UNITED STATES
aREc ,
o
o
NUCLEAR REGULATORY COMMisslON
REGION i
y
y
$
..g
431 PARK AVENUE
KING OF PRUSSI A, PENNSYLVANIA 19406
%,
JAN 21 1980
Docket No. 50-293
Boston Edison Company M/C Nuclear
ATTN: Mr. G. Carl Andognini, Manager
Nuclear Operations Department
800 Boylston Street
Boston, Massachusetts
02199
Gentlemen:
Subject:
Inspection 50-293/79-22
This refers to the inspection conducted by Mr. D. Kehoe of this office on
December 13-14, 1979 at Pilgrim Nuclear Power Station, Unit 1, Plymouth, Massa-
chusetts of activities authorized by NRC License No. DPR-35 and to the discussions
of our findings held by Mr. Kehoe with Mr. R. Machon of your staff at the
conclusion of the inspection.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter. Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
Within the scope of this inspection, no items of noncompliance were observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspecticn
report will be placed in the NRC's Public Document Room.
If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure.
Any such application must be
accompanied by an affidavit executed by the owner of the information, which
identifies the document or part sought to be withheld, and which contains a
statement of reasons which addresses with specificity the items which will be
considered by the Comission as listed in subparagraph (b) (4) of Section
2.790. The information sought to be withheld shall be incorporated as far as
possible into a separate part of the affidavit.
If we do not hear from you in
this regard within the specified period, the report will be placed in the Public
Document Room,
b
8002280
-
-
.
.
Boston Edison Company M/C Nuclear
2
JAN ? t 1980
No reply to this letter is required; however, if you should have any questions
concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
-
,
n
Brunner, Chief
.
R ctor Operations and Nuclear
support Branch
Enclosure: Office of Inspection and Enforcement Inspection
Report Number 50-293/79-22
cc w/ encl:
P. J. McGuire, Pilgrim Station Manager