Submits Generic Response to IE Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Sys. Seismic Analysis Input Info Conforms to Actual as-built Configuration of safety-related Sys
ML19211A424
Person / Time
Site: Wolf Creek, Callaway, Sterling  Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 11/01/1979
From: Petrick N
STANDARDIZED NUCLEAR UNIT POWER PLANT SYSTEM
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 7912180175
Download: ML19211A424 (71)


Text

1 .,  %

SNUPPS Standardized Nuclear Urut Power Plana System 5 Choke Cherry Rod Nicholas A. Petrick Rockville, Maryland 20850 Executive Director (301)869 8010 November 1,1979 SLNRC 79- 18 FILE: 0278.10 SUBJ: IE Bulletin 79-14: Seismic Analysis for As-Built Safety-Related Piping Systems Mr. Boyce Grier Director, Region I Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 Docket Nos: STN 50-482, STN 50-483, STN 50-485, STN 50-486

Dear Mr. Grier:

This letter is submitted as a generic response to the subject IE Bulletin for the SNUPPS Utilities, Kansas Gas and Electric Company, Union Electric Company and Rochester Gas and Electric Corporation.

Engineering, construction and quality assurance practices in effect on the SHUPPS Project will assure that the seismic analysis input informa-tion conforms to the actual "as-built" configuration of safety-related systems. These practices are described briefly in Enclosure 1, Generic SNUPPS Program for Implementation of IE Bulletin 79-14. The enclosed program description outlines the phases of piping design and erection and indicates the controls and procedures to be employed throughout the pro-ject to assure that the final seismic stress analyses accurately and completely reflect the as-constructed SNUPPS configurations. The SNUPPS plants are currently in Phases I, II and III of activity described in Enclosure 1. Details concerning the Phase IV final walkdown are being developed and will be implemented in a timeframe consistent with the start of hot functional testing. The combination of existing Phase I, II, III practices together with plans for the Phase IV final walkdown will assure compliance with the Bulletin's requirements.

Additional information requested by the subject Bulletin is provided as follows:

(a) Enclosure 2 is a list of safety-related piping systems.

(b) Enclosure 3 is a list of piping isometrics and/or drawings.

(c) Enclosure 4 is a list of pipe support drawing indices.

1599 156 7912180 IWrd

SLNRC 79-18 November 1,1979 Page 2 The above lists are current as of this date. These lists are continuously revised throughout the design and construction process and will represent the final plant systems configuration. The inspection data requested by the subject bulletin is being ana will continue to be generated as installa- ,

tion and erection progresses. These data will be retained at the SNUPPS jobsites and will be available for NRC examination and audit.

If you have any questions on this matter, please contact either the under-signed or Mr. S. J. Seiken of my Staff.

Very ruly yours, EN4\

holas A. Petr',ck SJS:dck Enclosures cc: Mr. Victor Stello, Jr., Director, Office of Inspection and Enforcement, USNRC, Washington, D.C.

Mr. James G. Keppler, Director, Region III, USNRC.

Mr. Karl V. Seyfrit, Director, Region IV, USNRC.

1599 157

g .. AD 5  %

ENCLOSURE 1 GENERIC SNUPPS PROGRAM FOR IMPLEMENTATION OF IE BULLETIN 79-14 1599 158 e

-i-TABLE OF CONTENTS PAGE

. SECTION 1. INTRODUCIION 1 SECTION 2. FOUR PHASES OF PIPING DESIGN AND CONSTRUCTION 2 SECTION 3. PHASE I PIPING DESIGN AND INSTALIATION 4 SECTION 4. PHASE II CONSTRUCTION QC INSPECTION 6 SECTION 5. PHASE III NON-CONFORMANCE CONIROL 7 SECTION 6. PHASE IV STRESS WALKDOWN 9 1599 159

SECTION 1. INTRODUCTION

1. IE Bulletin 79-14 IE Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems , was issued July 2,1979. Revision 1 to the bulletin was issued July 18, 1979. A supplement to the bulletin was issued August 15, 1979.

Supplement 2 to the bulletin was issued September 7, 1979.

