ML19289E832

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-334/79-07 on 790315-16.No Noncompliance Noted
ML19289E832
Person / Time
Site: Beaver Valley
Issue date: 04/10/1979
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Dunn C
DUQUESNE LIGHT CO.
Shared Package
ML19289E833 List:
References
NUDOCS 7905290154
Download: ML19289E832 (2)


See also: IR 05000334/1979007

Text

Tk

~ , < -

c/

4

UNITED STATES

y g) *

g

NUCLEAR REGULATORY COMMISSION

il2 y

4 (

o

REGION I

% ub i

jE

G31 PARK AVENUE

f

KING OF PRUS$1 A, PENNSYl_VANI A 19406

q

j

+.***

AIR 10 im

Docket No. 50-334

Duquesne Light Company

ATTN: Mr. C. N. Dunn

Vice President

Operations Division

435 Sixth Avenue

Pittsburgh, Pennsylvania

15219

Gentlemen:

Subject:

Inspection 50-334/79-07

This refers to the inspection conducted by Mr. D. Beckman of this office

on March 15-16, 1979 at Beaver Valley Power Station, Unit 1, Shippingport,

Pennsylvania of activit!es authorized by NRC License No. DPR-66 and to

the discussions of our findings held by Mr. Beckman with Mr. H. Williams

of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of th_is inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Pract h ," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within~ 20 days to this office to withhold such information

from public disclosure. Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790. The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

hear from you in this regard within the specified period, the report

will be placed in the Public Document Room.

204~/

194

7905290154

.

.

,

Duquesne Light Company

2

MR10ISD

No reply to this letter is required; however, if you should have any

questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

n

f

"

~

E

n

. Brunner, Chief

Redctor Operations and Nuclear

Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-334/79-07

cc w/ encl:

F. Bissert, Technical Assistant Nuclear

R. Washabaugh, QA Manager

J. Werling, Station Superintendent

G. Moore, General Superintendent, Power Stations Department

J. J. Carey, Nuclear Technical Assistant

2047

195

.