ML19290E736
| ML19290E736 | |
| Person / Time | |
|---|---|
| Site: | La Crosse File:Dairyland Power Cooperative icon.png |
| Issue date: | 01/31/1980 |
| From: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Linder F DAIRYLAND POWER COOPERATIVE |
| References | |
| NUDOCS 8003140462 | |
| Download: ML19290E736 (1) | |
Text
d g* 880 9 UNITED STATES 0
f NUCLEAR REGULATORY COMMISSION
[
71( f,,j REGION lit e
g 799 ROOSEVELT ROAo
=y GL t.N E LLYN ILLINO15 40137 ON 31880 Docket No. 50-409 Dairyland Power Cooperative ATTN:
Mr. F. W. Linder Cencral Manager 2615 East Avenue - South La Crosse, WI 54601 Gentlemen:
This Information Notice is provided as an early notification of a possibly significant matter. It is expected that recipients will review the information for possible applicability to their facili. es.
No specific action or response is requested at this time.
If furtaer NRC evaluations so indicate, an IE Circular or Bulletin will be issued to recommend ar request specific licensee actions. If you have questions regarding this matter, please contact the Director of the appropriate NRC Regional Office.
Sincerely, 0)btfg ames G. Keppler Director
Enclosure:
IE Information Notice No. 80-03 cc w/ encl:
Mr. R. E. Shimshak, Plant Superintendent Central Files Director, NRR/DPM Director, NRR/ DOR PDR Local PDR NSIC TIC Mr. John J. Duffy, Chief Boiler Inspector, Department of Induatry, Labor and Human Relations 6003140y g
o.
i UNITED STATES SSINS No..
6870 NUCLEAR REGULATORY COMMISSION Accession No.:
0FFICE OF INSPECTION AND ENFORCEMENT 7912190666 WASHINGTON, D.C.
20555 7'r January 31, 1980
}
N j
D IE Information Notice No. 80-03 MAIN TURBINE ELECTR0 HYDRAULIC CONTROL SYSTEM Description of Circumstances:
On September 6, 1979, while performing a routine startup of the Trojan Nuclear Plant, a speed control problem was encountered during warmup of the General Electric turbine and increase of turbine : peed to normal operating speed (1800 RPM).
Technicians were notified and trouble shooting in accordance with the technical manual was commenced to resolve the apparent oscillation between the primary and backup speed control circuits which was hindering normal turbine startup operations.
The technical manual indicates that it is permissible to remove either the primary or backup low value gate circuits which contain speed and acceleration error amplifiers.
Upon removal of the primary low value gate circuit card, the backup card amplifiers, coming from a saturated condition, became the controlling circuit.
During the shift in control circuits (primary to backup), the speed / acceleration error signal went to maximum which resulted in a full open signal to the turbine control valves.
Under existing plant conditions this appeared to the safety injection system as a major steam break downstream of the main steam isolation valves which resulted in a safety injection system actuation and reactor trip.
The Electrohydraulic Control System (EHC) technical manual indicated that slight load changes are likely when a low value gate card is removed.
The effect on an unloaded turbine appears to be much more significant and tests conducted by
- GEK Instruction Book 11381-0, " Speed Control Unit", Maintenance Section, Page 4.
o, IE Information Notice No. 80-03 January 31, 1980 Page 2 of 2 Trojan personnel indicate that the transient is initiated whether the turbine is at a set speed or in an acceleration mode to a set speed.
Discussions with General Electric personnel by the licensee have been initiated in an attempt to verify the phenomenon observed and, if applicable, alert other facilities which operate a turbine with a MK 1 EHC System regarding the potential operation of the control valves when trouble shooting the speed control unit in accordance with existing instructions.
This information is provided as an early notification of a possible significant matter.
It is expected that recipients will review the information for possible applicability to their facilities.
No specific action or response is requested at this time.
If further NRC evaluations so indicate, an IE Circular or Bulletin will be issued to reconimend or request specific licensee actions.
If you have questions regarding this matter, please contact the Director of the appropriate NRC Regional Office.
Enclosure:
List of Recently Issued IE Information Notices
IE Information Notice No. 80-03 Enclosure January 31, 1980 RECENTLY ISSUED IE INFORMATION NOTICES Information Subject Date Issued To Notice No.
Issued 80-02 8X8R Water Rod Lower 1/25/80 All BWR Facilities End Plug Wear holder power reactor OLs or cps 80-01 Fuel Handling Events 1/4/80 All holders of power reactor OLs and cps 79-37 Cracking in Low Pressure 12/28/79 All power reactor OLs Turbine Discs and cps 79-36 Computer Code Defect in 12/31/79 All power reactor OLs Stress Analysis of Piping and cps Elbow 79-35 Control of Maintenance 12/31/79 All power reactor facilities and Essential Equipment with an OL or CP 79-34 Inadequate Design of 12/27/79 All holders of power reactor Safety-Related Heat OLs and cps Exchangers 79-33 Improper Closure of 12/21/79 All power reactor facilities Primary Containment holding OLs and cps Access Hatches 79-32 Separation of Electrical 12/21/79 All power reactor facilities Cables for HPCI and ADS holding OLs and cps 79-31 Use of Incorrect Amplified 12/13/79 All holders of power reactor Response Spectra (ARS)
OLs and cps 79-30 Reporting of Defects and 12/6/79 All power reactor facilities Noncompliance, 10 CFR Part 21.
holding OLs and cps and vendors inspected by LCVIP 79-29 Loss of NonSafety-Related 11/16/79 All power reactor facilities Reactor Coolant System holding OLs or cps Instrumentation During Operation