ML19305B428

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-341/79-25 on 791218-21.Noncompliance Noted: Failure to Stop Work,Take Corrective Action & Establish Hold Points
ML19305B428
Person / Time
Site: Fermi 
Issue date: 01/21/1980
From: Erb C, Knop R, Lee E K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19305B422 List:
References
50-341-79-25, NUDOCS 8003190641
Download: ML19305B428 (12)


See also: IR 05000341/1979025

Text

-

_

- - -

.O

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No.

50-341/79-25

Docket No.

50-341

License No. CPPR-87

Licensee: Detroit Edison Company

2000 Second Avenue

Detroit, MI 48226

Facility Name: Enrico Fermi Nuclear Station, Unit 2

Inspection Conducted: December 18-21, 1979

by GlGve5&

'

Inspectors:

F.'J. d blonski

// /7/ 80

/

/

'f' g 'f/[. "

/[' Y#

'

E. W. K!

e

C.

/J5 [d

/

/~

n.

sf

' {C. %q

j

[

)

Approved By:

R. C. Knop, Chief

//2//f-

Projects Section 1

Inspection Summary

Inspection on December 18-21, 1979 (Report No. 50-341/79-25)

Areas Inspected: Follow-up of previously identified noncompliances/

unresolved items; independent inspection; mechanical work activities.

The inspection involved 84 inspector-hours onsite by three NRC inspectors.

Results: Of the areas inspected, three items of noncompliance were

identified.

(Infractions - failure to stop work, take corrective action,

and establish hold points.Section I, Paragraphs 1 and 2)

80031906g

_

.

DETAILS

.

Persons Contacted

Detroit Edison Company

  • T. Alessi, QA Director
  • R. Barr, Project QA Director
  • W. Everett, Project Superintendent
  • W. Fahrner, Project Manager
  • E. Hines, Assistant Vice President QA
  • W. Jens, Vice President Nuclear Operations
  • A. Walker, Site Project QA Engineer

Daniel InternrLional Corporation

  • M. Albertin, Assistant Project Manager
  • J. Blixt, QC Manager
  • J. Bolt, QA Manager
  • K. Dempsy, Assistant Construction Manager

M. Guest, Document Control Supervisor

  • D. Siefert, Project Manager

D. Wise, Procedure Coordinator

Wismer & Becker

D. Jantosik, Training Coordinator

  • C, Keller, QA Manager

W. Wright, Personnel Manager

  • E. Young, Project Executive Manager
  • Denotes those attending the exit interview.

Licensee Action on Previous Inspection Findings

(Closed) Noncompliance (341/79-13-03): Control of measuring and test

equipment. Checked radiographic laboratory and found lead numbers in

place and proper material identification. Calibration film tablets for

densitometer average checked at Wismer & Becker and NES. Determined new

film density tablets have been secured for each group. Corrective action

was in accordance with DECO's letter to NRC dated July 12, 1979.

(0 pen) Noncompliance (341/79-13-04): Control of special processes.

Radiographic shooting sketches nave been made of various source-film set

ups and reader sheets will now indicate the set up used. Lead identifica-

tion numbers were discussed in item 341/79-13-03 above. Bent penetrameter

and shim procedure was not reviewed.

Functional or Program Areas Inspected

Areas inspected are discussed in Sections I, II, and III of this report.

2-

.

Section I

.

Prepared by

F. J. Jablonski

Reviewed by

R. C. Knop, Chief

Projects Section 1

,

1.

Corrective Action - Stop Work

Reviewed all W&B Deviation Disposition Requests (DDR's) in the

Daniel series 2301-3871 for a period between December 1978-1979. It

appeared for the most part that the DDR's reflected problems which

should have been identified by implementation of W&B's QA-QC inspec-

tion program. For example, attributes included on weld process to

control sheets (WPCS), technique sheets, specifications, and proce-

dures were used as the basis for identifying deviations. ,

Deviations were numerous and included for example:

a.

Defects on vendor supplied materials

b.

Surface defects such as are strikes, punch marks, hack saw

cuts, etc.

c.

Mishandling of components, damage to weld end preps

d.

Weld rod control

e.

By passing of hold points

By passing of hold points is considered the most serious deviation.

(See Paragraph 2 below). The review of DDR's indicated greater than

40 instances where hold points had been by-passed. There did not

appear to be any decreasing trend over the period of review.

