39.1.5" 5 I 0.111' I NIA I NIA I H/A I FLON.-

                ~-
                                                  --------                   \
                                                                                          'I I

I _ _' _ \L _J_!I_ __,___ _ _ _ _ _ _ _ _ __ ~

              !!yon Tauchen 1!.    ~, ~-.......r.            ?--     :ar       ~                      ~\     (""")             ~z.~                             ci fz."1 (1-z..

lnlliols: OralM'lby. l.l!lll!I: Date: GE Rl!Vil!Wedll; Level: Date: ~Review: Date:

                                                                                                                                              ~          Poge       112 Dole:

of ~ 71 of 76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots I Ultrasonic Examination Indication Report

  • Dola Report N..nber: Yl!!§
  • HITACHI COi I Dalo Sheet Nwnbel: ~

Site l'lladl Bottom Procedure: EPRJ-lJHW.PA-1 Weld ID: l~B-28 DH Drawing: OCN-l~Hl-203-5-A Sile: y,g: Thickness: ~ Eicom Stnrt 1300 lo lomlion: O!@ide Radius of UPSr Efbow Wo Loco lion: Vkld Centerline Weld Width: u* Weld Height Flus/! fJoll End: Y!2 Ind Angle 9' of Indication Length wDiSiiiiiCe-- MetaiPOlh No. Used DAC U LMax L2 Wl WMox W2 MPl MPMolC HP2 Comments: 1 liO" !l2S

  • 111.11"
  • NIA 10" NIA NIA 1Z' NIA I 1111 I DNST 360"at Raat

'Sketch flP~ Fl.OW /'!PC l/'IO.j...

                                                                                                                                                                              'j~
  ~0       Cbod Olson         H~

Dote: ElconWler lRvet Date: J1 of y_ 72 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots System: r---* ..

  • HITACHI g

Indication I Coverage Plot Sheet Component ID Number: l*B-28DH Site: Projed: Pr!ach llottDm

                                                                                                                      ~

Configuration: Unit i lo Report Number.: mg Ef2!

                                                                           ~

I1----~ '

                                                                        ' 'LL' I I I CIRC Scan Coverage I I I 1* 1 I I

(!O Initials: Chad Olson Drown by.

                        !l Levet
                             !jll&'2012 Date:
                                        ?ffi*

GE Reviewed

                                                   .:r~.. ~ ,,~ ~Q ey;          Level:     oale:~=ed By.
                                                                                                                              'i-lZ-IZ..

Date.

  • I
                                                                                                                                                 ~

wed By: Poge R

                                                                                                                                                                    't(W/tv Date:

of li 73 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Indication I Coverage Site: l'mchBottDm Unit l Report Number.:

  • HITACHI Plot Sheet Project P1!!11l ~

System: g Component ID Number: 14-t-28 DH Configuration: fl2! to  !!!I!! AX Scan Coverage t:Q_ Initials: Chad Olson Drown by:

                          !J.~

level:

  • Dote:
                                         ~~

GERe~ Le11el:

Jz& 9/zll"~l Dote: ~dBy:

Q ~L~ Date: Page ll

                                                                                                                                                   ~

Dole: of ,!i 74 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Wall Thickness Site: Peach Bottom Unit: ~ Report No.:

  • 1 HITACHI Profile Sheet Project P2R18 162400
                                                                                                                                         ~
                                                                                                              ~                                  ~m System:                  RWCU Component ID Number:  12-1-2 OM Position      0-      90*     180"   270-I

[1]

                                    -                                                                       OJ NIA     NIA      NIA    NIA Crown Height               Flush 2          NIA     NIA      NIA    NIA Crown Width:                0.9" Valve                                       Elbow 3         0.48"    NIA      NIA    NIA UPST Component                              DNST Component Nominal Diameter:           4.0" 4       I O.JB"    NIA      NIA    NIA Weld Length:               14.9" 0.38" I  NIA      NIA   NIA                                                                                                FLOW ...

VA.t"°£ ~ £J.iJb\IV"

                                                                                              ~

C!.O Chad Olson !1 ~I ~.-.-.r~~_:::or_ 11-- ei<f I ~ 1.- \ <' <}..:.l._(o:_(1 czj Jo(c.o Drown by: Level: Dote: GE Reviewed ff: Dote: Dote: Dote: Page .?. of 2 75 of76

Unit2 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Indication I Coverage Site: Peach Bottom Unit ~ Report Number.:

      *       , HITACHI Plot Sheet                        Project:          P2R18                       162400 System:            RWCU                   Component ID Number:     l2-1-2 OM                             Configuration:            Valve   to        ~

t--~~~~~~~~~~~~~~~~~~~~~~~~~~~~~*~~~*-~~~

                                                                                                                ~

AX SCAN COVERAGE Valve to Pipe" ~

                                                                                                               '1/u.fZ.ot o 60RL & 70RL 0 Degrees RL Coverage missed from an L-Dimension ofO to 5.2" and 9.7" to 14.9".

No credit was achieved from 5.2" to 9.7" due to component configuration. 180 Degrees Shear coverage was credited on the downstream side of the weld in the base material around the entire weld length. Coverage Missed Wade F. Miller ~ eo Cf!gdO/son  !! 9/2l/?010 GE Hitachi 't/z,/-Zo/O Drown by; Level: Dote: Level Ill-RT, UT, MT, PT and vr-1.2,3 Page !l of 2 76 of76

Enclosure 2 Peach Bottom Atomic Generating Station Unit 3 Fourth lnservice Inspection Interval limited Coverage Non-Destructive Examination Coverage Plots

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots IHI Southwest Technologies Examination Summary Record Site: Peach Bottom Power Station Unit 3 UUI

  • Exelon Generation Outa e: P3R20 Summa ShHt No. 000100 tam: Reactor Pressure Vessel 100* ldenUflcatlon: V-1-A NOE NOE CallbraUon ExamShHt Method ProclRav/Ch /ICN Examination ShHtNo's. No. NRI Other Remarks AUT ISwT-PDl-AUT5/1/0/1 Probe 1 1100005 1 &28 x AUT ISwT-PDl-AUTS/1/0/1 Probe2 1100006 1 &28 x AUT ISwT-PDl-AUTS/1/0/1 Probe 3 1100007 1 &26 x AUT ISwT-PDl-AUT5/1/0/1 Probe4 1100008 1 &28 x AUT ISwT-PDl-AUTS/1/0/1 Probe 1 1100001 2A x AUT ISwT-PDl-AUTS/1/0/1 Probe2 1100002 2A x AUT ISwT-PDl-AUTS/1/0/1 Probe 3 1100003 2A x AUT ISwT-PDl-AUTS/1/0/1 Probe4 1100004 2A x Examination Summary:

This weld was examined from the inside surface using AIRIS-21 and Oynaray examination equipment

  -NoTiroOTdable indications were detected during this examination.

Limited examination due lo jet pump baffle plate and proximity of the N8 nozzle. The examination coverage was 88. 7o/*. Examination Angles for each probe included: PA60"-80"L, PA40°-50°S, PA30"-80"L, & PA0°L. Prepared By: Steven J. Todd SlgnatuN: Ji.r:-..IA.. IHI Pro act .l.n!: Reviewed By: Signature: Data: Slgnatu Exelon Corp. ANll _) 2 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots 1 ) J 5e111hw"t1 T"hnol...*1, .... IHI Southwest Technologies Examination Summary Record Site: Peach Bottom Power Station Unit 3 Utlll

  • Exelon Generation Outa e: P3R20 Summ Sheet No. 001000 s tem: Reactor Pressure Vessel 45° Identification: V-4-A NDE NOE Calibration Exam Sheet Method Proc/Rev/Ch ncN Examination Sheet No. No. NRI Other Remarks AUT ISwT-PDl-AUTS/1 /0/1 Probe 1 1100009 19 x AUT ISwT-PDl-AUTS/1 /0/1 Probe 2 1100010 19 x AUT ISwT-PDl-AUTS/1 /0/1 Probe 3 1100011 19 x AUT ISwT-PDl-AUTS/1/0/1 Probe4 1100012 19 x AUT ISwT-PDl-AUTS/1/0/1 Probe 1 1100005 20 x AUT ISwT-PDl*AUTS/1/0/1 Probe2 1100006 20 x AUT ISwT-PDl-AUTS/1/0/1 Probe 3 1100007 20 x AUT ISwT.PDl-AUTS/1 /0/1 Prcbe4 1100008 20 x AUT ISwT-POl-AUTS/1/0/1 Probe 1 1100001 21 x AUT ISwT-PDl-AUTS/1/0/1 Probe2 1100002 21 x AUT ISwT-POl-AUTS/1 /0/1 Probe3 1100003 21 x AUT ISwT-PDl-AUTS/1/0/1 Probe4 1100004 21 x Examination Summary:

This weld was examined from the inside surface using AIRIS-21 and Dynaray examination equipment No recordable indications were detected during this examination. The examination was limited due to the proximity of the feedwater and core spray spargers. The examination coverage was 83.2%. 0 Examination Angles for each probe included: PA60°-80°L, PA40°-so*s, PA30°-60°L, & PA0°L. Reviewed By: Slgnatura: Signature. Exelon Corp. ANH 3 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots ) IHI Southwest Technologies Examination Summary Record Site: Peach Bottom Power Station Unit 3 UUll : Exelon Generation Outa e: P3R20 Summa ShHt No. 0011 oo tem: Reactor Pressure Vassel 165" ldentlftc:aUon: V-4-B NOE NOE Calibration ExamShHt Method ProclRev/Ch CN Examination ShHtNo. No. NRI Other Remarks ISwT-PDl-AUT5/1 /0/1 Probe 1 1100009 22&24 x AUT 1SwT-PDl-AUT511/0/1 Proba2 1100010 22&24 x AUT ISwT-PDl-AUT5/1/0/1 Proba3 1100011 22&24 x AUT ISwT-PDl-AUT511/0/1 Proba4 1100012 22&24 x AUT ISwT-PDl-AUT511/0/1 Probe 1 1100013 23 x AUT ISwT-POl-AUT511/0/1 Proba2 1100014 23 x AUT ISwT-PDl-AUTS/1/0/1 Proba3 1100015 23 x AUT ISwT-PDl-AUT5/1/0/1 Proba4 1100016 23 x Examination Summary: This weld was examined from the inside surface using AIRIS-21 and Dynaray examination equipment. No recordable indications were detected during this examination. The examination was limited due lo the proximity of the feedwater and core spray spargers. The examination coverage was 83.2%. Examination Angles for each probe Included: PA60"-80°L, PA40°-50°S, PA30°-60°L, & PA0°L. Slgnatu1W: Exelon Co

  • Data: Slgnatu....

