Transcript of Supplemental Testimony on License Fees, Contention 10(a),to Be Given at Forthcoming Hearing.One Page
ML19261E947
Person / Time
Site: Crane Constellation icon.png
Issue date: 10/26/1973
From: Nash D
US ATOMIC ENERGY COMMISSION (AEC)
To:
Shared Package
ML19261E929 List:
References
NUDOCS 7910170999
Download: ML19261E947 (1)


Text

.

THREE MILE ISLiVID llUCLEAR STATI0;;--D0rKET ll0. 50-289 Supplementary Testimony on License Fees By Darrel A. Nash Contention 10 The extent to which the NEPA review concerning cost / benefit analysis and alternatives may not be complete in that the following point (s) have not been fully analyzed or included:

(a)

Costs of administration and regulation by governmental agencies (limited to the matter of license fees payable by applicants to the Atomic Energy Commission in connection with this facility)

The operating license fees payable by the Applicants to the Atomic Energy Co:missica in connection with Unit 1 of this facility total

$713,975 plus an annual operating license fee of $164,775.I Operating i

license fees of $355,825 and an annual cperating fee of $30,420 was in effect at the time of the preparation of the FES.E Uhile these are

. substantial fee increases the magnitude is small compared to overall capital and operating costs and dces not change the conclusions of the cost benefit analysis.

If Fees in effect as of Aucust 10, 1973 per Federal Register Vol. 38, No.132--Wednesday, Juli 11, 1973.

_2]

Fees in effect as of May 25, 1972, per Federal Re31 ster Vol. 37, No. 80--Tuesday, April 25, 1972.