This bulletin addresses the concern which was raised when inspection of certain operating plants disclosed that installed piping systems including the supports were not in conformance with design documents. The specific concern is that deviations between the design documents, used as input information to the seismic design of the piping systems, and the as-built conditions could potentially impact the validity of the seismic piping analysis.

In order to assure that the seismic piping analyses are still valid, the bulletin requires each plant in operation or under construction to inspect safety-related/ Seismic Category I systems, and compare the as-built installa-tion with the design documents which were used as inputs to the seismic analysis. Where significant deviations are discovered, the bulletin requires that they be resolved either by reanalysis or by modifications to the piping systems or their supports.

1599 160

SECTION 2. FOUR PHASES OF PIPING DESIGN AND CONSTRUCTION There are four specific phases in piping design and construction (refer to Figure 1) related to verification of seismic analyses. These include:

a 2.1 Phase I - Piping layout, stress analysis, pipe support design, fabrication and installation.

2.2 Phase II - Construction QC inspection performed in-process and prior to systems turnover and owner acceptance. Included in these inspections are verification of pipe run geometry; installation of supports and attachments; embedment installation; piping system weldments; valve and operator orientations; penetration installation and piping systems clearances. Inspection character-istics, scope of examination, acceptance criteria and measurement tolerances are provided n site construction procedures.

2.3 Phase III - Resolution of all non-conformances from the requirements of applicable design drawings and specifications including referenced codes and standards. Phase III is a continuing process performed in conjunction with the Phase II QC inspection activity. At the end of Phase III, all "as-built" conditions will have been accepted or reanalyzed by the designer and, where required, incorporated in the design documents as "as-builts".

2.4 Phase IV - Final piping and support walkdown inspection prior to hot functional testing to ensure that the piping systems will behave as designed, and will move free from interferences during operation. This walkdown inspection is intended to supplement the Phase II QC construction inspection program.

~

l599 161

DESIGN AND CONSTRUCTION PHASES OF A TYPICAL PIPING SYSTEM 4 IE BULLETIN 79-14 SCOPE >

PHASE I PIPING DESIGN i INSTAL!ATION PHASE II CONSTRUCTION QC INSPECTION 4 PHASES PHASE III DESIGN /CONSTRUC-TION RESOLUTIONS NCR SYSTEM l PHASE IV I FINAL

/ WALKDOLT

/

INSPECTION

/

TIME 1FN

/N /N /N PIPING PIPING PIPING SYSTEM SYSTEM SYSTEM MILESTONE IAYOLT CONSTRUC- HOT FUNC-TION TIONAL COMPLETED OR

- PIAhi FUEL LOAD 1599 162 FIGURE 1 (REFER TO SECTION 2)

4-SECTION 3. PHASE I - PIPING DESIGN AND INSTALIATION Phase I extends from piping layout to installation. Briefly, the work includes the following tasks:

3.1 Piping layout and issuance of piping isometric drawing (by Layout Group).

3.2 Piping stress analysis and issuance of pipe support Design Guides (by Stress Group).

3.3 Pipe support design (by Pipe Support Group).

3.4 Issuance of drawings t'or piping and support fabrication (by Plant Design Supervisor).

3.5 Piping and support fabrication (by Fabrication Shop and Constructor) .

3.6 Piping and support installation (by Constructor).

The seguence of design and coastruction is diagramed in Figure 2. Each step is performed in accordance with project procedures, i599 163

?

o

P11ASE I - FROM PIPING DESIGN TO INSTALIATION F

PIPING IAYOITT RESPONSIBLE OW GOW ISSUE ISO CROUP / PERSON ACTIVITIES PIPING ANAL.

STRESS CROUP ISSUE SUPPORT DESIGN IDAD LEGEND i f SUPPORT DESIGN e PIPE SUPPORT GROUP Ln e

l I ISSUE FOR FABRICATION FABRICATION S110P/

p pgg FABRICATION - 0F PIPE AND CONSTRUCTION SUPPORT I I INSTALIATION CONSTRUCTION 4

FIGURE 2 - (REFER TO SECTION 3)

SECTION 4. PHASE II - CONSTRUCTION QC INSPECTION .