ANll oat*= f/Jj,,)s

)

4 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi intervai Limited Coverage NOE Coverage Plots

  • ) I ~*hw*"' '"'h"....."' ""'*

IHI Southwest Technologies Examination Summary Record SHe: Peach Bottom Power Station Unit 3 UUll

  • Exelon Generation Outa e: P3R20 Sum Sheet No. 001200 s tem: Reactor Pressure Vessel Line Subassemb : Vertical Weld 2e5* ldenUflcatlon: V-4-C NOE NOE CallbraUon Ex*mSheet Method Proc/Rev/Ch ICN ExamlneUon Sheet No. No. NRI Other R*m*rks ISwT-PDl-AUT5/1/0/1 Probe 1 1100001 25&27 x AUT ISWT-PDl-AUT5/1/0/1 Probe2 1100002 25&27 x AUT ISWT-PDl-AUT5/1/0/1 Probe3 1100003 25&27 x AUT ISWT-PDl-AUT5/1/0/1 Probe4 1100004 25&27 x AUT ISwT-PDl-AUT5/1/0/1 Probe 1 1100005 26 x AUT ISwT-PDl-AUT5/1/0/1 Probe 2 1100008 26 x AUT ISWT-PDl-AUT5/1/0/1 Probe 3 1100007 26 x AUT ISwT-PDl-AUT5/1 /0/1 Probe4 1100008 28 x Examination Summary:

This weld was examined from the inside surface using AIRIS-21 and Dynaray examination equipment. No recordable indications were detected during this examination. The examination was limited due to the proximity of the feedwater and core spray spargers. The examination coverage was 79.0%. Examination Angles for each probe included: PA60"-80"L, PA40"-50"S, PA30°-60°L, & PAO"L. Date: l 0 {oci / Z.OL 5 Reviewed By: Signature: Exelon Co Date: lO I rf5 Signature: ANll Date: /o/;fbJ' 5 of53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • ) I S..1"-HIT9Ch"a...i... '-.

IHI Southwest Technologies Examination Summary Record Site: Peach Bottom Power Station Unit 3 Outage: Utlll : Exelon Generation P3R20 Summa Sheet No. 001600 s tern: Reactor Pressure Vessel Lin* Subassembl

  • U er Shell to Flan e Identification: C6 NDE NDE Calibration Exam Sheet Method ProclRev/Ch ICN Examination Sheet No, No. NRI Other Remarks ISWT-PDl-AUT5/1/0/1 Probe 1 1100001 35 x exams #35 A-0, 35AA-35BA AUT ISwT-POl-AUT5/1/0/1 Probe2 1100002 35 x exams #35 A-0, 35AA-35BA AUT ISwT-POl-AUT5/1/0/1 Probe3 1100003 35 x exams #35 A-0, 35AA-AC, 35 AE-35BA AUT ISwT-POl-AUT5/1/0/1 Probe4 1100004 35 x &lUlms #35 A-0, 35AA-35BA AUT ISwT-POl-AUTS/1/0/1 Probe 1 1100009 35 x elUlms #35 E-Z AUT ISWT-PDl-AUTS/1/0/1 Probe 2 1100010 35 x exams #36 E-Z AUT ISWT-PDl-AUT5/1/0/1 Probe 3 1100011 35 x &JCBms#36E-Z AUT ISWT-PDl-AUTS/1/0/1 Probe4 1100012 35 x egms #36 E-Z AUT ISwT-PDl-AUTS/1/0/1 Probe 3 1100003 35 x exam#36AD Examination Summary:

This weld was divided into sections. See remarks above for setion identification numbers. This weld was examined from the inside surface using AIRIS-21 and Oynaray examination equipment. Two (2) recordable indications were detected and determined to be allowable in accordance with the 2001 Edition of ASME Section XI Code with 2003 Addenda. The examination was limited due to the proximity of mainsteam nozzle plugs and the guide rods at o* and 180". The examination coverage was 85.9%. Examination Angles for each probe Included: PA60"-80°l, PA40"-50"S, PA30"-60"l, & PAO"L. Indication location Y Location Flaw T-Wall Number FlawT In.

  • LOC1tlon L In. al\%

JSAD-1 subsurface 708.3 Range 6ide 1.4 35A0-2 subsurface 702.0 Shell Side 14 Prapared By: Steven J . Tod Signature: J-r:-: Date: IHI Pro ect ~=- Reviewed By: Reviewed By: Slgnmture: Date: Signature. Exelon Corp. ANH

 )

6 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots P3R20 RPV Weld Examination Coverage Weld Weld Configuration Examination Limited Exam Area Coverage Calculation Total Coverage No. Description Limitation (Length Examined I Total Required Weld Length* (in.) Lenlrth l x I 00 = % exam coverage  % Ring I Vertical Weld@ Jet Pump Baffle Plate I 16.78 to 130.97 (l l 7.3/132.2) x 100 V-1-A 88.7 100° N8A Nozzle @ 105° 130.97 to 139.07 partial = 88.7% Ring 1 Vertical Weld@ (119.6/132.2) x 100 V-1-B 90.5 220° Jet Pump Baffle Plate 116.78 to 129.38 =90.5% Ring l Vertical Weld@ (119.6/132.2) x 100 V-1-C 90.5 340° Jet Pump Baffle Plate 116.00 to 129.38 = 90.5% Ring 1 Vertical Weld @ ( 132.2/ 132.2) x 100 V-2-A 100 50° None 0 = 100% Ring 1 Vertical Weld @ (132.2/132.2) x 100 V-2-B 100 170° None 0 = 100% Ring 1 Vertical Weld@ (132.2/132.2) x 100 V-2-C 100 290° None 0 = 100% Ring 3 Vertical Weld@ (132.2/132.2) x 100 V-3-A 100 107° None 0 = 100% Ring 3 Vertical Weld@ Core Spray Sparger (129.0/132.2) x 100 V-3-B 97.6 227° Bracket 472.18 to 478.48 partial =97.6% Core Spray Sparger Ring 3 Vertical Weld@ (129.7/132.2) x 100 V-3-C Downcomer Piping 396.68 to 412.88 partial 98.1 347° Flange 411.88 to 440.68 partial

                                                                                                                                       = 98.1%

Ring 4 Vertical Weld@ Core Spray & (114.2/136.6) x 100 V-4-A 83.6 45° Feedwater Sparger 481.88 to 504.28 = 83.6% Ring 4 Vertical Weld @ Core Spray & (114.2/136.6) x 100 V-4-B 83.6 165° Feedwater Sparger 481.88 to 504.28 = 83.6% Ring 4 Vertical Weld@ Core Spray & (108.1/136.6) x 100 V-4-C 79.1 285° Feedwater Sparger 473.78 to 502.48 = 79.1% Ring 5 Vertical Weld @ (125.7/136.6) x 100 V-5-A 92.0 90° Dryer Support Bracket 615.09 to 633.50 partial =92.0% Ring 5 Vertical Weld@ (136.6/136.6) x 100 V-5-B 100 210° None 0 = 100% Ring 5 Vertical Weld @ (136.6/136.6) x 100 V-5-C 100 330° None 0 = 100% 0° guide rod 780.50 to 14.50 C-6 Shell to Flange Weld 180° guide rod 386.58 to 405.00 MS Nozzle Plug 147.82 to 173.40 (661.371788.54) x 100 83.9 MS Nozzle Plug 226.40 to 246.68 = 83.9% MS Nozzle Plug 539.00 to 556.35 MS Nozzle Plug 617.50 to 640.50

  • Note: Partial indicates that only a portion of the area listed is limited (i.e. portion of the exam width in this area is limited).