Similar findings were made by the licensee's agent during an audit

performed in January, 1979. Corrective action was delineated in W&B

letter 2184J dated July 26, 1979. Even though threat of dismissal

for violation of hold points was included, corrective action has not

been effective in preventing recurrence of the deviations. (No

dismissals have occurred). Further, in a W&B memorandum dated

November 19, '979 to the W&B Project Executive Manager, the W&B

Project Quality Manager rescinded letter 2184J as a means of pro-

viding corrective action and recurrence control.

NOTE: The vast majority of the above DDR's implied or stated directly

the need for training as_the means of corrective action to prevent

recurrence. A review was made of W&B training records, lesson plans,

test forms, etc. Personnel being trained and the type of training

-3-

.

appeared to be commensurate with ongoing activities,

i.e.,

lack of

.

training does not appear to be the underlying cause of the chronic

abuse of bypassing hold points.

During the period described above, the licensee failed to stop work

for by passing hold points in accordance with established procedures

of the site mechanical' contractor. This matter is in noncompliance

with 10 CFR 50 Appendix B, Criterion V as described in Appendix A of

this report. (341/79-25-01)

Also during the same period, the licensee failed to determine the

causes of conditions adverse to quality and take prompt corrective

action to preclude repetition. This matter is in noncompliance with

10 CFR 50 Appendix B, Criterion XVI as described in Appendix A of

this report.

(341/79-25-02)

2.

Hold Points

W&B had been identified previously be DECO's agent as having program

problems with timely corrective action. The problems are summarized

in Daniel letter to W&B dated July 13, 1979 *No. DIC9-2684. Two

"show cause" letters dated September 18, 1978 and February 1, 1979

have been issued. (Attachment I to the above document) Adverse

trends initially reported in June 1978 included several instances of

missed hold points as well as numerous generic welding deficiencies.

(Attachment 2 to the above document) A summary of program deficien-

cies included violation of hold points identified during Edison QA

surveillance and W&B/DIC QC activities, and analysis of weld problems

and rejection. (Attachment 3 to the above document)

A DECO site QA file titled, " Hold Point Problems" documents corres-

pondence between the period July 10, 1979 to November 2, 1979 regard-

ing their concern about the removal of Daniel mandatory QC inspection

hold points from W&B welding travellers. (An inspection hold point

is an arbitrary place reached in the installation process which is

not by passed unless witnessed and approved by an inspector. Examples

of welding installation hold points include fit up, pre and post

weld heat temperature, visual inspection, nondestructive testing,

etc.) As of October 9, 1979, Daniel QC, Edison's agent (designated

representative) was eliminated from imposing mandatory QC hold

points from weld process control sheets and I-6 (weld repair) forms.

First line inspection and verification activities have reverted to

W&B, an organization that has been ineffective, in correcting the

adverse trends (Between October 9, 1979 and November 10, 1979 there

were 12 DDR's which identified violations of mandatory hold points).

The inspectors stated his concern that the missed hold points meant

that the required inspections of attributes were not doen at the

required time and that this chronic condition has existed for a long

,

time. Deletion of mandatory hold points by the applicant's agent in

the midst of adverse trends is in noncompliance with 10 CFR 50,

Criterion X as described in Appendix A of this report. (341/79-25-03)

-4-

l

.

l

1

_ _ - . _-

_ . _ _ - _ _ - _ _

3.

Surveillance

.

Daniel procedure No. AP-IV-12 describes responsibilities and actions

to be taken relative to review, approval, and designation of contrac-

tor mandatory hold points. The procedure is not implemented unless

surveillance by Daniel QC indicates a need. Needs ar established by

noting adverse trends.

Definitions of surveillance and trend were not provided in any

established procedure; terms are discussed below.

Surveillance usually means to progressively monitor by randomly

.

witnessing and inspecting items and work operations before,

during, or af ter in-process construction.

Trend usually means the general course or prevailing tendency.

.

To effectively monitor a designated task or activity and determine a

trend, it seems necessary for responsible QC personnel to be present

in a work area observing specific attributes over a predetermined

time. Surveillance, i.e. random witnessing, cannot alone be effec-

tive in determining trends.

Definitive sample sizes and acceptance criteria must be established

which are based on recognized standard practices. Repeated failure

to follow procedures, implement corrective action, or have complete

disregard for documentation requirements are examples of trends

adverse to quality and which must be corrected.

For surveillance to be considered a viable method of inspection, it

is apparent the licensee needs a procedure defining sample size and

acceptance criteria for attributes included on process control

travelers which document mechanical installation. Further, an adverse

trend must be defined based on the surveillance activities and then

mandatory hold points imposed.

Due to time restraints, this matter was not completed, therefore it

is unresolved. (341/79-25-04)

-5-

.

Section II

.

Prepared by E. W. K. Lee

Reviewed by D. H. Danielson, Chief

Engineering Support Section 2

1.

