Forwards IE Insp Repts 50-324/79-26 & 50-325/79-27 on 790726-27.No Noncompliance Noted
ML19275A373
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 08/21/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML19275A374 List:
References
NUDOCS 7910040192
Download: ML19275A373 (2)


See also: IR 05000324/1979026

Text

7h

'

V

Q 59

pn etco

f

fo

UNITED STATES

695

g

! 'k . fr

NUCLEAR REGULATORY COMMISSION

$[ h v /) n

.

-

E

REGION 11

101 MARIETTA ST., N.W., sulTE 310o

g

,/

ATLANTA, GEoRG!A 30303

.....

AUG 211979

,

In Reply Refer To:

RII:LM

50-325/79-27

50-324/79-26

Carolina Power and Light Company

ATTN:

Mr. J. A. Jones

Executive Vice President and

Chief Operating Officer

411 Fayetteville Street

Raleigh, N. C.

27602

Gentlemen:

This refers to the inspection conducted by L. Modenos of this office on July 26-27,

1979, of activities authorized by NRC Operating License Nos. DPR-71 and DPR-62

for the Brunswick Steam Electric Plant Unit I and 2 facilities, and to the

discussion of our findings held with A. C. Tollison at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement cf the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this. regard within

tia q,ecified period, the report will be placed in the Public Document Room.

9

e

s

I"*

b

t095 n}o

7910040/ Q P

.

AUG 21 B79

.

Carolina Power and Light

-2-

Company

.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

[

C. E. Murphy, Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

Inspection Report Nos. 50-325/79-27

and 50-324/79-26

cc w/ enc 1:

A. C. Tollison, Jr.

Plant Manager

Box 458

Southport, N. C.

28461

-

9

4095

359

.