Forwards IE Insp Rept 50-395/79-17 on 790522-25 & Notice of Violation
ML19249B243
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 06/26/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Mary Johnson
SOUTH CAROLINA ELECTRIC & GAS CO.
Shared Package
ML19249B239 List:
References
NUDOCS 7909040166
Download: ML19249B243 (2)


See also: IR 05000395/1979017

Text

.

  1. }* "t Guq'o,

UNITED STATES

_

NUCLEAR REGULATORY COMMISSION

EV! L # ' f' i

.

2 .D@ h ' E

REGION il

k

f

101 MARIE TT A sT., N W., SUIT E 3100

AT L ANT A, G EORGI A 30303

.....f

In Reply Refer To:

JLDi 9 e tg79

RII:WHM

50-395/79-17

South Carolina Electric and Gas Company

Attn:

M. C. Johnson, Vice President

Special Services and Purchasing

Post Office Box 764

Columbia, South Carolina 29218

Gentlemen:

This refers to the inspection conducted by W. H. Miller, Jr. of this

office on May 22-25, 1979 of activities au*

-rized by NRC Construction

Permit No. CPPR-84 for the V,

C. Summer Nm lear Station f acility, Unit 1,

and to the discussion of our findings he

with J. F. Algar at the

i

conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observ<+ ions by the inspector.

Two new unresolved items resulted from this inspection and are discussed

in the enclosed report.

These items will be examined during subsequent

inspections.

Within the scope of this inspection, no items of noncompliance were

disclosed.

During the inspectica it was found that certain activities under your

license appear to deviate from commitments to the Commission, and have

safety significance.

This item is identified in the Notice of Deviation

enclosed herewith as Appendix A.

Please provide us in writing within 20

days of your receipt of this letter your comments including a description

of corrective actions that have been or will be taken, corrective actions

which will be taken to avoid further deviations, and the date corrective

actions were or will be completed.

In accordance with Se ' ion 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this of fice to withhold such information

c.n c e np

sp} . . F . O x

790904 0 / ff'

j f

.

South Carolina Electric and

JUN

1979

Gas Company

-2-

from public disclosure.

Any such application must include a full state-

ment of the reasons on the basis of which it is claimed that the i n f o rma-

tion is proprietary, and should be prepared so that proprietary information

identified in the application is contained in a separate part of the

document.

If we do not hear from you in this regard within the specified

period, the report will be p. laced in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

v

f

\\

/C.E.1 urphy, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice of Deviation

2.

Inspection Report No. 50-395/79-17

cc w/ enclosures:

T. B. Conners, Jr.

Conners, Moore and Corber

1747 Pennsylvania Avenue, N.W.

Washington, D.C.

20006

A. A. Smith

Quality Assurance

Post Office Box 8

Jenkinsville, South Carolina

29065

O. S. Bradham, Manager

Nuclear Operations

Post Office Box 8

Jenkinsville, South Carolina 29065