Forwards IE Insp Repts 50-460/79-11 & 50-513/79-11 on 791001-31,notice of Violation & Notice of Deviation
ML19260D448
Person / Time
Site: Washington Public Power Supply System
Issue date: 12/04/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Strand N
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML19260D439 List:
References
NUDOCS 8002110062
Download: ML19260D448 (2)


See also: IR 05000460/1979011

Text

' ' ,

n

,

UiDkl Q

fE{)

ga arcoq

-

-

,

4

h;

UNITED STATES

[ 'y , '.,q 'j

NUCLEAR REGULATORY COMMISSION

'

'

7, J '

s

REGION V

0,,',

.

[

1990 N. CALIFORNI A BOULEVARD

[

SUITE 202, WALNUT CREEK PLAZA

6

V

3

  • ...e

WALNUT CRE E K, CALIFORNI A 94596

.

DEC 041373

Docket flos. 50-460

50-513

Washington Public Power Supply System

P. O. Box 968

Richland, Washington 99352

Attention: Mr. fl. O. Strand

flanaging Director

Gentlemen:

Subject: 'lRC Inspection at Washington fluclear Projects 1 and 4

This refers to the inspection conducted by fir. A. Toth of this office

during the period of October 1-31, 1979 of activities authorized by NRC

Construction Permit f!os. CPPR-134 and 174, and to the discussion of his

findings held with fir. T. Houchins and other members of your staff on

October 9, 22, 29 and flovember 5,1979.

Areas examined during this inspection are described in the enclosed in-

spection report. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with f;RC requirements, as set forth

in the flotice of Violations, enclosed herewith as Appendix A.

This item

of noncompliance has been categorized into a ievel as described in our

correspondence to all fiRC licensees dated December 31, 1974.

This notice is sent to you pursuant to the provisions of Section 2.201,

of the f RC's " Rules of Practice," Part 2, Title 10, Code of Federal Reg-

ula tions .

Section 2.201 requires you to submit to this office, within

thirty (30) days of your receipt of this notice, a written statement or

explanation in reply including (1) corrective steps which have been taken

by you and the results achieved; (2) corrective steps which will be taken

to avoid further violations; and (3) the date when full compliance will

be achieved.

1939

093

8002110 Ohb

.

Washington Public

,er Supply System

-2-

DEC 041979

Based on the results of this inspection, it appears that one of your ac-

-

tivities was not conducted in full compli nce with your comitments in the

PSAR, as set forth in the Notice of Deviation , enclosed herewith as Appendix B.

With

your reply to this letter, please include your cr nents and proposed actions

relative to this item.

In accordance with Section 2.790 of the f RC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the en-

closed inspection report will be placed in the flRC's Public Document Room.

If this report contains any information that you believe to be proprietary,

it is necessary that you submit a written application to this office, within

30 days of the date of this letter, requesting that such information be

withheld from public disclosure. The application must include a full state-

ment of the reasons why it is claimed that the information is proprietary.

The application should be prepared so that any proprietary information

identified is contained in an enclosure to the application, since the appli-

cation without the enclosure will also be olaced in the Public Document Room.

If we do not hear from you in this regard within the specified period, the

report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be glad

to discuss them with you.

Sincerely,

h

L

,

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

Enclosures :

A.

Notice of Violation

B.

IE Inspection Repor)

Nos. 50-460/79- $ 11

50-513/79-@;l

cc w/o enclosure B:

M. E. Witherspoon, Division Manager

Quality Assurance, WPPSS

J. P. Thomas, Project flanager, WPPSS