Phase II consists of a program of on-site QC construction inspection of sufficient scope to verify that all safety-related piping systems have been erected and installed in accordance with approved and current design drawings

  • e and specifications. These inspection activities include the following:

4.1 Preparation of construction inspection procedures indicating scope of inspection; characteristics to be examined; acceptance criteria and measurement tolerances.

4.2 QC inspection by personnel qualified and certified in accordance with ANSI N45.2.6.

4.3 Preparation, review and retention of QC inspection and "as-built" data.

599 I65 e

e

SEcrION 5. PHASE III - NON-CONFORMANCE CONTROL Phase III consists of an ongoing program, performed in conjunction with Phase II inspection, for identification and control of piping and pipe support non-conform-ances.to approved design document requirements. Non-conformances which must either ,

be reworked to comply with design requirements or which are to be replaced or rejected may be dispositioned by the site constructor (s) in accordance with site approved procedures. Non-conformances recommended for repair or use-as-is dis-position by the constructor are processed to the designer for review and approval.

Piping and pipe support non-conformances are examined by the Stress and/or Pipe Support disciplines for potential impact on previously completed seismic stress analyses. Where required, design analysis calculations are performed to support the approved disposition.

Before-the-fact design changes proposed by the constructor (s) either as Field Change Requests (FCRs) or Construction Variance Requests (CVRs) are processed and controlled per Phase I - Piping Design in accordance with design procedures.

At the end of the construction activity, piping and support non-conformances dispositioned on an "as-is" basis will be incorporated into "as-built" drawings.

Approved FCRs and CVRs are also reflected in applicable design documents.

A flow chart depicting the processing of non-conforming piping and support systems is provided in Figure 3. The details of each step are described in standardized non-conformance control procedures governing constructor ind designer processing of Non-Conformance Reports (NCRs) .

1599 166

PilASE III - CVR/FCR/NCR RESottfrION -

RESPONSIBLE CROUP .

CONSTRUCTOR CONSTRUCTION ., ISSUE FCR/CVR ACTIVITIES INSPECTION ISSUE NCR PROCESS TO RESPONSIBLE LEGEND DESIGN AGENCY V

CVR FCR/NCR / PIPING STRESS CROUP EVAL 1 NO  ;/ REAHALYSIS (JUSTIFIED)

YES co I

CVR/FCR/NCR SUPPORT SUPPORT PIPE SUPPORT GROUP - EVA L. 2 go NODIFICATION REDESIGN (ACCEITED)

YES W 1 r I P

l m

DOCUMENTREV\.

(REQUIRED AS- \m FABRICATION / CONSTRUCTION

{

y BUILT INCI.UDED) /

/

CVR/FCR/NCR EVAL. : CVR/FCR/NCR EVALUATION OF (1) PIPING CEOMETRY, (2) PIPE SUPPORT TYPE, LOCATION AND DIRECTION, FIGURE 3 - (REFER TO SECTION 5) CVR/FCR/NCR EVAL. : CVR/FCR/NCR EVALUATION OF SUPPORT DETAILS.

SECTION 6. PHASE IV - STRESS WAIXDOWN Phase IV is the final piping and support inspection review performed before the hot functional test and is intended to ensure that the piping systems will behave as designed. At the time of the inspection review, the piping systems are ready to be operated.

This inspection is commonly referred to as the " Stress Walkdown" or " Hanger Surveillance". The emphasis is that it is not a repeat of the QC function described in Phase II, but rather is intended to insure:

A. Piping and its supports have not been effected by subsequent construction and testing activity.

B. Piping is free of interferences during all anticipated modes of operation.

C. All the pipe supports with working ranges have been properly adjusted.

Details concerning the stress walkdown inspection are currently being developed and vill be implemented on a atandardized basis" at each of the SNUPPS jobsites.

A procedure describing the SNUPPS stress walkdown will be prepared by the piping systems designer and will be available for review within the next 6-9 months.

1599 168

?

~

....,.-_:..= . - - ~ r " --- ~ ~~' - _ . . . . . . .

