ML19259A175
| ML19259A175 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 10/16/2019 |
| From: | Justin Poole Plant Licensing Branch 1 |
| To: | Bryan Hanson Exelon Nuclear |
| Poole J, NRR/DORL/LPLI, 301-415-2048 | |
| References | |
| EPID L-2019-LLE-0009 | |
| Download: ML19259A175 (14) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 October 16, 2019
SUBJECT:
THREE MILE ISLAND NUCLEAR STATION, UNIT 1 - EXEMPTIONS FROM THE REQUIREMENTS OF 10 CFR 50.82(a)(8)(i)(A) AND 10 CFR 50.75(h)(1)(iv)
Dear Mr. Hanson:
The U.S. Nuclear Regulatory Commission (NRC) has approved the enclosed exemptions from specific requirements of Title 10 of the Code of Federal Regulations ( 10 CFR)
Section 50.82(a)(8)(i)(A) and Section 50.75(h)(1 )(iv), for Exelon Generation Company, LLC.
This action is in response to your application dated April 12, 2019, which requested the exemptions to allow the of use funds from the decommissioning trust fund for spent fuel management activities, without prior NRC notice, for Three Mile Island Nuclear Station, Unit 1.
A copy of the exemptions is enclosed. The exemptions have been forwarded to the Office of the Federal Register for publication. If you have any questions, please contact me at (301) 415-2048 or via e-mail at Justin.Poole@nrc.gov.
Docket No. 50-289
Enclosure:
Exemptions cc: Listserv Sincerely, Justin C. Poole, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
ENCLOSURE EXEMPTIONS EXELON GENERATION COMPANY, LLC THREE MILE ISLAND NUCLEAR STATION, UNIT 1 DOCKET NO. 50-289
NUCLEAR REGULATORY COMMISSION Docket No. 50-289 Exelon Generation Company, LLC Three Mile Island Nuclear Station, Unit 1 Exemptions I. Background.
Exelon Generation Company, LLC (Exelon, the licensee) is the holder of Renewed Facility Operating License No. DPR-50 for the Three Mile Island Nuclear Station, Unit 1 {TMl-1 ).
The facility is located in Dauphin County, Pennsylvania.
By letter dated June 20, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17171A151), Exelon submitted a certification in accordance with Section 50.82(a)(1 )(i) of Title 10 of the Code of Federal Regulations (10 CFR), stating its determination to permanently cease operations at TMl-1 no later than September 30, 2019. By letter dated September 26, 2019 (ADAMS Accession No. ML19269E480), Exelon submitted to the NRC a certification in accordance with 10 CFR 50.82(a)(1 )(ii), stating that as of September 26, 2019, all fuel had been permanently removed from the TMl-1 reactor vessel. By separate letters dated April 5, 2019 (ADAMS Accession Nos. ML19095A009, ML19095A010, and ML19095A041 ), Exelon submitted the TMl-1 spent fuel management plan (SFMP),
site-specific decommissioning cost estimate (DCE), and post-shutdown decommissioning activities report (PSDAR), respectively.
II. Request/Action.
By letter dated April 12, 2019 (ADAMS Accession No. ML19102A085), Exelon submitted a request for exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1 )(iv). The requested exemption from 10 CFR 50.82(a)(8)(i)(A) would permit Exelon to use funds from the TMl-1 Decommissioning Trust Fund (DTF} for spent fuel management activities in accordance
with the TMl-1 site-specific DCE. The exemption from 10 CFR 50.75(h)(1)(iv) would also permit Exelon to make these withdrawals without prior notification of the NRC, similar to withdrawals for decommissioning activities made in accordance with 10 CFR 50.82(a)(8).
The 10 CFR 50.82(a)(8)(i)(A) requirement restricts the use of DTF withdrawals to expenses for legitimate decommissioning activities consistent with the definition of decommissioning that appears in 10 CFR 50.2. The definition of "decommission" in 10 CFR 50.2 reads as follows:
to remove a facility or site safely from service and reduce residual radioactivity to a level that permits-( 1) Release of the property for unrestricted use and termination of the license; or (2) Release of the property under restricted conditions and termination of the license.