Reactor Coolant Pressure Boundary Piping - Observation of Work and

Work Activities

The inspector observed fitting up and alignment of Residual Heat Removal

System Weld No. E11-2299-2W01 on Isometric drawing No. 6M721-2299.

It

was determined that procedure requirraents were met and good construction

practices were adhered to.

No items of noncompliance or deviations were identified.

2.

Safety Related Piping - Observation of Welding Activities

The inspector observed the following welding activities:

a.

Reactor Core Isolation Cooling System weld No. E51-3174-11WF2 on

isometric drawing No. 6M721-3174-1.

b.

Residual Heat Removal System welds No. E11-3178-3WFT and

No. E11-3178-3WF4 on isometric drawing No. 6M721-3178-1;

No. E11-3154-11WO on isometric drawing No. GM721-3154-1;

No. E11-3185-5WF1 on isometric drawing No. 6M721-3185-1;

and No. E11-3173-0W17 on isometric drawing No. 6M721-3173-1.

c.

High Pressure Coolant Injection System welds No. E41-3162-9WF1

on isometric drawing No. 6M721-3162-1; No. E41-3172-1WF2 on

isometric drawing No. 6M721-3172-1; and No. E41-3162-10WF1 on

isometric drawing No. 6M721-3162-10A.

d.

Core Spray System weld No. E21-3149-2W7 on isometric drawing

No. 6M721-3149-1.

It was determined that (1) work was conducted in accordance with

traveller; (2) proper welding materials were used; (3) welding procedure

requirements were met; (4) work area was free of weld rod-stubs, and

(5) physical appearance was acceptable.

No items of noncompliance or deviations were identified.

3.

Safety Related Piping - Observation of Work and WorkActivities

~

The inspector observed weld end preparation of Residual Heat Removal

System Weld No. E11-3160-1WO on isometric drawing No. 6M721-3160-1.

-It was determined that work performance met the applicable requirements

and good construction practices were adhered to.

-6-

-_ __

__ _ __-

___

.

No items of noncompliance or deviations were identific'.

,

4.

Safety Related Piping - Observation of NDE Work Activities

The inspector observed liquid penetrant examination of Residual Heat

Removal System welds No. E11-3184-0W10 and No. E11-3184-10W on iso-

metric drawing No. 6M721-3184-1.

It was determined that:

(1) procedure requirements were met, (2)

personnel were properly qualified and (3) indications were identified

on both welds by the examiner and welds were re-examined after surface

conditioning.

No items of noncompliance or deviations were identified.

5.

Safety Related Piping - Weld Heat Treatment

a.

Review of Procedure

The inspector reviewed W&B Procedure No. WB-C-118, Revision 2,

" Methods of Control and Monitoring of Preheat and Interpass

Temperatures".

It was determined that the procedure is acceptable,

b.

Observation of Werk

While observing welding activities for items stated in paragraph 2

of this report, the inspector determined that preheat met the pro-

cedure requirements.

No items of noncompliance or deviations were identified.

6.

Safety Related Piping - Special Welding Applications

The inspector observed the following repair work activities:

i

a.

Weld repair of Residual Heat Removal System Weld No. E11-3173-1WO

on isometric drawing No. 6M721-3173-1 and Core Spray System weld

No. E21-3144-02W5-C2-R1.

b.

Grinding defects of Reactor Core Isolation Cooling System weld

No. E51-3176-7WF4-R2 on isometric drawing No. 6M721-3176-1.

It was determined that (1) work was conducted in accordance with

traveller; (2) proper materials were used and (3) procedure

requirements were met.

.

No items of noncompliance or deviations were identified.

-7-

.

.

.

7.

Safety Related Piping - Welding Qualifications

The inspector reviewed the following documents:

W&B Procedure No. WB-E-118, Revision 6, including Interim Change

a.

Serial No. 95, " Welder and Brazer Qualification",

b.

Qualification record of eleven welders who performed welding on

welds stated in paragraphs 2 and 6 of this report.

It was determined that the above documents met the requirements of

.ASME B&PV Code Section IX.

,

No items of noncompliance or deviations were identified.

,

1

-8-

.

-

)

-

Section III

.

Prepared by C. M. Erb

Reviewed by D

H. Danielson, Chief

Engineering Support Section 2

1.

Control, Hanger Installation

a.

Control of drawings and procedures by the licensee and contractors

was checked by picking several drawing numbers being used in the

plant and matching the revision with the latest revicion in document

control. The following drawing numbers and procedures were checked

out.