7 of53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots

  • HITACHI RPV Scan Plan Peach Bottom Unit-3 N4 - Feedwater Nozzle N4C (PEA-3-003400)

Inner t5~T S5 ban VO!uma s 4 l Sq. to. M>" S4 E.urfl VokJme 'Z 4.3 Sq. ln. 60" S6 E.dm Volume

  • JJ .J Sq. In Inner 15._, T S5 E.Gln ~ AdMWed "' 4 l Sq tn 8'r SC Eom Volume ...,_wed
  • 4 J Sq. In
                                                                        &er 56£,xan\~ ~~ 15.l&cl tn
                                           <t                           EWl'W1l&ion wiLme: I ii.W Caa. C-.r N-itl* I Cl'OJfdantnlJal ...,,..,..,,., Ol 1'9 ~., 8!i1'iT OU"                          11 nol r~ I a..w hi        2001Etllmnwl2003 Addend.a Meor tudKe     r scan nae ~ di.le to Wli4 cap
                                                       ' or                                        140"
                                                       "'1'1                                       60"1 N~ Nozzle to Shell Scan Limits at Top Dead Center Page£_or~

Peach Bollom Uni1*3, P3R19 Page 14~f 2394 8 of53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual RPV Nozzle Examination

  • HITACHI Coverage Calculation Sheet Peach Bottom Unit-3, P3R19, 2013 N4C N4C (PEA-3-003400)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Eleam Area af Area Length Percent EXllm Volume = 41.6 Area Sq. in. Scanned Scanned Scanned Scanned 60" T-Scon 156) I A 37.3 15.3 36.8% 360 18,4% 60" T*Scon IS41 I A 4.3 4.3 10.3% 360 5.2% IRS P-Scan IS51 I A 4.3 4,3 100.0'!b 360 50.0% 60" T*Scan 1561 I 60° T-Scan (541 I I I I I IK:> P-Scan 1551 I I 60' T*Scan IS61 I 60" T-Scon 1541 I IRS P-Scan 1551 I 60" T-Scan 1561 I 60" T-5con 1541 I IRS P-5con 1551 I 60" T-Scan 1561 I I I I 60" T-Scon 1541 I IH~ f'-Scan IS~! I I I I I I

                                                                                                      % Total Compaslle Coverage "'       73.6~.

Comments A - Manual scanning was restncted due to the nozzle canf1gurat1an !\ate - This coverage calculat!On 1s vahd (or AS:.,E Section XI, 2001 Ed111an w/ 2003 Addenda. 200!t Ed1tian w/ No Addenda and the 2007 Ed111on w/ 2008 Addenda Note - Rounding methods may affect calculated values 56 *Supplement 6, S4

  • Supplement 4, SS Supplement
  • 5. Weld length in degrees.

Peaell Bo11om Unit*3, PJR19 Page 14~4t'of 2394 Page _:t_ of~ 9 of53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI RPV Scan Plan Peach Bottom Unit-3 N4 - Feedwater Nozzle N4D (PEA-3-003500) inner 1.5"' 1 S.5 Enm Vdume
  • 4.3 Sq. '"

EMr 5' Eam "*"""' ... 3 Sq !ti . W 56 Ecrn VDlunW

  • 31.3 6q In tMe115_,.T ~SE1.m\lolume~2 43 Sq kl 50* S.t EQm Volune Achltvad
  • 4.l Sq In 60"' 56 Esurn \lofrumt ktMwOd. 15.3 Sq "'
                                           <t                          ~              YCl!umetaw. Coda C.w N*fH::!-1 Cftl.lnNrenllll nanW'lnlaDft  °' M OUlet 85.'%T DO'"                         Ui not ra~ I* w the 20CI I     EcMIOn wJ 100J Addrnd.I Pffat surface T~Kan not   ~cl       du* to wcrkf ap
                                                      !>IJ'f 1'0'"

60-T N4 Nozzle lo Shell Scan Limits at Top Dead Center Peach Bollom Unil*J. P3R I 9 Page 146<jC0f 2394 PaQe _i_ ol __s_ 10 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

                                                                                                                   ?.trofLrlL o o31' oo
  • HITACHI RPV Scan Plan Peach Bottom Unit-3 N4 - Feedwater Nozzle N4D (PEA-3-003500) tr.ner 151!. r :a E.um Vc&..lme a 4.3 SQ In.

ao* S4 tum Vdwm* ~ *~SQ "1. GQ* S9 E.am Vd&wc

  • l7.l Sa. In.

klner 15~T SS Es.11nVot.rn11Ach .. Yld= .. .J Sq. Ht 10" S4 E.aun \'akltl* Adt...,_d: 4.l Sq 111. ea* $8 Cum Vdurne Achieved* 15.3 Sq. In.

                           ...<t                         E.m~~* . *.w                   ClldoC.1aN-61:J..1 Crc.rnhtentllll ....,,.,nuDl't af ~ GUier .!15'tio r
  • nal **quilWCI 11.w. ~ 1001EOfl.90tlwf2003 AIJGtnct ,
                         '  f HtMU" 111.faca T...aain nOJt rwund OJll rHloldlOn ta wdli aip
                            '~
                            *I I
                                          *o*

I i-;u*r 14(1" 60'1 i

                                 -        -                                                  ~

N4 Nozzle to Shell Scan L1m1t. al Top Dead Center P3 </bf B 11 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual RPV Nozzle Examination

   . ) HITACHI Coverage Calculation Sheet Peach Bottom Unit-3, P3Rl9, 2013 N40 N4D (PEA-3-003500)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area of Area Length Percent Exam Volume = 4L6 Area Sq. in. Scanned Scanned Scanned Scanned 60" T-5con 1561 I A 37.3 15.3 36.8% 360 18.4% 60"T-Scon 1541 I A 4.3 4.3 10.3% 360 5.2% IR5 P-5con 15!>1 I A tu 4.j lUU,u.,. .lDU  !>0.U'lii 60" T-Scon 1561 I I I I I I 60" T-Scon 1541 I IKS P-Scon 1ss1 I I I I I I 60" T*Scon 1561 I 60" T-Scon {S41 I I I IRS P-Scon (SS) I I I 60" T*Scon 156) I 60" T-Scon 154) I IK"> l'*">COnt">"I I I I I I I 60" T*Scon 1561 I I I I I I 60" T-Scon (541 I I IKS P*..,con 1s..,1 I I I I I I

                                                                                                  %TOtol Composite Coverage=-- 73]i%
                                                                                                                                                       ....... ~ * *.'ul l Comments.      A~ Manual scanning was restrideddue tcilhe nozzle conligurot1on.

Note - This coverage colculotJOn 1s vohd for ASME Section XI. 2001 Edition w/ 2003 Addenda. 2004 Edll1on w/ No Addenda and the 2007 fd1t1on w/ 2008 Addenda Note - Rounding methods may effect calculated values. 56 - Supplement 6. 54

  • Supplement 4. SS Supplement
  • 5. Weld length in degrees.

Peach Bollom Unlt-3. PJR19 Page 14ftt11bf 2394 Page ..!:L or __k_ 12 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e Peach Bottom 3 - N4 Nozzle - Feedwater N4E (PEA-3-003600) 60°RL T-Scan Coverage

             /
               /
                 /
                   -                I:
                      ' - - - - - - - - - 18.8" -----------~
                                                ~I          3.5" 15.8" I

I I T-Scans ( I ~ 1------ 1 I I I ~ I/ _____ _j I I I ~ ~ ~ Cs 13 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e Peach Bottom 3 N4 Nozzle - Feedwater N4E (PEA-3-003600) 60°RL P-Scans Coverage

                   /
                     /
                       - ......- - - - 9 . 5 "

r-6.0" I I

                 /

H-2.2" I P-Scans 60°P 60°P I (J e, ~ I I I l------- 1 I B l I I I I I I/ / _ _ _ _ _ _J I I

~
~

cq 0

~

14 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e e Peach Bottom Unit-3 . Feedwater N4 Nozzle N4E (PEA-3-003600) S6 NS Exam Volume = 29.8 Sq. In.

                                                                                               =

S6 FV Exam Volume 44.1 Sq. In. 54(Inner15% T) Exam Volume= 9.3 Sq. In.

                         <t                                          60°T NS Coverage achieved = 2.8 Sq. In.
                                                                                                      =

60"T FV Coverage achieved 33.2 Sq. In. 60°T S4(Inner15% T) Coverage achieved= 9.3 Sq. In .

                   /
                 /
               /

I I aC) f 60"T w Ir------ I 8 I 1 I I I I I I t'() I I () (3; 15 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e - Peach Bottom Unit-3 Feedwater N4 Nozzle N4E (PEA-3-003600) S6 NS Exam Volume= 29.8 Sq. In. SS FV Exam Volume =44.1 Sq. In. S4 (Inner 15% T) Exam Volume = 9.3 Sq. In.

                         't                                           soap NS Coverage Achieved = 2.5 Sq. In.

soap FV Coverage Achieved =22.4 Sq. In. soap & NN (Inner 15% T) Coverage Achieved= 9.3 Sq. In.

                   /
                 /
               /

D I I ~ I soap 8 Ir------ 1 I I I I I I ~ I I I ~ I

                            -------i

{) I) 0 16 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e e

            -                                                                          Reactor Pressure Vessel Coverage HITACHI Calculation Sheet Peach Bottom Unit-3 N4 - Feedwater Nozzle N4E (PEA-3-003600)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld length Percent Exam Volume= 83.2 Area Sq. In. Manual Manual Manual Manual 60° T-5can 156 N51 A 29.S 2.8 3.4% 360 1.7% 60" T-Scan 156 FVI A 44.l 33.2 39.9% 360 20.0% 60°T-5can154 UCI A 9.3 9.3 11.2% 360 5.6% 60" P-5can (56 N5l A 29.S 2.5 3.0% 360 1.5% 60" P-5can !56 FVI A 44.l 22.4 26.9% 360 13.5% 60" P-Scon & NIV 154 UCI A 9.3 9.3 11.2% 360 5.6% 60° T-5con (56 N51 60" T-5can (56 FVI

 ~

60" T-5can (54 UCI 60" P-5can 156 N51 60" P-5can (56 FVI

 §'                       60" P-5can & N/V 154 UCJ 60" T-5can (56 NSI 60°T-Scan156 FVI 60" T-5con 154 UCI 60° P-5can 156 N51 60° P-5can 156 FVI 60° P-5can & NN (54 UCI
~                                                                                                                                         ./
                                                                                                               % Total Composite Coverage="-- 47.8% /"""""'
~      Comments:      A - Manual scanning was restricted. due to nozzle configuration.