This definition does not include activities associated with spent fuel management activities.
Therefore, an exemption from 10 CFR 50.82(a)(8)(i)(A) is needed to allow Exelon to use funds from the DTF for spent fuel management activities. The requirements of 1 O CFR 50. 75(h)(1 )(iv) also restrict the use of DTF disbursements (other than for ordinary and incidental expenses) to decommissioning expenses until final radiological decommissioning is completed. Therefore, partial exemptions from 10 CFR 50.82(a)(8)(i)(A) and 1 O CFR 50. 75(h)(1 )(iv) are needed to allow Exelon to use funds from the TMl-1 DTF for spent fuel management activities in accordance with the TMl-1 site-specific DCE.
The requirements of 10 CFR 50. 75(h)(1 )(iv) further provide that, except for withdrawals being made under 10 CFR 50.82(a)(8) orfor payments of ordinary administrative costs and other incidental expenses of the fund in connection with the operation of the fund, no disbursement may be made from the DTF without written notice to the NRC at least 30 working days in advance. Therefore, an exemption from 10 CFR 50.75(h)(1)(iv) is also needed to allow 2
Exelon to use funds from the TMl-1 DTF for spent fuel management activities at TMl-1 without prior NRC notification.
Ill. Discussion.
Pursuant to 10 CFR 50.12, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR Part 50:
(1) when the exemptions are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense and security; and (2) when any of the special circumstances listed in 10 CFR 50.12(a)(2) are present. These special circumstances include, among other things:
(a) Application of the regulation in the particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule; and (b) Compliance would result in undue hardship or other costs that are significantly in excess of those contemplated when the regulation was adopted, or that are significantly in excess of those incurred by others similarly situated.
A.
Authorized by Law The requested exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75{h){1)(iv) would allow Exelon to use a portion of the funds from the TMl-1 DTF for spent fuel management activities at TMl-1 without prior notice to the NRC, in the same manner that withdrawals are made under 10 CFR 50.82(a)(8) for decommissioning activities. As stated above, 10 CFR 50.12 allows the NRC to grant exemptions from the requirements of 10 CFR part 50 when the exemptions are authorized by law. The NRC staff has determined, as explained below, that there is reasonable assurance of adequate funding for radiological decommissioning because the licensee's use of the DTF for activities associated with spent fuel management will not negatively impact the availability of funding for radiological decommissioning. Accordingly, 3
the exemptions are authorized by law because granting the licensee's proposed exemptions will not result in a violation of the Atomic Energy Act of 1954, as amended, or the Commission's regulations.
B.
No Undue Risk to Public Health and Safety The underlying purpose of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(iv) is to provide reasonable assurance that adequate funds will be available for the radiological decommissioning of power reactors. As explained in further detail in Section D below, based on the NRC staff's review of Exelon's site-specific DCE and the staff's independent cash flow analysis provided in the enclosed Table 1, "NRC Cash Flow Analysis of TMl-1 Decommissioning Trust Funds and Associated Costs, including Spent Fuel Management," the NRC staff finds that the use of the TMl-1 DTF for spent fuel management activities at TMl-1 will not adversely impact Exelon's ability to terminate the TMl-1 license (i.e., complete radiological decommissioning) as planned, consistent with the schedule and costs contained in the PSDAR.
Furthermore, an exemption from 10 CFR 50.75(h)(1)(iv) to allow the licensee to make withdrawals from the DTF for spent fuel management activities without prior written notification to the NRC will not affect the sufficiency of funds in the DTF to accomplish radiological decommissioning because such withdrawals are still constrained by the provisions of 10 CFR 50.82(a)(8)(i)(B) - (C) and are reviewable under the annual reporting requirements of 10 CFR 50.82{a)(8)(v) - (vii).
There are no new accident precursors created by using the DTF in the proposed manner. Thus, the probability of postulated accidents is not increased. Also, based on the above, the consequences of postulated accidents are not increased. No changes are being made in the types or amounts of effluents that may be released offsite. There is no significant increase in occupational or public radiation exposure. Therefore, the requested exemptions will not present an undue risk to the public health and safety.
4
C.
