ML19269D222
| ML19269D222 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 01/03/1979 |
| From: | Galen Smith NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Andognini G BOSTON EDISON CO. |
| Shared Package | |
| ML19269D220 | List: |
| References | |
| NUDOCS 7903070496 | |
| Download: ML19269D222 (2) | |
See also: IR 05000293/1978027
Text
.I
4.
/ *.%
UNITED STATES
'
- 4
NUCLEAR REGULATORY COMMISSION
.,
REGION I
g
631 PARK AVENUE
KING OF PRUS$1 A. PENNSYl.V APet A 19406
Docket No. 50-293
Boston Edison Company M/C Nuclear
ATTN:
Mr. G. Carl Andognini, Manager
Nuclear Operations Department
800 Boylston Street
Boston, Massachusetts
02199
Gentlemen:
Subject:
Inspection 50-293/78-27
This refers to the inspection conducted by Dr. M. Shanbaky of this
office on November 28 - December 1,1978 at Pilgrim Nuclear Power Station,
Plymouth, Massachusetts, and at the Boston Edison Corporate Offices in
Boston, Massachusetts of activities authorized by NRC License No. DPR-35
and to the discussions of our findings held by Dr. Shanbaky with Messrs.
McGuire, Rosen, and other members of Mr. Rosen's and your staffs at the '
conclusicn of the inspection.
Areas examined during this inspection are described in the Office of
Inspection and Enforcement Ir.spection Report which is enclosed with this
letter. Within these areas, the inspection consisted of selective
examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Our inspector also verified the steps you have taken to correct the
items of noncompliance brought to your attention in a letter dated
November 7, 1977. We have no further questions regarding the steps you
took to correct items A, B, and C.
With regard to item D, we note that
corrective action to prevent recurrence was not fully implemented.
Based on the results of this inspection, it appears that one of your
activities was not conducted in full compliance with NRC requirements,
as set forth in the Notice of Violation, enclosed herewith as Appendix
A.
This item of noncompliance has been categorized into the levels as
described in our correspondence to you dated December 31, 1974.
This
790307099b
Boston Edison Company M/C Nuclear 2
-
notice is sent to you pursuant to the provisions of Section 2.201 of the
NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office, within twenty (20)
days of your receipt of this notice, a written statement or explanation
in reply including:
(1) corrective steps which have been taken by you
and the results achieved; (2) corrective steps which will be taken to
avoid further items of noncompliance; and (3) the date when full compli-
ance will be achieved.
The item shown in the Notice of Violation enclosed with this letter, is
a recurrent or uncorrected item.
In your response please give this
matter your particular attention.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter and the
enclosures will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to
be proprietary, it is necessary that you make a written application
within 20 days to this office to withhold such information from public
disclosure. Any such application must be accompanied by an affidavit
executed by the owner of the information, which identifies the document
or part sought to be withheld, and which contains a statement of reasons
which addresses with specificity the items which will be considered by
the Commission as listed in subparagraph (b) (4) of Section 2.790.
The
information sought to be withheld shall be incorporated as far as possible
into a separate part of the affidavit.
If we do not hear from you in
this regard within the specified period, the report will be placed in
the Public Document Room.
Should you have any questions concerning this inspection, we will be
pleased to discuss them with you.
Sincerely,
-
.
GergiH. Smith, Chief
c
F el Facility and Materials Safety
, ranch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Office of Inspection and Enforcement Inspection
Report Number 50-293/78-27
cc w/encls:
P. J. McGuire, Pilgrim Station Manager
A. Z. Roisman, Natural Resources Defense Council (Without Report)