Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-424/79-11 & 50-425/79-11
ML19274F966
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/03/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19274F967 List:
References
NUDOCS 7908270232
Download: ML19274F966 (1)


See also: IR 05000424/1979011

Text

a

/g># 88Gugo

UNITED STATES

'

NUCLEAR REGULATORY COMMISSION

E'

'g

'

. , . , ,

REGION 11

' * - -

r

-

-

  • [p

f

101 MARIETT A ST., N.W., Sulf E 3100

o

ATLANTA, GEORGI A 30303

'

j'

.....

In Reply Refer To:

RtG 0 31979

RII:JRH

50-424/79-11

50-425/79-11

Georgia Power Company

Attn:

J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street

Atlanta, Georgia 30303

Gentlemen:

This refers to your letter of July 31, 1979, responding to the Notice of

Violation transmitted to you by our letter dated July 5, 1979, and to

the subsequent telephone discussion held between Mr. E. Groover of your

staff and Mr. J. Lenahan of this office on August 1, 1979.

It is our understanding that you will provide a supplemental response

to this office by August 10, 1979.

Sincerely,

.[

.J'

J'

=

r

Charles E. Murphy, Chief

Reactor Construction and Engineering

Support Branch

.

cc:

K. M. Gillespie

-

Construction Project Manager

Post Office Box 282

Waynesboro, Georgia 30830

E. D. Groover

QA Site Supervisor

Post Office Box 282

Waynesboro, Georgia 30830