Responds to NRC Re Violations Noted in IE Insp Rept 50-302/79-12.Corrective Actions:Fuel Handling Procedure FP-302 Will Be Revised Into Three Separate Procedures
ML19270G225
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 05/04/1979
From: Stewart W
FLORIDA POWER CORP.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19270G158 List:
References
CS-79-145, NUDOCS 7906050164
Download: ML19270G225 (2)


Text

e v-e'r ' l '5 'e t.SHRC RECC'-

e'

}c I

.i(;i ( 's AT. t.NT A. G" e( (

:+

C.!

',({( ( 8*s t c. e (dc' q p t.J e

c. S
  • 2 8 "

I Florida 4 nay 1,79 Po.om.r we 3-0-2-a-2 CS-79-145 coa Mr. J. P. O'Reilly, Director Docket No. 50-302 Office of Inspeciton & Enforcement License No. DPR-72 U.S Nuclear Regulatory Commission Ref.:

RII: PTB 101 Marietta St., Suite 3100 50-302/79-12 Atlanta, CA 30303

Dear Mr. O'Reilly:

We offer the following responses to the apparent Items of Noncompliance in the referenced inspection report.

NOTICE OF VIOLATION A. Technical Specification 6.8.1 requires in part that procedures shall be maintained and implemented for activities such as new fuel receipt and inspection.

Contrary to the above, for each of the new fuel shipments received during the period of Septembtr through November 1979, portions of Procedure FP-302, " Fresh Fuel Receipt, Inspe'ction, Inventory, Documenta-tion and Storage" were not completed.

~

B. 10 CFR 50, Appendix B, Item V requires in part that instructions for activities affecting quality, such as new fuel inspection, shall include acceptance criteria.

Contrary to the above, Procedure FP-302, " Fresh Fuel Receipt, Inspection, Inventory, documentation and Storage" does not include acceptance criteria for conditions monitored prior to inspection of the new fuel, or for inspection of the fuel cladding, supporting structures, and cther com-ponents of the fuel assembly.

A&B Response: Fuel Handling Procedure FP-302 vill be revised into three separate procedures.

One each for Container Receipt, Fuel Assembly Un-loading and Inspection, and Container Shipment, with each procedure con-taining sign-off blanks integrated to the procedure instead of ger.atic sign-off sheets.

790605010f Ha292 Oirg g

7t 4

J. P. O'Reilly Ref:

R11: PTB Page 2 Babcock and Wilcox, Inc. have been requested to provide additional criteria for on-site fuel assembly inspection. Fuel Handling Proceddre FP-302 presently addresses the requirements as stated by B&W Specification No.

2042/0470. Upon receipt of additional inspection criteria, a revision to FP-302 will be implemented. Procedural steps in which no acceptance criteria is stated, such as moisture indication and container pressure, the criteria will be established, if applicable, or these steps will be deleted from the procedure.

To effect full compliance, procedure reviews and revisions will be com-pleted by 1 September 1979.

Should there be further questions, please contact us.

Very truly yours, FLORIDA POWER CORPORATION

\\

~

W. P. Stewart Manager, Nuclear Operations JC/rc Nuclear Plant Manager