Forwards IE Info Notice 79-24, Overpressurization of Containment of PWR Plant After Main Steam Line Break. No Action Required
ML19254E575
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 10/01/1979
From: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: William Jones
OMAHA PUBLIC POWER DISTRICT
References
NUDOCS 7911010493
Download: ML19254E575 (1)


Text

CENTRAL FILES PDR:HQ 1{R

..I UNITED STATES

/en arco %

NUCLEAR REGULATORY COMMISSION NSIC g#

RtcioN iv I

611 RY AN PL AZ A DRIVE, SUITE 1000

'I o

ig -'

j ARLINGTON, TEXAS 76012 5 g #

kN[,f, a t- [!

October 1, 1979 Docket No.

50-285 Omaha Public Power District ATTN:

W. C. Jones, Division Manager -

Production Operations 1623 Harney Street Omaha, Nebraska 68102 Gentlemen:

The enclosed IE Information Notice provides information with regard to en analysis that ider.tifies an event that could result in overpressu-rization of containment at a pressurized water reactor.

Sincerely,

/

{. r/_, l'/ w]

/

/m -

Il

/-

Karl V. Seyfrit g Director

Enclosures:

1.

Information Notice 79-24 2.

'ist of IE Information Notices Issued in the Last Six Months cc:

S. C. Stevens, Manager Fort Calhoun Station Post Office Box 98 Fort Calhoun, Nebraska 68102 1283 104 m

7911010

)

SSINS: 6870 Accession No:

7908220123 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D. C.

20555 IE Information Notice No. 79-24 Date: October 1, 1979 Pa6e I of 1

~

OVERPRESSURIZATION OF CONTAINMENT OF A PWR PLANT AFTER A MAIN STEAM LINE BREAK Virginia Electric and Power Co. submitted a report dated September 7,1979, that identified a deficiency in the original analysis of containment pressurization as a result of a steam line break for North Anna Power Station, Units 3 and 4.

Stone and Webster Engineering Corporation performed a reanalysis of containment pressure following a main steam line break and determined that, if the auxiliary feedvater system continued to supply feedwater at runout conditions to the steam generator that had experienced the steam line break, containment design pressure would be exceeded in approximately 10 minutes. The long-term blowdown of the water supplied under runout conditions by the auxiliary feedwater system had not been considered in the earlier analysis. The corrective action is now under review by the owner, architect engineer, and NSSS supplier.

This IE Information Notice is provided as an early notification of a possibly significant matter that is still under review by the NRC staff.

It is expected that recipients will review the information for possible applicability to their facilities. No specific action or response is requested at this time.

If NRC 4,

evaluations so indicate, further licensee actions may be requested or required.

z No written response to this Information Notice is required.

If you have any questions regarding this matter please contact the Director of the appropriate

'[

NRC Regional Office.

,[i.

c.. y enn a

1 ped"2 h

s.

1283 105 d,

I h

s.

IE Information Notice No. 79-24 October 1, 1979 LISTING OF IE INFORMATION NOTICES ISSUED IN 1979 Information Subject Date Issued To Notice No.

Issued 79-10 Nonconforming Pipe 4/16/79 All power reactor Support Struts facilities with a Construction Permit (CP) 79-11 Lower Reactor Vessel Head 5/7/79 All Holders of Reactor Insulation Support Problem Operating Licenses (OLs)

Construction Permits (cps) 79-12 Attempted Damage to New 5/11/79 All fuel facilities, Fuel Assemblies research reactors, and power reactors with an Operating Licensee (OL) or a Construction Permit (CP) 79-13 Indication of Low Water 5/29/79 All Holders of Operating Level in the Oyster Creek License (OL) or Reactor Construction Permit (CP) 79-14 NRC Position of Electrical 6/11/79 All Power Reactor Cable Support Systems facilities with a

/

Construction Permit (CP) and applicants

[N,,

~,

-15 Deficient Procedures 6/7/79 All Holders of Reactor

,4 Operating Licenses (OLs) and Construction Permits (cps)

$1, 79-16 Nuclear Incident at Three 6/22/79 All Research Reactors Mile Island and Test Reactors with Operating Licenses (OLs)

" ~

79-17 Source Holder Assembly 6/20/79 All Holders of Reactor Damage From Misfit Between Operating Licenses (OLs)

G.

Assembly and Reactor Upper and Construction Grid Plate Permits (cps)

Enclosure Page 1 of 2 1283 106

)

IE Information Notice No. 79-24 October 1, 1979 79-18 Skylab Reentry 7/5/79 All holders of Reactor Operating Licenses (OLs) 79-19 Pipe Cracks in Stagnant 7/17/79 All Holders of Reactor Borated Water Systems at Operating Licenses (OLs)

PWR Plants and Construction Permits (cps) 79-20 NRC Enforcement Policy 8/14/79 All Holders of Reactor NRC Licensed Individuals Operating Licenses (OLs) and Construction Permits (cps), Research Reactors, Test Reactors Licensees with Licensed Ogarators 79-21 Transportation and 9/7/79 All power and research Commerical Burial reactors with Operating of Radioactive Material License (OL) 79-22 Qualification of Control 9/14/79 All power reactor Systems facilities with an Operating Licenses (OL) and Construction Permits (CP) 79-23 Emergency Diesel Generator 9/26/79 All power reactor Lube Oil Coolers facilities with an Operating License (OL) or Construction Permit (CP)

Enclosure Page 2 of 2 1283 107

.