- Enclosure 2

/

LIST OF SAFETI REIATED SYSTEMS Page 1 of 2

1. Reactor Coolant System .
2. Chemical and Volume Control System ,
3. High Pressure Coolant Injection System
4. Residual Heat Removal System
5. Accumulator Safety Injection System
6. Containment spray System
7. Component Cooling Water System
8. Essential Service t'ater System
9. 1.uxiliary Feedwater System
10. Main Feedwater System
11. Main Steam System
12. Standby Diesel Generator System
13. Emergency Fuel Oil System
14. Fuel Pool cooling and Cleanup System
15. Borated Refueling Water Storage System
16. Containment Air cooling System 1599 # 69
17. Containment Hydrogen Control System
18. Containment Leak Rate, Test *
19. Aux. Turbine System
20. Steam Cen. Blowdown System
21. Reactor Make-up System *
22. Containment Purge System *
23. 71oor & Iquipment Drains System (Portions only)
24. Fire Protection System *

., , . . . _ _ __ . .._._n._

~

~

, t Pagc 2 of 2

.e

25. Compressed Air System * .
26. i,iguid Radwaste System *
27. Nuclear Sampling System *
  • Containment Penetration Areas Only.

1599 170 m

G e e

Enclosure 3 ..

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

t PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03EJ01 Residual Heat Removal System 8 7-6-79 M-03EJ02 Residual Heat Removal System 10 8-15-79 M-03EJ03 Residual Heat Removal System 6 8-15-79 M-03EJ04 Residual Heat Removal System 5 3-26-79 M-03EJ05 Residual Heat Removal System 6 2-1-79 H-03EJ06 Residual Heat Removal System 3 7-11-79 M-03EJ07 Residual Heat Removal System 1 12-21-78 1599 171

=

O

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS FROJECT:

SYSTEM.:

a PIPING ISOMETRICS AND/OR DRA'TNGS TITLE REVISION DATE IDENTIFICATION NO.

Containment Spray System 8 1-26-79 M-03EN01 Containment Spray System 9 7-9-79 M-03EN02 Containment Spray System 3 3-6-79 M-03ENO3 Containment Spray System 3 8-3-79 M-03EN05 H-03EN06 Containment Spray System 4. 6-21-79 1599 172 G

G 27

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

e PIPING ISOMETRICS AND/OR DPJWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03EG01 Component Cooling Water System 9 9-6-79 M-03EG02 Component Cooling Water System 1 6-20-78 M-03EG03 Component Cooling Water System 7 9-6-79 M-03EG04 Component Cooling Water System 6 10-2-79 M-03EG05 Component Cooling Water System 5 11-20-78 Component Cooling Water System 7 2-27-79 M-03EG06 M-03EG07 Component Cooling Water System 6 8-1-79 M-03EG08 Component Cooling Water System 7 5-16-79 M-03EG09 Component Cooling Water System 3 9-28-78 M-03EG10 Component Cooling Water System 4 2-5-79 M-03EG11 Component Cooling Water System 5 2-5-79 Component Cooling Water System 5 2-5-79 H-03EG12 M-03EG13 Component Cooling Water System 6 2-5-79 Component cooling Water System 6 2-5-79 M-03EG14 Component Cooling Water System 7 6-4-79 M-03EG15 Component Cooling Water System 4 2-5-79 M-03EG16 Component Cooling Water System 4 2-5-79 M-03tG17 Component Cooling Water System 1 6-21-79 M-03EG18 M-03EG21 Component Cooling Water System 3 L2-15-78 H-03EG22 Component Cooling Water System 2 5-16-79 M-03EG23 Component Cooling Water System 3 12-28-78 1599 173

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST PORM 2 SNUPPS PROJECT:

. ~

SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO. _

Component Cooling Water System 4 7-7-78 M-03EG24 Component Cooling Water System 3 1-26-79 M-03EG25 Component Cooling Water System 3 10-31-78 M-03EG26

~

1599 174

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST. FORM 2 SNUPPS PROJECT:

SYSTEM:-

PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03EF01 Essential Service Water 5 2-12-79 M-03EF02 Essential Service Water 8 7-11-79 M-03EF03 Essential Service Water 8 2-6-79 M-03EF04 Essential Service Water 6 2-6-79 M-03EF05 Essential Service Water 10 8-27-79 M-03EF06 Essential Service Water 7 2-6-79 M-03EF07 Essential Service Water 4 6-14-79 M-03E708 Essential Service Water 1 4-3-79 M-03EF14 Essential Service Water 1 7-11-79 M-03EF15 Essential Service Water 1 7-11-79 Essential Service Water 4 4-18-79 M-03E709 Essential Service Water 4 8-14-79 M-03EF10 Essential Service Water 3 6-2-78 M-03EFil Essential Service Water 5 9-6-79 M-03EF13