Consistent with the Common Defense and Security The requested exemptions would allow Exelon to use funds from the TMl-1 DTF for spent fuel management activities at TMl-1. Spent fuel management under 10 CFR 50.54(bb) is an integral part of the planned decommissioning and license termination process and will not adversely affect Exelon's ability to physically secure the site or protect special nuclear material.
This change to enable the use of a portion of the funds from the DTF for spent fuel management activities has no relation to security issues. Therefore, the common defense and security is not impacted by the requested exemptions.
D.
Special Circumstances Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii), are present whenever application of the regulation in the particular circumstances is not necessary to achieve the underlying purpose of the regulation.
The underlying purpose of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv), which restricts withdrawals from DTFs to expenses for radiological decommissioning activities, is to provide reasonable assurance that adequate funds will be available for radiological decommissioning of power reactors and license termination. Strict application of these requirements would prohibit the withdrawal of funds from the TMl-1 DTF for spent fuel management activities, until final radiological decommissioning at TMl-1 has been completed.
The April 1, 2019, annual report on the status of decommissioning funding for TMl-1 (ADAMS Accession No. ML19091A140), and the PSDAR both report a DTF balance of
$669.6 million as of December 31, 2018. The cash flow analysis in Table 2 of the April 12, 2019, application is based on a beginning DTF balance of $662.9 million as of December 31, 2018. The licensee stated that the beginning DTF balance was adjusted to account for 2017 and 2018 site radiological decommissioning planning and 2018 spent fuel management planning costs that would be reimbursed if the exemptions were granted. The Exelon analysis 5
in the TMl-1 site-specific DCE, PSDAR, and exemption requests project the total radiological decommissioning cost of TMl-1 to be approximately $1 billion in 2018 dollars and the spent fuel management costs to be $158.6 million in 2018 dollars. This amounts to total estimated costs of approximately $1.16 billion for decommissioning and spent fuel management, with license termination occurring in 2081.
The NRC staff performed an independent cash flow analysis of the DTF over the 60 year SAFSTOR period (assuming an annual real rate of return of two percent, as allowed by 10 CFR 50. 75( e )( 1 )(ii)) and determined the projected earnings of the DTF. The results of the staff's analysis are presented in the enclosed Table 1. In its analysis, the NRC staff used the lesser opening DTF balance of $662.9 million as a conservative estimate that reflects less money available to cover radiological decommissioning and spent fuel management costs.
As shown in the enclosed Table 1, the NRC staff confirmed that the current funds in the DTF and projected earnings are expected to be available and sufficient to complete all NRC required radiological decommissioning activities at TMl-1, and also to pay for spent fuel management activities. Therefore, the NRC staff finds that Exelon has provided reasonable assurance that adequate funds will be available for the radiological decommissioning of TMl-1, even with the disbursement of funds from the DTF for spent fuel management activities.
Consequently, the NRC staff concludes that application of the requirements of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50. 75(h)(1 )(iv), that funds from the DTF only be used for radiological decommissioning activities and not for spent fuel management activities, is not necessary to achieve the underlying purpose of the rule; thus, special circumstances are present supporting approval of the exemption requests.
In its submittal, Exelon also requested exemption from the requirement of 10 CFR 50.75(h)(1 )(iv) concerning prior written notification to the NRC of withdrawals from the DTF to fund activities other than radiological decommissioning. The underlying purpose of notifying the NRC prior to withdrawal of funds from the DTF is to provide opportunity for NRC 6
intervention, when deemed necessary, if the withdrawals are for expenses other than those authorized by 10 CFR 50.75{h)(1){iv) and 10 CFR 50.82(a)(8) that could result in there being insufficient funds in the DTF to accomplish radiological decommissioning.
By granting the exemptions to 10 CFR 50.75(h)(1)(iv) and 10 CFR 50.82(a)(8)(i)(A), the NRC staff considers that withdrawals consistent with the licensee's submittal dated April 12, 2019, are authorized. As stated previously, the NRC staff has determined that there are sufficient funds in the DTF to complete radiological decommissioning activities as well as to conduct spent fuel management activities consistent with the PSDAR, site-specific DCE, and the April 12, 2019, exemption requests. Pursuant to the requirements in 10 CFR 50.82(a)(8)(v) and (vii), licensees are required to monitor and annually report to the NRC the status of the DTF and the licensee's funding for managing spent fuel. These reports provide the NRC staff with awareness of, and the ability to take action on, any actual or potential funding deficiencies.
