ML19262B477
| ML19262B477 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 12/14/1979 |
| From: | Miller W NRC OFFICE OF ADMINISTRATION (ADM) |
| To: | Mcguire P BOSTON EDISON CO. |
| References | |
| NUDOCS 7912280064 | |
| Download: ML19262B477 (1) | |
Text
y[onna,)
u UNITED STATES NUCLEAR REGULATORY COMMISSION g.lg,p'py y
'. g WASHINGTON. D. C. 20555
.q j
\\ l+t 5 /
...+
DOCKET N0. 50-293 DEC 141979 Boston Edison Company M/C NUCLEAR ATTN: Mr. P. J. McGuire Station Manager - Nuclear Operations RFD #1 Rocky Hill Road Plymouth, Massachusetts 02360 Gentlemen:
With your letter dated August 28, 1979 (79-169), you transmitted your Simulator Retraining Program for the Pilgrim Nuclear Power Station to the Office of Nuclear Reactor Regulation for review and approval. By letter dated October 23, 1979, we informed your Company that this filing is subject to the requirements of 10 CFR 170.22, and requested a Class II fee of $1,200. This fee has not been received; therefore, it should be submitted to this office within fifteen days after your receipt of this letter.
Sincerely, Q Q. (, ') \\ 's((\\
i s
LO William 0. Miller, Chief License Fee Management Branch Office of Administration cc: Mr. G. Carl Andegnini Superintendent - Nuclear Operations Department Boston Edison Company M/C NUCLEAR 800 Boylston Street Boston, Massachusetts 02199 CERTIFIED fiAIL REiURN RECEIPT REOUESTED 1648 090 7 9122 8 Og.