~

3 a 27 1599 175

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM-PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

H-03ALO1 Auxiliary Feedwater 6 4-11-79 M-03ALO2 Auxiliary Feedwater 4 2-12-79 M-03ALO3 Auxiliary Feedwater 3 6-27-78 M-03ALO4 Auxiliary Feedwater 5 6-29-79 Auxiliary Feedwater 5 2-16-79 M-03ALOS I

6 of 27 .

1599 176

..___,e._____ __, , , . _ , _ , _ , _ . , , ,

Rev. 1 IE BULLETIN 79 DESIGii DCCITriENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

a PIPING IS0 METRICS AND/OR DRAk'INGS TITLE REVISION DATE IDENTIFICATION NO.

M-03AE04 Feedwater 6 7-9-79 M-03AE05 Feedwater 7 7~9-79 e

epp 9

m 1599 177

- - . . .,.- , ,., -,-.or ..... ._ ... .. ._._._.... -- ._.. -

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

a PIPING ISOMETRICS AND/OR DRAk'INGS 5

TITLE REVISION DATE IDENTIFICATION NO.

M-03AB01 Main Stream 9 8-27-79 M-03AB02 Main Stream 6 12-1-78 q

O 1599 178

~ -

Rev. 1 IE BULLETIN 79 DESIGN DOCUMEh"I LIST PORM 2 ShTPPS PROJECT:

SYSTEM PIPING ISOMETRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03KJ01 Standby Diesel Engine 1 11-6-79 Standby Diesel Engine 1 10-2-79 M-03KJ02 1599 179 9 of 27

..-* Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 FROJECT: SNUPPS SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-03JE02 Emergency Fuel Oil 1 7-19-79 M-03JE03 Emergency Fuel 011 1 7-19-79 1599 180 9

e O

--... , .._..-,,-n-. . . , . , - _ - - -

... aw..---

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

PIPING IS0 METRICS AND/OR DRAVINGS IDENTIFICATION NO. TITLE REVISION DATE M-03SJ01 Nuclear Sampling System 1 8-29-79 P

. 1599 181

  • O

.m,.._._.___. __. .

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS FROJECT:

. ~

SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03ECO2 Fuel Pool Cooling & Cleanup 4 8-9-79 Fuel Pool Cooling & Cleanup 2 9-19-79 M-03EC?4 1599 182 Y

e O

' Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS PROJECT:

SYSTEM:

a PIPING IS0 METRICS AND/OR DRAk7NGS TITLE REVISION DATE IDENTIFICATION NO.

Borated Refueling Water Storage 7 5-8-79 M-03BN01 Borated Refueling Water Storage 7 5-8-79 M-03BN02 1599 183

=

O e


-- - . . - - , . . ~ . . . , . _ . . ,

Rev. 1 IE BULLETIN 79 DESIGN DOCUMEh7 LIST FORM 2 SNUPPS PROJECT:

~ ~

SYSTEM:

e PIPING ISOME.TRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03GN01 Containment Cooling 5 8-23-79 M-03GN02 Containment Cooling 5 9-7-79 1

1599 184 g

<e

\

- -. . -. ...-,,,,=,.: a. . ...nw.__...

Rev. 1 IE BULLETIN 79 DESIGN DOCUMP.NT IIST FORM 2 SNUPPS PROJECT:

SYSTEM:

t PIPING ISOMETRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03GS01 Containment Hydrogen Control 4 9-6-79 1599 185 e ,

e

  • Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

PIPING IS0 METRICS AND/OR DRAk'INGS TITLE REVISION DATE IDENTIFICATION NO.

M-03FC01 Auxiliary Turbines 6 11-6-78 M-03FC02 Auxiliary Turbines 2 9-12-78 1599 186 16 of 27

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM; PIPING ISOMETRICS AND/OR DRAk'INGS TITLE REVISION DATE IDENTIFICATION NO.

