Forwards IE Insp Rept 50-293/79-19 on 791127-29.No Noncompliance Noted
ML19294B266
Person / Time
Site: Pilgrim
Issue date: 01/15/1980
From: Galen Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Andognini G
BOSTON EDISON CO.
Shared Package
ML19294B267 List:
References
NUDOCS 8002280113
Download: ML19294B266 (2)


See also: IR 05000293/1979019

Text

OR

.

.

UNITED STATES

p Ho ,D

o

o

NUCLEAR REGULATORY COMMISSION

/ ?o

REGION l

&

h

. j

631 PARK AVENUE

y w ij~#

'

5p .

KING OF PRUSSI A. PENNSYLV ANIA 19406

.....

J:1.'l ! 5 m

Docket No. 50-293

Boston Edison Company M/C Nuclear

ATTN: Mr. G. Carl Andognini, Manager

Nuclear Operations Department

800 Boylston Street

Boston, Massachusetts 02199

Gentlemen:

Subject:

Inspection 50-293/79-19

This refers to the inspection conducted by Mr. R. L. Nimitz of this office on

November 27-29, 1979, at Pilgrim Nuclear Power Station, Unit 1, Plymouth,

Massachusetts of activities authorized by NRC License No. DPR-35 and to the

discussions of our findings held by Mr. Nimitz with Mr. R. Machon of your staff

at the conclusion of the inspection, and to a subsequent telephone discussion

between Mr. Nimitz and Mr. M. G. Hensch of your staff on December 5,1979.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

-

these areas, the inspection consisted of selective examinations of procedures

ard representative records, interviews with personnel, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such infonnation from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790.

The information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified period, the report will be placed in the Public

Document Room.

80022 8v l h

.

.

Boston Edison Company

2

,,,, ! 5 U U

M/C Nuclear

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

-

Sincerely,

[' [- '

,!

-

(

I

';

(gsg.'/f. \\lL"~nn

1

l-

."

1

~'

-

George H. Smith, Chief

Fuel Facility and Materials Safety

Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-293/79-19

cc w/ encl: