Text

.

Sn nro

[

o

UNITED STATES

!

NUCLEAR REGULATORY COMMISSION

n

g

a

REGION il

.

o,

101 MARIETTA ST., N.W., SUITE 3100

%*****

ATLANTA, GEORGIA 303o3

OCT 2 51979

In Reply Refer To:

RII:MDH

50-413/79-18

50-414/79-18

Duke Power Company

Attn:

W. O. Parker, Jr.

Vice President, Steam Production

Post Office Box 33189

Charlotte, North Carolina 28242

Gentlemen:

This refers to the inspection conducted by M. D. Hunt of this office on

October 2-3, 1979 of activities authorized by NRC Construction Permit Nos.

CPPR-116 and CPPR-117 for the Catawba Nuclear Station facility, and to the

discussion of our findings held with D. L. Freeze at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observationr, by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe ta be

proprietary, it is necessary that you make a written application eithin 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

1443 05/

7 93

.

.

Duke Power Company

-2-

OCT 2 51979

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

.

kf

n'y+

C. E. Murphy, Chief

Reactor Construction and

Engineering Support Branch

,

Enclosures:

Inspection Re, ort Nos. 50-413/79-18

and 50-414/ 9-18

cc w/ enclosures:

D. G. Beam, Project Manager

Post Office Box 223

Clover, South Carolina 29710

1443

068