Forwards IE Insp Repts 50-424/79-01 & 50-425/79-01 on 790110-12 & Notice of Violation
ML19263D036
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/06/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19263D027 List:
References
NUDOCS 7903200463
Download: ML19263D036 (2)


See also: IR 05000424/1979001

Text

.

't

a nao

UNITED STATES

ug#o,

NUCLEAR REGULATORY COMMISSION

~M , }

,

o

REGloN il

a$

101 MARIETTA STREET, N.W.

k4

(%,,,,p#

ATLANTA, GEORGIA 30303

FEB

6 1979

,

In Reply Refer To:

RII:JRH

50-424/79-1

50-425/79-1

Georgia Power Company

ATTN:

Mr. J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street, N.W.

Atlanta, Georgia 30303

Gentlemen:

This refers to the inspection conducted by Mr. J. R. Harris of this office on

January 10-12, 1979 of activities authorized by NRC Construction Permit

Nos. CPPR-108 and CPPR-109 for the Alvin W. Vogtle, Units 1 and 2 facility,

and to the discussion of our findings held with Mr. D. M. Fiquett, Manager,

Field Operations at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews

with personnel, and observations by the inspector.

We have examined actions you have taken with regard to previously identified

enforcement matters. These are discussed in the enclosed inspection report.

One new unresolved item resulted frota this inspection and is discussed in the

enclosed report. This item will be examined during subsequent inspections.

During the inspection, it was found that certain activities under your

,

license appear to be in noncompliance with NRC requirements. This item and

references to pertinent requirements are listed in the Notice of Violation

enclosed herewith as Appendix A.

This notice is sent to you pursuant to the

provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10,

Code of Federal Regulations. Section 2.201 requires you to submit to this

office, within 20 days of your receipt of this notice, a written rtatement or

explanation in reply including:

(1) corrective steps which hve been taken

by you and the results achieved; (2) corrective steps which will be taken to

avoid further noncompliance; and (3) the date when full compliance will be

achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If this

7903200463

.

FEB

6 1979

.

.

Georgia Power Company

-2-

report contains any information that you (or your contractor) believe to be

p roprieta ry , it is necessary that you make a written application within 20

days to this office to withhold such information from public disclosure. Any

such application must include a full statement of the reasons on the basis of

which it is claimed that the information is proprietary, and should be prepared

so that proprietary information identified in the application is contained in

a separate part of the document. If we do not hear from you in this regard

within the specified period, the report will be placed in the Public Document

Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

Charles E.

u rphy ,

ief

Reactor Constr

ton and Engineering

Support Branch

Enclosure:

1. Appendix A, Notice of Violation

2. Inspection Report Nos.

50-424/79-1 and 50-425/79-1

cc w/ enc 1:

Mr. K. M. Gillespie

Construction Project Manager

Vogtle Nuclear Plant

P. O. Box 282

Waynesboro, Georgia 30830

Mr. E. D. Groover

.

QA Site Supervisor

Vogtle Nuclear Plant

P. O. Box 282

Waynesboro, Georgia 30830

'