Forwards IE Insp Repts 50-317/79-18 & 50-318/79-15 on 791003-05 & Notice of Violation
ML19296B116
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 11/23/1979
From: Galen Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML19296B106 List:
References
NUDOCS 8002200090
Download: ML19296B116 (2)


See also: IR 05000317/1979018

Text

.

.

UNITED STATES

/pm arc ,D

o

o,

NUCLEAR REGULATORY COMMISSION

[

REGION t

f,g

$,

g

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

%; -

/

,,

.....

NOV 2 3 G73

Docket Nos. 50-317

50-318

Baltimore Gas and Electric Company

ATTN: Mr. A. E. Lundvall, Jr.

Vice President, Supply

P. O. Box 1475

Baltimore, Maryland 21203

Gentlemen:

Subject:

Inspection 50-317/79-18; 50-318/79-15

This refers to the inspection conducted by Mr. G. P. Yuhas of this office

on October 3-5, 1979 of activities authorized by NRC License Nos. DPR-53

and DPR-69 and to the discussions of our findings held by fir. Yuhas with

Mr. L. B. Russell and other members of your staff at the conclusion of the

inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within these areas, the inspection consisted of selective examinations of

procedures and representative records, interviews with personnel, and

observations by the inspector.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with NRC requirements, as set forth in

the Notice of Violation, enclosed herewith as Appendix A.

This item of

noncompliance has been categorized into the levels as described in our

correspondence to you dated December 31, 1974.

This notice is sent to you

pursuant to the provisions of Section 2.201 of the NRC's ' Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you

to submit to this office, within twenty (20) days of your receipt of this

notice, a written statement or explanation in reply including:

(1) corrective

steps which have been taken by you and the results achieved; (2) corrective

steps which will be taken to avoid further items of noncompliance; and (3)

the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosures

will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it

8002200 0 9 O

Baltimore Gas and Electric Company

2

NOV 2 31373

.

is necessary that you make a written application within 20 days to this

office to withhold such information from public disclosure. Any such application

must be accompanied by an affidavit executed by the owner of the infonnation,

which identifies the document or part sought to be withheld, and which

contains a statement of reasons which addresses with specificity the items

which will be considered by t'1 Commission as listed in subparagraph (b)

(4) of Section 2.790.

The iniormation sought to be withheld shall be

incorporated as far as possible into a separate part of the affidavit.

If

we do not hear from you in this regaro within the specified period, the

report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely,

f/

I-L, j sh

George ,H.

Smith, Chief

Fuel Facility and Materials Safety

Branch

Enclosure.s :

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection

Report Numbers 50-317/79-18, 50-318/79-15

cc w/ encl:

R. M. Douglass, Manager, Quality Assurance

L. B. Russell, Chief Engineer

W. Gibson, General Supervisor, Operations QA

R. C. L. Olson, Senior Engineer

K. H. Sebra, Principal Engineer