Additionally, 10 CFR 50.82(a)(8)(vi) requires that the annual financial assurance status report must include additional financial assurance to cover the estimated cost of completion if the sum of the balance of any remaining decommissioning funds, plus earnings on such funds calculated at not greater than a two-percent real rate of return, together with the amount provided by other financial assurance methods being relied upon, does not cover the estimated cost to complete the decommissioning. The requested exemption would not allow the withdrawal of funds from the DTF for any other purpose that is not currently authorized in the regulations without prior notification to the NRC. Therefore, the granting of this exemption to 10 CFR 50.75(h)(1)(iv) to allow the licensee to make withdrawals from the DTF to cover authorized expenses for spent fuel management activities without prior written notification to the NRC will still meet the underlying purpose of the regulation.
Special circumstances, in accordance with 10 CFR 50.12(a)(2)(iii), are present whenever compliance would result in undue hardship or other costs that are significantly in excess of those contemplated when the regulation was adopted, or that are significantly in 7
excess of those incurred by others similarly situated. The licensee stated that the DTF contains funds in excess of the estimated costs of radiological decommissioning and that these excess funds are needed for spent fuel management activities. Preventing access to those excess funds in the DTF because spent fuel management activities are not associated with radiological decommissioning would create an unnecessary financial burden without any corresponding safety benefit. The adequacy of the DTF to cover the cost of activities associated with radiological decommissioning and pay for costs associated with spent fuel management is supported by the staff's independent cash flow analysis in the enclosed Table 1. If the licensee cannot use its DTF for spent fuel management, it would need to obtain additional funding that would not be recoverable from the DTF, or the licensee would have to modify its decommissioning approach and methods. The NRC staff concludes that either outcome would impose an unnecessary and undue burden significantly in excess of that contemplated when 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) were adopted.
Since the underlying purposes of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) would be achieved by allowing Exelon to use a portion of the TMl-1 DTF for spent fuel management activities without prior NRC notification, and since compliance with the regulations would result
- in an undue hardship or other costs that are significantly in excess of those contemplated when the regulations were adopted, the special circumstances required by 10 CFR 50.12(a)(2)(ii) and 10 CFR 50.12(a)(2)(iii) exist and support the approval of the requested exemptions.
E.
Environmental Considerations In accordance with 10 CFR 51.31(a), the Commission has determined that the granting of the exemptions will not have a significant effect on the quality of the human environment (see Environmental Assessment and Finding of No Significant Impact published in the Federal Register on October 16, 2019 (84 FR 55342).
8
IV. Conclusions.
In consideration of the above, the NRC staff finds that the proposed exemptions confirm the adequacy of funding in the TMl-1 DTF to complete radiological decommissioning of the site and to terminate the license and also to cover estimated spent fuel management activities.
Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense and security. Also, special circumstances are present. Therefore, the Commission hereby grants Exelon exemptions from the requirements of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) to allow them to use of a portion of the funds from the TMl-1 DTF for spent fuel management activities, without prior NRC notification, consistent with the PSDAR and site-specific DCE dated April 5, 2019.
The exemptions are effective upon issuance.
Dated at Rockville, Maryland, this 16th day of October, 2019.
For the Nuclear Regulatory Commission.