R~ 0 9/2ll& 6" () ~~ 1.hf'/;. ? ....... Note - Rounding methods may affect calculated values. UC-Underclad,.FV-Full volume. NS-Near Surface. Weld length in degrees \) 17 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e Peach Bottom 3 N4 Nozzle - Feedwater N4F (PEA-3-003700) 60°RL T-Scan Coverage

                /
                  /
                    / -               I: _

i . - - - - - - - - - 18.8" - - - - - - - - - - - - - - i - i 1 1s.s* 3.5~ I I I T-Scans I () I 0 60°T 1------ ..J 1 I

~        I                                     I I

I/ _____ _j I I

   ~
   ~
   °'

0

   "'(\

18 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e Peach Bottom 3 N4 Nozzle - Feedwater N4F (PEA-3-003700) 60°RL P-Scans Coverage

                       /
                         / - ii..               9.5" i-- s.o*

I I

                     /

J---12.2" I P-Scans 60°P 60°P I I I g I I l------ 1 I 0 0 l I I I I I 11/_ _ _ _ _ _J I I

    ~
    ~

0 N 19 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e e Peach Bottom Unit-3 Feedwater N4 Nozzle N4F (PEA-3-003700) 56 NS Exam Volume =29.8 Sq. In. S6 FV Exam Volume =44.1 Sq. In. S4 (Inner 15% T) Exam Volume = 9.3 Sq. In. 60°P NS Coverage Achieved = 2.5 Sq. In.

                       't                                                                            =

60°P FV Coverage Achieved 22.4 Sq. In. 60°P & NN (Inner 15% T) Coverage Achieved= 9.3 Sq. In.

               /
                 /
                   / -

I I

~

0 I 60°P . w Ii - - - - - - I

~

1 I I I I I I I I I

                          -------\

t 4..Q ~ (\I 20 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e e Peach Bottom Unit-3 Feedwater N4 Nozzle N4F (PEA-3-003700) 56 NS Exam Volume = 29.8 Sq. In.

                                                                                                 =

56 FV Exam Volume 44.1 Sq. In. 54(Inner15% T) Exam Volume= 9.3 Sq. In. ct = 60°T NS Coverage achieved 2.8 Sq. Jn.

                                                                                                         =

60"T FV Coverage achieved 33.2 Sq. In. 60°T S4 (Inner 15% T) Coverage achieved =9.3 Sq. In.

                  /
                /
              /

I I I soI T 0 e"" () I r------ 1 I 0 I I I I I I I ~ -------1 ~ "5'

~.

21 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e e - Reactor Pressure Vessel Coverage HITACHI Calculation Sheet Peach Bottom Unit-3 N4 - Feedwater Nozzle N4F (PEA-3-003700) CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld length = 360. Required Exam Area Scanned of Area Weld length Percent Exam Volume= 83.2 Area Sa. In. Manual Manual Manual Manual 60" T-5con IS6 NSI A 29.8 2.8 3.4% 360 1.7% 60" T-Scon IS6 FVI A 44.1 33.2 39.9% 360 20.0% 60" T-Scon IS4 UCI A 9.3 9.3 11.2% 360 5.6% 60" P-Scon IS6 NS) A 29.8 2.S 3.0% 360 1.5% 60° P-Scon IS6 FV) A 44.l 22.4 26.9% 360 13.5% 60" P-Scon & NN (S4 UCI A 9.3 9.3 11.2% 360 5.696 60" T-5con iS6 NS) 60" T-Scon IS6 FVI 60" T-5con IS4 UCI 60" P-Scon IS6 NS) 60" P-5con 156 FVI 60" P-Scon & NN IS4 UC) 60°T-5con156 NS) g 60" T-5con 156 FVI 60" T-Scon 154 UCI ~ 60" P-Scon 156 NSI ~ 60" P-5con iS6 FVI 60" P-Scon & NN IS4 UCI

                                                                                                        % Total Composite Coverage=         47.8%
                                                                                                                                                   ... 0 'l/21/0!

Comments: A - Manual scanning was restricted. due to nozzle configuration. ~ (l1frt't ~ CJ/z:i. I Zt:P9 ~ Note - Rounding methods may affect calculated values. UC-Underc\od. FV-Full volume. NS-Near Surface. Weld length in degrees

                                                                                                                                    ~l/,,eer'       %s/

~ N

                                                                                                                                   "'/'A~                /'o9 22 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots Peach Bottom 3 N3 Nozzle - Main Steam N3A (PEA-3-002900) 60° NS Exam Volume = 22.4 Sq. In.

                                                                                        =

60° FV Exam Volume 19.8 Sq. In. 60° (Inner 15% T) Exam Volume= 4.3 Sq. In.

               /
             /

60°T- NS Exam Coverage= 0.4 Sq. In. I 60°T- FV Exam Coverage= 14.9 Sq. In. I 60°T- (Inner 15% T) Exam Coverage= 4.3 Sq. In. I I I I ~I \. 60°T 60"T I I I 1-- ~ I I r I .._,"' I I 0 I I 11

                    ---i 23 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom 3 N3 Nozzle - Main Steam N3A (PEA-3-002900 soa NS Exam Volume =22.4 Sq. In. 60a FV Exam Volume= 19.8 Sq. In. 60a (Inner 15% T) Exam Volume =4.3 Sq. In.

               /
             /

I = 60aP-NS Exam Coverage 0 Sq. In. I

                                                                                          =

soap_ FV Exam Coverage 6.4 Sq. In. 50ap_ (Inner 15% T) Exam Coverage= 4.3 Sq. In. I I I I soap I I I I l--- 1 I ~ &o I O<:! I I 0 I-

..0 24 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Reactor Pressure Vessel Coverage Calculation Sheet Peach Bottom 3 I PB3R18 N3A N3A (PEA-3-002900 Fall/ 2011 CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume= 46.5 Area Sci. In. Manual Manual Manual Manual 60° T-Scan ($4 UC) A 4.3 4.3 9.2% 360 4.6%

60" T-Scan CS6 FV) A 19.8 14.9 32.0% 360 16.0% 60° T-Scan S6NS A 22.4 0.4 0.9% 360 0.4% 60° P-Scan S4UC A 4.3 4.3 9.2% 360 4.6% 60° P-Scan S6FV A 19.8 6.4 13.8% 360 6.9% so* P-;:,,can 56111;:, A 22.4 0 0.0% 360 0.0% 60° T-Scan S4UC 0 0 60°T-Scan S6FV 0 0 60" T-Scan S6NS 0 0 60" P-Scan S4UC 0 0 60° P-Scan f56 FV 0 0 60° t'-:.can !86 NS) 0 0 60°T-Scan S4UC 0 0 60"T-Scan 56FV 0 0 60"T-5can 156NS 0 0 so* P-Scan S4 UC) 0 0 60" P-Scan (56 FV) 0 0 so* P-Scan (56 N8J 0 0

                                                                                                 % Total Composite Coverage=       32.6%
                                                                                                                                           - . OlllZllll!

~ Comments: A - Manual UT was restricted due to the nozzle configuration. S' -D Note - Rounding methods may affect calculated values. UC-Underciad, FV-Full volume, NS-Near Surface. Weld length in degrees. 25 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom 3 N4 Nozzle - Feedwater N4A (PEA-3-003250) 60° NS Exam Volume= 18.7 Sq. In 60° FV Exam Volume= 19.8 Sq. In Inner 15%T Exam Volume (60° & IRS)= 4.3 Sq. In 60° NS P-Scan achieved 0 Sq. In=

                                                                                  =

60° FV P-Scan achieved 6.8 Sq. In Inner 15%T & IRS P-Scan achieved= 4.3 Sq. In

              <t I

I I I I I ii\ 60°P 60°P I I I I-- I I I 'R I l ft\ I I I I i' I I 0 ~ I- ----1 ()(! 26 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom 3 N4 Nozzle - Feedwater N4A (PEA-3-003250) 60° NS Exam Volume= 18.7 Sq. In 60° FV Exam Volume = 19.8 Sq. In Inner 15%T Exam Volume (60°T & IRS)= 4.3 Sq. In 60° NS T-Scan achieved = 0.4 Sq. In 60° FV T-Scan achieved= 16.8 Sq. In

                                                                                        =

60° T-Scan Inner 15% Tachieved 4.3 Sq. In ct I I I I I I T-Scans 60°T 60°T I I I I I I-- I I I I "Cl I 11:1>

-. I

" I -.l --~

)

Cl(' 27 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Reactor Pressure Vessel Coverage Calculation Sheet
  • Peach Bottom 3 / PB3R18 N4A N4A (PEA-3-003250)

Fall/ 2011 CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume = 42.8 Area Sq. In. Manual Manual Manual Manual 60°T-5can S4UC} A 4.3 4.3 10.0% 360 5.0% 60" T-Scan I S6FVJ A 19.8 16.8 39.3% 360 19.6% 60°T-Scan 56N5 A 18.7 0.4 0.9% 360 0.5% 60° P-Scan 54UC A" 4.3 4.3 10.0% 360 5.0"k 60° P-Scan 156 FV) A 19.8 6.8 15.9% 360 7.9% 60° P-Scan S6 NS) A 18.7 0 0.0% 360 O.O"k 60° T-5can S4UC 0 0 so* T-Scan S6FV 0 0 60°T-5can S6N5 0 0 so* P*5can CS4 UC1 0 0 60° P-Scan 156 FVI 0 0 60° P-Scan (S6 NS) 0 0 60°T-Scan 54UC 0 0 60°T-Scan 56FV 0 0 60°T-Scan 56NS 0 0 60° P*Scan S4UC 0 0 60° P-Scan S6FV 0 0 60° P-Scan 56N::S 0 0 ~