M-03BM01 Steam Generator Blowdown 5 7-19-79 M-03BM02 Steam Generator Blowdown 4 11-22-78 H-03BM03 Steam Generator Blowdown 3 3-5-79 M-03BM17 Steam Generator Blowdown 2 7-30-79 M-03BM18 Steam Generator Blowdown 1 4-18-79 M-03BM19 Steam Generator Blowdown 1 4-18-79 M-03BM20 Steam Generator Blowdown 1 4-18-79 1599 187 17 of 27

  • Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS PROJECT:

SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

Reactor Make-up Water 4 10-4-78 M-03BLO3 1599 188 9

Rev. 1

.~ - '

IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS FROJECT:

SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS REVISION DATE IDENTIFICATION NO. TITIE Floor & Equipment Drains 6 9-13-79 M-03LF02 Floor & Equipment Drains 8 7-11-79 M-03LF10 1599 189 i

19 of 27

  • Rev. 1 IE BULLETIN 79-?.4 - DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE H-03RC21 Fire Protection 4 9-24-79 1599 190 9

e

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTDi:

PIPING ISOMETRICS AND/OR DRAkT GS TITLE REVISION DATE IDENTIFICATION NO.

Containment Leak Rate Test 1 5-29-79 M-03GP01 1599 191

~. .. .

21 of 27

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03KA01 Compressed Air 6 6-14-79 M-03KA43 Ccupressed Air 2 8-1-79 1599 192 O

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS

" ~

SYSTEM:,

PIPING IS0 METRICS AND/OR DRAVINGS TITLE REVISION DATE IDENTIFICATION NO.

M-03HB01 Liquid Radwaste 6 1-19-79 M-03HB24 Liquid Radwaste 5 3-19-79 M-03HB28 Liquid Radwaste 2 7-30-79 M-03HB27 Liquid Radwaste 1 6-6-79 1599 193 o .

S e

1

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS PROJECT:

SYSTEM.:

PIPING ISOMETRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

Reactor Coolant 2 3-26-79 M-03BB08 Reactor Coolant 2 3-26-79 M-03BB09 Reactor Coolant 3 3-26-79 M-03BB11 Reactor Coolant 1 6-18-79 M-03BB12 ,

Reactor Coolant 0 12-5-78 M-03BB13 Reactor Coolant 4 1-22-78 M-03BB01 Reactor Coolant 2 7-23-79 M-03BB02 Reactor Coolant 2 3-19-79 M-03BB04 0 12-13-78 M-03BB05 Reactor Coolant Reactor Coolant 0 12-13-78 M-03BB06 4 6-18-79 M-03BB07 Reactor Coolant 1 9-26-79 ,

M-03BB14 Peactor Coolant 0 12-13-78 M-03BB15 Reactor Coolant

- 1599 194

  • e 9

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 SNUPPS PROJECT:

SYSTEM:

PIPING IS0 METRICS AND/OR DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

Chemical & Volume Control 8 6-25-79 M-03BG01 Chemical & Volume Control 9 5-15-79 M-03BG02 Chemical & Volume Control 8 7-3-79 M-03BG03 Chemical & Volume Control 5 6-25-79 M-03BG04 Chemical & Volume Control 9 7-18-79 M-03BG05 Chemical & Volume Control 4 3-14-79 M-03BG09 Chemical & Volume Control 6 6-25-79 M-03BG11 Chemical & volume control 4 10-11-78 M-03BG15 Chemical & Volume Control 6 9-19-79 M-03BG16 Chemical & Volume Control 6 8-21-79 M-03BG17 Chemical & Volume Control 4 7-11-79 M-03BG18 Chemical & Volume Control 4 10-4-78 M-03BG21 Chemical & volume control 4 3-19-79 M-03BG22 Chemical & Volume Control 5 6-29-79 M-03BG23 Chemical & Volume control 5 7-3-79 M-03BG24 Chemical & Volume Control 4 8-15-79 M-03BG33 3 6-24-79 M-03BC10 Chemical & volume Control 2 7-11-78 M-03BG34 Chemical & Volume Control 1599 195 25 of 27

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTEM:

PIPING IS0 METRICS AND/OR DRAk'INGS TITLE REVISION DATE IDENTIFICATION NO.