- b. E:~ng:::r-Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
9
Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 Table 1 - NRC Cash Flow Analysis of TMl-1 Decommissioning Trust Funds and Associated Costs, including Spent Fuel Management (thousands of constant 2018 dollars)
Opening DTF License Spent Fuel Interest 2%
EOYTrust Balance Termination Management Costs Fund Value Costs
$662,953
$20,490
$27,477
$12,300
$627,286
$627,286
$66,516
$30,973
$10,596
$540,393
$540,393
$45,645
$25,395
$9,387
$478,740
$478,740
$38,025
$14,963
$8,515
$434,267
$434,267
$10,088
$123
$8,481
$432,537
$432,537
$9,099
$1,139
$8,446
$430,745
$430,745
$6,057
$4,152
$8,411
$428,947
$428,947
$6,057
$4,152
$8,375
$427,112
$427,112
$6,057
$4,152
$8,338
$425,241
$425,241
$6,073
$4,163
$8,300
$423,305
$423,305
$6,057
$4,152
$8,262
$421,358
$421,358
$6,057
$4,152
$8,223
$419,372
$419,372
$6,057
$4,152
$8,183
$417,347
$417,347
$6,073
$4,163
$8,142
$415,253
$415,253
$6,057
$4,152
$8,101
$413,145
$413,145
$6,052
$7,385
$7,994
$407,702
$407,702
$6,040
$13,784
$7,758
$395,635
$395,635
$5,702
$0
$7,799
$397,732
$397,732
$5,686
$0
$7,841
$399,887
$399,887
$5,686
$0
$7,884
$402,085
$402,085
$5,686
$0
$7,928
$404,327
$404,327
$5,702
$0
$7,973
$406,598
$406,598
$5,686
$0
$8,018
$408,930
$408,930
$5,686
$0
$8,065
$411,309
$411,309
$5,686
$0
$8,112
$413,735
$413,735
$5,702
$0
$8,161
$416,194
$416,194
$5,686
$0
$8,210
$418,718
$418,718
$5,686
$0
$8,261
$421,293
$421,293
$5,686
$0
$8,312
$423,919
$423,919
$5,702
$0
$8,364
$426,581
$426,581
$5,686
$0
$8,418
$429,313
$429,313
$5,686
$0
$8,473
$432,099
$432,099
$5,686
$0
$8,528
$434,942
$434,942
$5,702
$0
$8,585
$437,825
$437,825
$5,686
$0
$8,643
$440,781
$440,781
$5,686
$0
$8,702
$443,797
$443,797
$5,686
$0
$8,762
$446,873
$446,873
$5,702
$0
$8,823
$449,995 Enclosure
2057
$449,995
$5,686
$0
$8,886
$453,195 2058
$453,195
$5,686
$0
$8,950
$456,459 2059
$456,459
$5,686
$0
$9,015
$459,789 2060
$459,789
$5,702
$0
$9,082
$463,168 2061
$463,168
$5,686
$0
$9,150
$466,632 2062
$466,632
$5,686
$0
$9,219
$470,165 2063
$470,165
$5,886
$0
$9,286
$473,565 2064
$473,565
$5,702
$0
$9,357
$477,220 2065
$477,220
$5,686
$0
$9,431
$480,965 2066
$480,965
$5,686
$0
$9,506
$484,784 2067
$484,784
$5,686
$0
$9,582
$488,680 2068
$488,680
$5,702
$0
$9,660
$492,638 2069
$492,638
$5,686
$0
$9,739
$496,691 2070
$496,691
$5,886
$0
$9,816
$500,621 2071
$500,621
$5,686
$0
$9,899
$504,833 2072
$504,833
$5,702
$0
$9,983
$509,114 2073
$509,114
$24,709
$0
$9,688
$494,093 2074
$494,093
$61,226
$0
$8,657
$441,524 2075
$441,524
$150,301
$0
$5,824
$297,048 2076
$297,048
$113,681
$0
$3,667
$187,034 2077
$187,034
$75,862
$0
$2,223
$113,396 2078
$113,396
$75,687
$0
$754
$38,463 2079
$38,463
$32,813
$0
$113
$5,763 2080
$5,763
$133
$0
$113
$5,743 2081
$5,743
$95
$0
$113
$5,760 TOTAL
$1,001,949
$158,629 2
LTR ML19259A175; Exemption ML 192549A179; FRN ML19259A182 OFFICE NRR/DORL/LPL 1/PM NAME JPoole DATE 9/25/2019 OFFICE NMSS/DUWP/RDB/BC*
NAME BWatson DATE 10/02/2019 OFFICE NRR/DORL/D NAME CErlanger DATE 10/16/2019 NRR/DORL/LPL 1/LA CSmith 9/25/2019 OGC - NLO w/comments*
AGhosh 10/03/2019 NRR/DORL/LPL 1/PM JPoole 10/16/2019