                                                                                                % Total Composite Coverage =      38.1%
                                                                                                                                          -.08123111!

z-A - Manual UT scanning was restricted due to nozzle configuration. "' Comments: 0 "'I\ Nole - Roundina methods may affect calculated values. UC-Underclad, FV-Full volume, NS-Near Surface. Weld length in degrees. oQ 28 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom 3 N4 Nozzle - Feedwater N4B (PEA-3:003300) 60° NS Exam Volume= 18.7 Sq. In 60° FV Exam Volume= 19.B Sq. In Inner 15%T Exam Volume (60°T & IRS)= 4.3 Sq. In 60° NS T-Scan achieved = 0.4 Sq. In 60° FV T-Scan achieved= 16.8 Sq. In

                                                                                      =

60° T-Scan Inner 15% Tachieved 4.3 Sq. In ct 60"T I I I ~ I "'" I I

... ---l

~ 29 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom 3 N4 Nozzle - Feedwater N4B (PEA-3-003300) S0° NS Exam Volume= 18.7 Sq. In S0° FV Exam Volume= 19.8 Sq. In Inner 15%T Exam Volume {S0° & IRS)= 4.3 Sq. In S0° NS P-Scan achieved =0 Sq. In

                                                                                 =

S0° FV P-Scan achieved 6.8 Sq. In Inner 15%T & IRS P-Scan achieved = 4.3 Sq. In ct

       !'\..

I I I I I I ii\ soap soap I I I I-- I I I I I

;o    I                 I
    ~

z. ... I I I I '1 I- ---1 0 Oc;) 30 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI Reactor Pressure Vessel Coverage Calculation Peach Bottom 3 / PB3R18 N48 N4B (PEA-3-003300)

Fall/ 2011 CODE CROS~ECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld length Percent Exam Volume ;: 42.8 Area Sq. In. Manual Manual Manual Manual 60° T*Scan (54 UC A 4.3 4.3 10.0"4 360 5.0% 60° T-Scan 56 FVl A 19.8 16.8 39.3% 360 19.S% 60° T*Scan SS NS) A 18.7 0.4 0.9% 360 0.5% 60° P*Scan (S4 UCl A" 4.3 4.3 10.0".4 360 5.0% so* P-Scan ISS FV) A 19.8 6.8 15.9% 360 7.9% 60° P*Scan (S6 NS) A 18.7 0 O.O"k 360 O.Cl'Yo so* T-Scan S4UC 0 0 60°T*Scan S6FV 0 0 so* T-Scan S6NS 0 0 so* P-Scan (54 uc1 0 0 60° P*Scan (SS FV) 0 0 so* P*Scan (SS NS) 0 0 S0°T-Scan S4UC 0 0 so* T*Scan S6FV 0 0 so* T*Scan S6NS 0 0 60° P*Scan I S4UC) 0 0 so* P*Scan css FVl Q so* P*Scan (~6 NS) 0 0 0 0

                                                                                             % Total Composite Coverage ;:     38.1%

R9V. 0 IW3I05 U\ Comments: A

  • Manual UT scanning was restricted dUe to nozzle configuration.

~ OG Note

  • Rounding methods may affect calculated values. UC-Underclad, FV*Full volume, NS-Near Surface. Weld length in degrees.

31 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e HITACHI RPV Scan Plan Peach Bottom 3 N1

  • Recirc Outlet Nozzle N1A (PEA-3-004100) 111* 15-'!t.T 5! Eum Vlnlme
  • 4 l Gq vi ao ' ' E*mn vavn1 *
  • l 5Q '"
                                                             &cl ' $1b9'ftV--.*44ISq In
                                                              !\Mr   H~T    U £-.am \oc:"""' AeNrl'l'IG *
  • l 4'1 111 CiO" $4 Enm VG\lme Actllf'"911
  • 4 l !q 111 eo* .seeurnvoium.~"* to~ SQ..,
                                                             £..r1tftn~UGn\o'f-.t.imlllilt COOICu*N..el).1
                                                             ~.,_.,....,.mlNtc"at ~*              111hr a.5"f
                                                              'NltflauirMl1a* ll!t 1001 Edl'CW\**1\IOJ Ad~nda
                                                             -.:,.,,~r.un**"""'a.,,.**.ttt.tJ
  • U'.11~JOl'I
                                                                                                       '°"'

Nl Nozzle to Shell Scan Limits at Top Dead Center Page 1487 of 2394 Peach Bottom Umt 3. PJRHl N1/\ Page _j,_ of _:]_ 32 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual RPV Nozzle Examination

  • HITACHI Coverage Calculation Sheet Peach Bottom Unit-3, P3Rl9, 2013 NlA N1A (PEA-3-004100)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required EJCam Area of Area Length Percent EJCam Volume= 48.9 Area Sq. in. Scanned Scanned Scanned Scanned 60' T-Scon IS61 I A 44.6 10.2 20.9% 360 10.4% 60' T-Scon IS41 I A 43 4.3 8.8% 360 4.4% IK!> 1'-Scon '""' I A 4.J 4.J llJU.V7'1 jll\J 50.0% 60' T-Scan IS61 I 60' T-Scan 1541 I I I I I It<:. l'*Scon 1:.:.1 I I 60' T-Scan 156! I 60' T-Scon 1541 I I I I I I IRS P-Scon ISSI I 60' T-Scon IS61 I 60' T-Scon 1541 I I I I IR:. l'-5con 1551 I I 60' T*Scan {561 I I I I I I 60' T*Scan {54) I I I I IK5 P-:.con 1ss1 I I I I I I

                                                                                                  -*  -        pos1te coverog         -   --
                                                                                                                                                   """ 111~c.i u:

Comments: - A: Monuol scanning wos restncted due-lo the nozzle conf19urot1on. Note - This coverage colculot10n 1s vohd for ASME Sect10n XI. 2001 Edil!On w/ 2003 Addenda. 2004 Ed1t1on w/ No Addenda and the 2007 Ed11Jon w/ 2008 Addenda Note - Rounding methods may affect cokuloted values S6 - Supplement 6. S4 - Supplement 4, 55 Supplement - 5. Weld length in degrees. Peocn Bonam Unll*l. PJR19 Page_.L.011_ Page l~i% of 2394 33 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots Peach Bottom 3 N1 - Recirculation Outlet Nozzle NIB (PEA-3-004200) NS T-Scan Exam Volume - 26.2 Sq. In. FV T-Scan Exam Volume - 19.6 Sq. In. Inner 15%T Exam Volume (IRS & 60°T) =4.2 Sq. In.

                                                                                        =

60" NS T-Scan achieved 0 Sq. In. 60" FV T-Scan achieved= 13.6 Sq. In.

                                                                                                =

Inner 15%T 60" T-Scan achieved 4.2 Sq. In. 60"T I

)P Ii'

-......./ Cl _..i) 34 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom 3 N1 - Recirculation Outlet Nozzle NIB (PEA-3-004200) NS T-Scan Exam Volume - 26.2 Sq. In. FV T-Scan Exam Volume - 19.6 Sq. In. Inner 15%T Exam Volume (IRS & 6091") =4.2 Sq. In. 60" NS T-Scan achieved= OSq. In. I

                                                                                   =

60" FV T-Scan achieved 6.1 Sq. In. Inner 15%T 60° T..Scan achieved= 4.2 Sq. In. I I I I I I I 60"P I 60"P I I I I I-- I iP I S' I I

~                  I 0                  I-

"71 -0 35 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots HITACHI Reactor Pressure Vessel Coverage Calculation Sheet Peach Bottom 3 / PB3R18 N18 NIB (PEA-3-004200) Fall/ 2011 CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume= so. Area Sq. In. Manual Manual Manual Manual 60° T-Scan 154 UC A 42 4.2 8.4% 360 4.2% 60"T-Scan S6FV A 19.6 13.6 27.2% 360 13.6% 60° T-Scan (S6 NS A 26.2 0 0.0% 360 O.Oo/o 60° P*Scan IS4 UC A* 4.2 4.2 8.4% 360 4.2% 60° P-Scan 1ss FV> A 19.6 6.1 12.2% 3SO 6.1% 60° P*Scan (S6 NS) A 26.2 0 0.0% 360 0.0% 60° T-Scan S4UC 0 0 so* T-Scan S6FV 0 0 60°T-Scan S6NS 0 0 60" P-Scan S4UC 0 0 so* P-scan 56 FV 0 0 60° P-Scan (56 NS 0 0 so* T-Scan IS4 UC 0 0 60° T-Scan 56 FV 0 0 60° T-Scan CS6 NS 0 0 so* P-Scan CS4 UCl 0 0 60° P-Scan CS6 FV> 0 0

~                 so*  P-Scan (::>ti N~}                                     0                                     0 S'

P\  % Total Composite Coverage= 28.1% Rev. 0 !ll23I05 0 "1 Comments: A - Manual UT scanning was restricted due to nozzle configuration. -0 Note - Rounding methods may aHect calculated values. UC-Underclad, FV-Full volume, NS-Near Surface. Weld length In degrees. 36 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI RPV Scan Plan Peach Bottom Unit-3 N2 - Recirc Inlet Nozzle N2C (PEA-3-004500)
                                                                       .,_,5.,.TSSEun!VOlumo*'35q In iCi 54 Earn Volume
  • 4.3 Sq. k1 GO'"S&E..mV~e*363Sq.kl lnnar 15%T 55 &an VOiume Actua"8d 60" S< Eum VaUno Adlieved
  • USq. In a* 3 Sq tn 60" sa i;..., v...... Adlloved c 1s.* Sq. 1n ft E.uminllllDn woU1"IO I o.w Cade Cua N-613-1 Ci'cumfetantlml ~ af Iha DUIDJ 85"T ocr II nal reqund 18.W .... 2001 Eduon WI 2DllJ Adoenda Neat surface T*lan nol ntqund due lo wald cap rostncloon
                                                                                                 ,. O' OO"T                                         &O'T N2 Nozzle to Shell Scan Limits ot Top Dead Center Peach Bollom U..1-3. P3R19                               Page 14~~C0f 2394 Poge ...£ 01_.h.