Plant

System

Document Control

6M721-3172-1 Rev. H

HPCI

-H

6M721-3172-2 Rev. E

HPCI

-E

6M721-4161 Rev. D

HPCI

-D

SS-721-2995 Rev. B

--

-B

  • E11-2327-G04 Rev. B

-A

--

6WT-E41-7783 Rev. 0

-0

--

6VT-E41-7783 Rev. 0

-0

All the above drawings were in order except for the marked * one,

where the latest' drawing apparently had been issued to the field

before being programmed into the computer.

b.

The latest index of procedures were checked against those in use

with the following results:

Interim

Index Procedure No.

Title

Changes (ICP)

Rev. No.

WB-A-108 Rev. O

Identification

No. 130

0

& Control

Material & Parts

WB-C-120 Rev. O

General Trans-

O

--

portation Pro-

cedure

  • WB-Q-102 Rev. 5

Liquid Penetrant Rev. 6 on

9

Examination

3/79

-9-

.

  • WB-Q-103 Rev. 5

Visual Weld Ex-

No's 60, 107,

10

.

amination

113, 93

  • WB-Q-108 Rev. 4

Magnetic Particle 105, 49

8

Examination

WB-Q-109 Rev. 3

Ultrasonic Ex-

3

--

amination

.

WPS-7002 Rev. 12

Structural SMAW

132

12

Welding

The above procedures are initiated by Wismer & Becker Co., approved

by Daniel and by General Electric where NSS systems are involved.

To make a revision an ICP is initiated by W&B and goes to Daniel

for comment. This ICP is given a revision number and several ad-

ditions of ICP's without reissue of the procedure may be done.

You will note on 3 procedures * above the revision in the index

list is 4 or 5 numbers less than the actual number of ICP's.

This is considered to be an unresolved item, No. 341/79-25-05 because

of the difficulty in following the system and determining exact

status of changes with contractors such as GECo.

No items of noncompliance or deviations were identified.

2.

Calibration of Equipment

A check of the program for calibration of equipment used by W&B is

given below. A tag showing last date of calibration and due date for

another was found on W&B equipment which was kept in a locked stores

area.

Equipment

Time Interval

_

pressure gauges

6 mo. more often if required

by Engineering

contact thermometer

yearly

yearly

yearly

dial indicators

--

  • tong tester - Amps

yearly

yearly

voltmeter - ammeter

yearly

magnetic particle

6 mo.

,

- 10 -

.,

,_

.

_.

- - .

5

Those items marked with an asterisk would appear to have an overlong

,

period between calibrations, particularly where loaned out to many

different operators.

In the past, offsite calibration has been per-

formed by Toledo Testing, but this function will be performed in the

future by the DECO instrument Testing Laboratory. DECO use Ashcroft

dead weight testers for pressure gauges and have standards traceable

to NBS standards in other areas.

3.

Specification Deviations Valves

Three deviations on Powell Valves equipped with Limitorque operators

were examined.

In each case, a Deviation Disposition Request (DDR)

was issued and a diaposition to restore the part and a corrective

action to prevent recurrence stated.

DDR 2817, Valve No. V8-2141, Category "A", Install DCR-P0851

Disposition: Disposition valve operator into upward position

Corrective Action: Emphasize importance of following written

instructions at foremans meeting

DDR 2966, Valve No. V8-2160, Category A, Install 3071-31 Rev. A

Disposition: Rotate motor to comply 3071-31, Rev. A, Revised motor

Corrective Action:

Field coordination problem, train personnel

DDR M2975, Valve No. 4061-1, Category A, Install DCR 0678

Disposition: Rotate valve motor to proper position, See DCR 0678

attached.

Corrective Action: Do not install valve operator or limitorque in

downward position. Review field supervision.

The above cases illustrate a situation, where limitorques are being

incorrectly installed and the corrective action of more training is

ineffective.

No items of noncompliance or deviations were identified.

Unresolved Items

i

Unresolved items are matters about which more information is re-

quired in order to ascertain whether they are acceptable items,

'

items of noncompliance, or deviations.

Unresolved items disclosed

during the inspection are discussed in Section I, Paragraph 3, and

Section-III, Paragraph 1.

j

- 11 -

'

J

--

. *-

Exit Interview

.

The inspectors met with site staff representatives (denoted in the

Persons Contacted Paragraph) at the conclusion of the inspection.

The inspectors summarized the scope and findings of the inspection.

In addition, the inspectors discussed the eight previous times that

Criterion XVI, corrective action, had been violated at this site and

the high turn over rate of Wismer & Becker work force. The licensee

acknowledged the findings.

)

,

i

12 -

-

l

1