37 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual RPV Nozzle Examination

  • HITACHI Coverage Calculation Sheet Peach Bottom Unit-3, P3Rl9, 2013 N2C N2C (PEA-3-004500)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area of Areo Length Percent EJCom Volume = 40.6 Areo Sq. In. Scanned Scanned Scanned Scanned 60" T-Scon 1561 I A 36.3 15.4 37.9% 360 19.0% 60" T-Scan 1541 I A 4.3 4,3 10.6% 360 5.3% IRS P*Scan 1551 I A 43 4.J 1000% 360 500% 60" T-Scan 1561 I I I I I I GO" T-Scan 1541 I IRS P-Scon i.:i:u I I 60" T-5can 1561 I I 60" T-5con 1541 I I IRS P-Scan 1ss1 I I 60" T-5con 1561 I I I I 60" T Scan 1541 I IRS P-5can l~~I I 60" T-Scon 1561 I 60" r -Scan 1541 I I I I IRS P-scan 1ss1 I

                                                                                                % Ta1al Campos11e coverage,.        74.:3%

ii.- '" .. :~: Commeri!S. A-~ Manual scanning was resfr1ctedCJue tothe nozzle cont1g urat1an Note This cove1oge calculauon is valid for ASME Section XI, 2001 Ed11ton w/ 2003 Addenda. 2004 Edition w/ No Addenda and !he 2007 Ed1t1on w/ 2006 AddenCIO Note - Rounding methods may affect calculated values 56 - Supplement 6, S4 Supplement 4, 55 Supplement - 5 Weld length 1n degrees. Peaeh Bottom Unol-3, PJRTB Page 14~C0f 2394 Page _!:j_ of_..!::.__ 38 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom Unit-3 Recirc Inlet N2 Nozzle N2D (PEA-3-004600) 60° NS Exam Volume= 17.6 Sq. In. 60° FV Exam Volume= 19.8 Sq. In.

                                                                                                      =

S0° (Inner 15% T) Exam Volume 4.3 Sq. In. S0° NS T-Scan achieved= 0.S Sq. In. 60" FV T-Scan achieved= 17.1 Sq. In. n 60" (Inner 15% T-Scan achieved = 4.3 Sq. In. I I I I I ;I\ T-Scan 60"T so*r I I I L_ I I ~ I I r- I "' I ~ I 0 "II ----i ~ 39 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Peach Bottom Unit-3 Recirc Inlet N2 Nozzle N2D (PEA-3-004600)

                                                                                                 =

S0° NS Exam Volume 17.S Sq. In.

                                                                                                 =

S0° FV Exam Volume 19.8 Sq. In.

                                                                                                         =

S0° (Inner 15% T) Exam Volume 4.3 Sq. In.

                                                                                                   =

60° NS P-Scan achieved 0.1 Sq. In.

                                                                                                   =

S0° FV P-Scan achieved 7.5 Sq. In. Inner 15%T Scan achieved =4.3 Sq. In. I I I I I I I II

                  ~Scans II so*p I

I L_ I -;YJ I s- ....J 0 Tl o<? l I I I l-40 of 53

Unit 3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots e HITACHI Reactor Pressure Vessel Coverage Calculation Sheet Peach Bottoms f PB3R18 N2A IN2D - bmj I Fall I 2011 CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area Scanned of Area Weld Length Percent Exam Volume= 41.7 Area Sq.In. Manual Manual Manual Manual 50° T-Scan (54 UC A 4.3 4.3 10.3% 360 5.2o/o 60° T-Scan S6 FV A 19.8 17.1 41.0"k 360 20.5% 60° T-Scan S6 NS A 17.6 0.6 1.4% 360 0.7% 60° P-Scan (S4 UC A* 4.3 4.3 10.3% 360 5.2% 60° P-Scan SS FV A 19.8 7.5 18.0% 360 9.0% 60° P-Scan (SS NS) A 17.6 0.1 0.2% 360 0.1% 60° T-Scan (S4 UC 0 0 60° T-Scan S6 FV 0 0 60° T-Scan SS NS 0 0 60° P-Scan S4UC 0 0 60° P-Scan S6FV 0 0 60° P-Scan SSNS 0 0 60°T-Scan S4UC 0 0 60°T-Scan SSFV 0 0 60" T-Scan S6NS 0 0 60° P-Scan S4 UC 0 0 60° P-Scan SS FV 0 0 50° P-Scan (S6 NS 0 0 ~  % Total Composite Coverage= 40.S'Yo 5' Rft. D !11231115 m Comments: A - Manual UT scanning was restricted due to nozzle configuration. VI 0 n Note - Rounding methods may affect calculated values. UC-Undercfad, FV-Full volume, NS-Near Surface. Weld length In dearees. ~ 41of53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

                                                                                                                          'RH<>~ it Ob'i eoo
 ~                                             RPV Scan Plan

' .J HITACHI Peach Bottom Unit-3 N2 - Recirc Inlet Nozzle N2F (PEA-3-004soo) lnt1er t !'i~ T SS F.%01m V:>>lulf\C ,. .a 3 Sq In. 60" S4 E:orn Volume : '1 J Sq tn eo* S5 E"""' V~lume ; 36 3 Sa In 1n-ier 15~ T S!i E:.ie:arn Volume Ac:11,evea - "' J SQ Ir

60. Sol E*om VOiume Achieved :: '4 J SQ In Sol' :si; ECJm VOlu'llC AGhoe,..d =15.4 Sq In
                               't                               E.irammuonw&ume .a..w. Cod'!C3So? N-61J*1 C*cun'l1tretll ill e,.arrwiation or Ql.e ouk!* lb~ T oo*                               *snot requ'fe::l l a .w I"* '0C1 E~tOf"I WI 2003 i\ddenda Ne61r sur:ace T*scan net 1Dq\J1rt:a aJr to we10 cap
                                                                ~tllttloO .

4 Ct' 14 o* 60" T llO-Y

                                 'J2 Nozzle to Shell Scan Limits ot Top Dead Center IJ '-/ or 7 42 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots

                                                                                                                         ~fO,_TiL06'18tlD m '~°' *'

I '!'. '1 Manual RPV Nozzle Examination

        ~            !    HITACHI
           -._:,..-                                                                Coverage Calculation Sheet Peach Bottom Unit-3, P3R20, 2015 N2F NOZ                          N2F (PEA-3-004800)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required EMam Area of Area Length Percent Exam Volume= 40.6 Area Sq. in. Scanned Scanned Scanned Scanned 60' T-Scari 1561 I A 36.3 15.4 379% 360 19.0<;{, EC' T-Sccn (54) I A 4.3 l..3 106% 360 5.3% IRS F-Scon 1SSI I A 4.3 4.3 100.0% 360 50.0'!!: co* T-Scan !S6i I I 60° --scan (Si.I I IRS F-Scon (551 I 60° T-Scan (561 I I 60' T-Scan (5£.1 I IRS ;:i.scon lS51 I 60° T-Scan 1561 I 60" T-Scon iSt.l I IRS P-Scor. 1551 I 60' T*Scon (Sf>I I 60' T-Scon :S41 I IRS P*SCO" ISSl I I

                                                                                                  % Total Composite Coverage= -         7.'...3%
                                                                                                                                                      ~, .... Cl ci \YU Corrrents.           A - Manua1 scorirung was restrlc<e-d due fo the ~owe CO"lligurot on.

l\ote - -his ca\*croge cclcJlot1on is vohd for ASME Scct1or XI 2CC1 Ea1uon w/ 2003 Addenaa Nole- Round ng methoc, rrcy aHect cakulal~d val Jes 56 - S"pple'l1en1 6. 54

  • Suop'em,;nl I.._55 51..pp e>nent
  • 5 we a lcnath 1n decrees fJ f oF 7 43 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

  • HITACHI RPV Scan Plan Peach Bottom Unit-3 NS - Core Spray Nozzle N5A (PEA-3-003800) 111ncr 151114.T SS Eaam Vof!Jme
  • l 6 Sq In 15a* S4 Eli..n Volume
  • 3 Q Sq kt 60" SO E*.m Vokdne
  • 33 D SQ In Inner 15%TS5£.1omV~~
  • 38Sq In
                                                                           &0° 54 EA*n \lolldM Ac::tweW'd .. 3 a Sq m
                                                                          &a* se Eaam VoturN ~
  • 12 e SCI '"
                                                                           &1t1W\OUM VOluntG' a w Cod* Case fHI 13-'

Ctrc;aanft'fef11ud **~ Df the: o.tlat' 15..,T II not teQUWed f

  • w In* 2lXU EdltMln WI 2001 Add""IQ tttor surface T*acan no1requnaouc1a WWld eap It 611"1
                                                                                                 ~

I * " NS Nozzle to Shell Seen Limits ot fop Deed Center Pe;i,cn Souom Urnt-J, P3R 19 Page S of _ft_ Page 14!fil'bf 2394 44 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots Manual RPV Nozzle Examination

  • HITACHI Coverage Calculation Sheet Peach Bottom Unit-3, P3Rl9, 2013 NSA N5A (PEA-3-003800)

CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld length = 360. Required Exam Area of Areo length Percent Exam Volume = 36.6 Area Sq. In. Scanned Scanned Scanned Scanned

                      &0" T-Scan 1561      I     A             33.0             129             35.2%             360             176%

60" T-Scon 1541 I A 3.6 36 98% 360 49% IRS P-Scon ISSI I A 3.6 3.6 1000% JW -501)% 60' T-Scan IS61 I I I I 60" T-Scon IS41 I I I I I IRS P-Scon IS51 I 60" T-Scon 1561 I I I I I 60" T-Scon 1541 I I T IRS P-Scon 1551 I I I 60" T-Scan 156) I I I 60" T-Scon IS41 I I I I l IRS P-5con 1551 I I 60" T-Scan IS61 I I 60" T-Scan IS41 I I IRS P-Scan ISSI I I I

                                                                                               % Total Composite Coverage:        72 5%
                                                                                                                                                   . ..  *'lol *i Comments        A  Manuo1 scanning was restncted due to lhe noule conhgurat1on Nole This coverage colculouon 1s valid for ASME Section XI 2001 Edilion w/ 2003 Addenda 2004 (d111on w/ No Addenda and the 2007 Edition w1 2008 Addenda Note - Rounding methods may affect coh:uloted value> S6 - Supplement 6, S4 - Supplement 4 SS Supplement 5 Weld length 1n degrees Peaell Bollom UM-3 PJR 19                                                                                                          Page_!/_ DI _k_

Page 14 t!J"of 2394 45 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots . ) HITACHI RPV Scan Plan Peach Bottom Unit-3 N9 - Control Rod Drive Nozzle In...,

  • 3'W-I !;<,~ff* V0'4""~ - '4 ~ 5q. t1 f10"' -;1, l11oni llobme * '* 1 s11 Ir 60" SG c...,,. Vclume ' 19D SQ II inner  :~~t..J S~ r-WO~ Volume l\i:t.IC\fe'C
  • Ji I ~I *O.

60" St. &::Irr VrJu,..e Ac.hil?'.h.~ .. ~ l SQ .. cc* 5& ~ vck.imt? Ac.h:l'VCa -1113 SQ 1n E>iomino1-on.tOM.imc1awC:iceC'3:1ot!..,~1J. C*rlu1nfe1en~1 e"~mincl'.CVI o'" 'l'\e o.. tc* es~u I) nol rcqui1..u i.a.w l'le 2001 Ftft.on ""' ;:OOJ '-d::le'l:ll

                        <t.                UP.t,. !!UlttJte * ~t:ll not l'"'lllMt"IJ Ot/ltl l it Wt-hi OU.
                                           ,~ :rrcllon nn I I                                                                       :J :'t lS                                                            *=" r
                                    ..r *
               ,1 I

I N9 Nozzle to Shell Scan Limits at Top Dead Center

                                                                                                              ~~6 ~of~

q.~.,s (9 46 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots ti

 -~~.-,,

\;* / HITACHI RPV Scan Plan ~-~ Peach Bottom Unit-3 N9 - Control Rod Drive Nozzle

                                                                                     , ,,,.~,.;. *  ... -s:   t*il~Vcu1""e=           !Sq,,..

1(' f(., " ~.;, t*.lmV,....,me ""'- 1. Sri

  • 60:' S6 ~.:JfTI V::>lt.,..<e - H 0 S-1 111 l,'ltl r: !i'nT' SS : .. cm 1.01..irne .'\i;httt\le:J ; 0 :> ~ * \

6;J .. ~ .. t."*Jl'T'f iJc!ur--e A<'M"'.*e:I ... 00 So M o;O'"Sbh*.r.1 ' lch.i~ Ar.1\ *Fvt~ - i0.1 511.11: II :11ntTll'10l~Lr* vc 1*.J"\e 1nw. C D'"!~Cr. !.fl C: rcumtP.rP.nl :J 1 C*nlT"1'10l1of1011tie ~le* 8)*,f N-6u-: s nee *e1;.11a*J ow. t..e 2C'Nl Ei1*hnr: w/ 7001 ktc'1 n.'J:..

                                            \       <t.                              '.*ar J:11*fo.:t1T-<<on111H *~:Ju1ttl.J uu~ *.o we ~a :o;
                                             .\                                      re;tu*.:.\;n Ii                            \ 'c 1\

I\

                   /1                                                                                     ,,*:a*.-
                                                          ,I *- *-
                                                                         £.."': *T
                                                      ,." / J------- ./-         *------

I l- - -- _t,; *-I / ,,,

                                                                                                    /            -

_,..- '( I i __,./

                       ........ )****......        ..::.. *       ~--...                                                                                 ----,

I ,' 1} ~/ /

                  'I              I            / "(_,

I ,.v" j

                  \1            -~- /-- _,, - _j
                    *:<~                                          I
                       --..=-..-:::::::::=-
  • I
                                                                                                                                                   --====_j N9 1'.ozzle to Shell Scan Limits@ Insulation Suppon Brocket Limitauon
                                                                                                                                                               /)c,t5     H' $o(7
                                                                                                                                                                     'l * .:1'1. 15 47 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots 1$ -) HITACHI Manual RPV Nozzle Examination Coverage Calculation Sheet Peach Bottom Unit-3, P3R20, 2015 N9NOZ CODE CROSS-SECTIONAL AREA TOTAL CODE COVERAGE Percent Weld Length = 360. Required Exam Area of Area Length Percent Exam Volume = 41.6 Areo Sa. In. Scanned Scanned Scanned Scanned 6Q' T-Scon 156) ) A 373 153 368% 340 174% 60' T-Sccn (541 I A 4.3 4.3 10.3% 340 u.9% IKS P-Scor 1~51 I A 4~ l'.j 1UU ,U70 350 48.6% 6Q' T-Sco'l 1561 I 8 373 lC.: 243% I 20 0.7% 60* T-Scor> (54) I 8 il.3 0.0 00% 20 C.0% IRS P-SCOI" 1551 I B l..3 0.0 0.0% 20 00% 60' 7-Scon 1561 I 60' T-Scon 1541 I IRS P-Scon l~SJ I 60° T-Sc:in 1561 I I 60° - -Sc:m (54) I l=lS P-Scan 1551 I 60° T-Scon IS6l I 6C* T-SCC" (54) I IRS P-Scon IS5J I

                                                                                                    % - 01crcompos1te Coverage=          *1:.5%
                                                                                                                                                     ..... - .:11.>;:- :1 Comments       A - Monu::il sc:mnirg .Nos restnCted due Lo tne nozzle conf1;iura!J0'1 8 - Monuol scarr ng was *e;;1*1:ted dLe Lo the 1nsulot1on s~pcort bro:<<el Mot~ - -hi> coverage colculo11c- is vo 1c fo* AS"1E Section t<I. 200: Ed:t1on wl 20CJ Addenda.

Note - Rounc1r;:i rrethad5 may ai'ect ; alr uloted \*Clues 56 - Supplement 6 54 - Supplement 4. 55 S~ppler'oe'1t 5 Weld lengr, m deg re~s PIJ<at.- t.. al 9 48 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots l [ -* HITACHI Wall Thickness S.te: Proch Bollom lJlllt ~ ReponNo" Profile Sheet PrCjeCt ~ 1@!!!!!

                                                                                                                                             ~

System: PoWon I o* I 90'

                           ~

I 180' I l70' I ComponentlD Number. ~

                                                                                                                       ~m                  rn         14 0.65"     NIA       NIA       NIA        Crown Height                ~

rn ' f4I [fil 0.6S"' NIA NIA NIA Crown Wodlh: l.2rr O.llJ" I NIA I NIA I NIA I Nominal Diameter. 12.U' I ~ UPST Component \ ;/ Pene11alion DNST Component D.113" I NIA I NIA I ~~ Weld length: ~ NIA I NIA I NIA I NIA I -FLOVi/ .... I l Flo1d ~ Pipfc t J- .i!fG- Robert Glesentt

                                !!   !!/llV20ll 1 {Q/I/~--              -,,-; 9k/,1}t                     t\     LL           q~~~                                     ~

lniltOls Dfownby: Level* Date: GE Reviewed By: Level Date. U tiiilvReview: Date: Oote: Poge  !! of !l Page 1793 of 2394 49 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots

Exelon Supplemental Report Report No UT*15Jef Oil~

3 Of 5 Component ID: 12-1-2R Summary No 162410 Exam1ner Olson, Chad M. &../OU Le vet: II Reviewer* ~'1T.L4.J>e 1 ~) I z. Date: /l!).1 1 S 1 Examiner _N_l_A_ _ _ _ _ _ _ _ _ _ _ _ __ Level~ S1teReview ::.,6 9 .,.~ Date: ~ Level:~ j ~re.~ Other. N/A ANll Review: Comments. Sketcn or Photo: Y'AL\& ~ ~

                                                                             ~
                                          't.
                           ~
                          "A 1

N/A.

                                       \~*~*
                              ,- -- ~ ,__:_:_:iZU--------
                                          ../

c

                                              ...< o~
                                                    *;'13          Q_s~
                                                                                             "' ..:k,.tµ ~ ~ ~ c;;;o':l M. Ds * .5111'"

11

                                                                                          ~ 'ts Bd,.. 1.-<1S *~ .. ~f- .11" o""r 1.S'15 e.;u. 5'.io~ ~;.,-\I St:o....~~u;I) o:z.s**<1.1*' :z.15 C:,.,... .z-,s-=. 1.sqc:;.- ,.,-i,. I P..~.O'-~~      SQ'"l"o
                                                                                                                        ~ -:.;}..- 3~.S%
                                                                                                                                      ~a.~.u~

IO@S 50 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots I ff J

 ............ T.. h~....... I"'*

IHI Southwest Technologies Examination Summary Record Slte: Peach Bottom Power Slatlon Unit 3 UUlltv: Exelon Generation IOutaae: P3R20 Summarv Sheet No. 001100 Svstem: Reactor Pressure Vessel Una Subassemblv: Weld Reoalr 35" Identification: RW-1 NOE NOE Callbratlon Exam Sheet Method Proc/Rev/ChaRCN Examination SheatNo. No. NRI Other Remarks AUT ISwT-PDl-AUTS/110/1 Probe 1 1100001 36&37 x - AUT ISwT-PDl-AUTS/1/0/1 Probe2 1100002 36&37 x - AUT ISwT-POl-AUTS/1/0/1 Probe 3 1100003 36&37 x - AUT 1SwT-POl-AUT5/1 /0/1 Probe4 1100004 36&37 x - Examination Summary: This weld was examined from the inside surface using AIRIS-21 and Dynaray examination equipment. No recordable indications were detected during this examination. The examination was limited due the jet pump riser brace. The examination coverage was 78.1%. Examination Angles ror each probe included; PA60"-80"L, PA40"-50"S, PA30"-60°L, & PAO"L. Prepanid By: Steven J. ToJidl Signature: J.r:--l;<<M. J \

0. 1 f Data: to }o<t/w15 IHI Prolect ,.(a'.t'te';° Reviewed By:

Slgnatu...: Exelon Corp. J/r " jJ,J\

                                       ~?

Data: Reviewed By)i? ~ lf) ((~(! $ SJ,~aturei:/JJi/JJ/i {_,-- h Data: / O J

                                                                                                                       ~ tf//J ,.--

v 51 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NOE Coverage Plots IHI Southwell l*chnalD91**. Inc, Sile/Plant : Peach Bonom Unit l IHI SOUTHWEST TECHNOLOGIES AUTOMATED ULTRASONIC EXAMINATION RECORD Weld ldenllncallon: RPV-R\\-1 Pro/RC\ /Ch!!llCN: 0 ISwT-PDl-AUTS 110* I E:umlnadon No.: ID-36 Project No.: lS*Ol-427 Weld

Description:

Bekhne Region Repair DC\icc Confil!llration: 136-00016 Mod.Con(.: 1311-000IJA Scan Path Dra"*inl!.: 134-00142 E11m D*te E111mln11ion Time Surface Tcmneraturc °F Data Acquisition Operator (*) I SNT LC\*el: Start I End Start I End Carlos II. Barbcrino I IT IO*Ocl-1.S lll7 I 1131 99 I 99 Data AcqulsUlon Scan Controller Par*metcra Increment Allis/De1*1ce Planned Actual Scan Alia/Arm Planned Actual Poslllonal Parameters Controller. AIRIS-21 Lower Limit 288.75 288 75 Lower Limit 66.10 68.1-1 Beam Direction: C\\/OnlCcw/Up Scan. Arm U1111erlimit 306.75 305.85 Unner Limir 77.60 74.14 Probe Type: PA22*006 Increment: Device Inc. Interval (Rcsolulion) 0.90 DCI (Scan Resolution) 0.10 Scanning Speed: I S inches per second Mode: Automolic Scan Conversion Counts 400 Conversion Counts 400 Number of Scans: 21 Scan Motion: Bi-dircctionol Con version Um ts Inches Conversion Units Inches Device Position: A (180) Com:chon: NIA Moster Acquisition File: RPV ID CHl_O st.cw (CW)_bcam llVSctup Calibration Records: Euminalion "iotea: Probe Channel I Anl!le(s) Skew Sein Offset Sten Ofl!let H60-80°Ll 2-140-S0°Sl o* + l.SO(in) Probe I

  • I 7S(in) 1100001 3-(30-60°Ll 4-(0°)

Probe 2 H60-80°L 2-c4o-so*s> 270° + 3.00{in) + 014(in) 1100002 3-(30-60°L) 4-(0°) Enmin11ion Remarks: H60-80°L 2*(40-S0°S) Limiled cxamina1ion due 10 the proximitv oflhe ict pump risor bracket Probe 3 180'

  • l.7S{in)
  • l.50{in) 1100003 3-(30*60'L) 4-10°1 8:. 511ccimcn holder H60*80°L) 2-(40-SO"Sl
  • 0.24(in) 1100004 Probe 4 90°
  • 3.00(m) 3-(30-60°L) 4-(0' )

Data Analysts Increment & Scan Po1illon1 Actual Recordable lndlc81ion1 Analyst Remarks Increment Posi1ion Scan Position Yes No NA Anochmcnt: Scan No.(s) S1or1 SIOP S1an Slop Channel I 0 0 n 1-20 288.75 305.85 68.14 74.14 Probe I Channel 2 0 0 D 0 Yes 0 No Channel 3 0 0 0 Further Evaluation Channel I 0 0 0 Required: Probe 2 Channel 2 n 0 D Channel 3 0 0 0 0 Yes 0 No Channel I 0 0 0 Archh*e Media: Probc3 Channel 2 D 0 0 Channel 3 0 0 0 0 Exlcmal Hard Drhc: Channel I 0 0 0 Probe4 Channel 2 0 0 D 0 CD-ROM f\ Channel 3 0 0 0 DVD-ROM

                                                                                          ~ """ \

Analyst I SNT ~\'Cl I Date: Carlos i\I. Barren/ Ill/ 10 Oct 2015

                                                                                        \                  ~~
  • -*---** .. --~- *- ..... \ \

52 of 53

Unit3 Peach Bottom Atomic Generating Station Fourth ISi Interval Limited Coverage NDE Coverage Plots IHI Southw*U Te<hn*legin. Inc. Sile/Plant : Peach Bollom Un ii 3 IHI SOUTHWEST TECHNOLOGIES AUTOMATED ULTRASONIC EXAMINATION RECORD Weld Identification: RPV-R\\'-1 Pro/Rcv/Che/ICN: ISwT-PDl-AUT5* I *O ' I Esaminalion :"io,: ID-37 Project No.: IS-01-427 Weld Descrinlion: Bckluic Rcl!IOn Re1111r Del*ice Conlieuration: 116-00016 Mod.Coor.: 138-000IJA Scan Path Drawin11: 134-00142 Exam Date Examination Time Surface Temperature °F Daca Acquisition Operalor (s) I SNT Lenl: Start I End Start I End Curios II. Barberi no I IT IO-Oc1-15 1142 I 1152 99 I 99 Data Acquisition Scan Controller Parameters Increment Asls/Dc1*ice Planned I Actual Scan Asia/Ann Planned I Actual Positional Parameters Conlrollcr. AlRlS-21 LowerLimil 288 7S I 288.72 Lower Limit 75.73 I 75.73 Beam Direction: Cw/On Cc11/Up Scan: Arm U.,.,..rLimit 306.7S I JOS.67 U"""rLimit 87.23 I 8723 Probe Type: PA22-006 lnc~ment: Device Inc. lntel'\*al (Resolutioo) 0.90 DCI (Scan Rcsolulion) 0.10 Scanning Speed: I 5 inches por second Mode: Automatic Scan Conversion Counts 400 Conversion Counls 400 Number of Scans: 21 Scan Motioo: Bi-din:clional Con1*ersion UnilS Inches Con1*ersion Units Inches De\*1ce Position: A(IBO) Concc1ion : NIA .:\lasler Acquisition File: RPV ID CH 1_0 skew (CW)_bt'.1m. IJ VSca1p Calibration Records: Enminalion :"iotes: Probe Channel /Anl!lo<s) Skew Scan Offset Step orrset l-(60-80°Ll 2-C40-50°S) oo Probe I - l.75(in) + 1.SO(in) 1100001 3*f30*60°Ll 4-I0°) 1-(60-80°L) 2-(40-50°S) + 024(in) Probe 2 270" - 3.00(in ) 1100002 3-CJ0-60°L) 4-(0") Eumination Remarks: 1-160-BO"L) 2-C40-50°S) + 1.7.S(in) - l.50(in) 1100003 Probe 3 180' 3-(30-60. L) 4-(0") H60-80' Ll 2-c40-so*s1 1100004 Probe 4 90' - 3.00(in) - ll.24(in) 3-(30-60' L) 4-(0°) Data Analysis Increment & ScDn Positions Actual Recordable lndkadons AnDl\'9t Remarks Scan No.(s) lncremenl Posilion Sam Position Yes No NA Anachmcnl: Start Slot> Siert Slop Channel I 0 0 n 1-20 288.75 305.85 7S.73 87.23 Probe I Channel 2 0 0 0 0 Yes 0 No Channel 3 0 0 0 Fu rt her Evol uotion Channel I 0 0 0 Required: Probe2 Channel 2 D 0 LI Channel 3 0 0 0 OYcs 0 No Channel I 0 0 0 Archh*e Media: Probe 3 Channel 2 n f.il 0 Channel 3 0 0 0 0 External Hord Dri\'e Channel I 0 0 0 Probc4 Channel 2 0 0 0 0 CD-ROM z:Jumnel 3 D ..... 0 0 DVD-ROM Analyst I SNT Lc\*el I Dale: Carlos \1. Barrera / Ill / I 0 Oct 20 IS \.A \'\\~A 53 of53}}