High Pressure Coolant Injection 6 10-19-78 M-03EM01 High Pressure Coolant Injection 4 12-28-78 M-03EM02 High Pressure Coolant Injectior. 4 3-5-79 M-03EM03 M-03EM04 High Pressure Coolant Injection 3 ,6-21-79 High Pressure Coolant Injection 3 3-19-79 M-03EM05 M-03EM08 High Pressure Coolant Injection 4 3-29-79 High Pressure Coolant Injection 2 3-5-79 M-03EM10 High Pressure Coolant Injection 2 7-12-79 M-03EM06 High Pressure Coolant Injection 2 8-7-79 M-03EM11 High Pressure Coolant Injection 2 7-9-79 M-03EM12 High Pressure Coolant Injection 1 6-21-79 M-03EM13 1599 196 e

26 of 27

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 2 PROJECT: SNUPPS SYSTDi:

PJPIbG ISOMETRICS AFD/OR DRAVINGS IDENTIFICATI(S NO. TITLE REVISION DATE Wolf Creek ESWS Pu=phouse Piping Plan 4 6-8-79 M-KC0111(Q)

ESUS Pu=phouse Piping Sections 4 6-8-79 M-KC0911(Q)

Callaway Unit 1 M-UC0111(Q) ESWS Pu=phouse Piping Plan 4 9-27 79 M-UCO211(1) IMS Cooling Tower Piping Plan &

Section 3 8-30-78 M-UC0911(Q) ESWS Pu=phouse Piping Section &

Details 3 6-21-79 Callaway Unit 2 M-WCO211(Q) URS Cooling Tower Piping Plan &

Section 2 11-17-78 Rochester ESWS Pu=phouse Piping Plan 0 9-30-77 M-RC0111(Q)

ESWS Pu=phouse Piping Plan & Sect. 0 9-30-77 M-RC0911(Q)

M-RC0912(Q) ESWS Pumphouse Piping Section 0 9-30-77 1599 197 27 of 27

j .. . . _

.. Enclosure 4

  • Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FGtM 5 PROJECT: SNUPPS SYSTEM: .

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06EJ01 Residual Heat Remval System 11 5-1-79 Residual Heat Removal System 10 6-20-79 M-06EJ02 M-06EJ03 Residual Heat Removal System 15 9-19-79 M-06EJ04 Residual Heat Removal System 3 5-16-79 M-06EJ06 Residual Heat Removal System 1 9-18-79 Residual Heat Removal System

  • M-06EJ07 i

NOTE:

  • Drawings will be issued at a later date. .

1599 198

Rev. 1 IE BULLETIN 79 DECICN DOCUMENT LIST PCRM S PROJECT: SNUPPS SYSTEM: .

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06BP01 Accu =ulator Safety Injection System - -

M-06EP02 Accu =ulator Safety Injection System - -

NOTE: Drawings vill be issued at a later date.

)

O

~ ~

1599 199 g 9

Rev. 1 IE BULI.ETIN 79 DESIGN DOCUMENT LIST FCRM S PROJECT: SNUPPS SYSTEM: .

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE Containment Spray System 11 7-24-79 M-06EN01 Contain:nent Spray System 15 6-20-79 M-06EN02 Containment Spray System 5 7-12-79 M-06ENO3 Containment Spray System 5 8-15-79 M-06EN05 Containment Spray System

  • M-06EN06 NOTE:
  • Drawing vill be issued at a later date.

O e

1599 200 .

~ . - -

  • Rev. 1 IE BULI.ETIN 79 DESIGN DOCUMENT LIST PCRM S PROJECT: SNUPPS SYSTEM: ,

PIPE SUPPORT DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

Co=ponent Cooling Water System 12 ~7-16-79 M-06EG01 Component Cooling Water System 9 7-25-79 M-06EG02 Component Cooling Water System 13 7-26-79 M-06EG03 Component cooling Water System 8 5-9-79 M-06EG04 Component cooling Water System 5 7-11-79 M-06EG05 Component Cooling Water System 13 8-27-79 M-06EG06 Component Cooling Water System 12 8-20-79 M-06EG07 Component Cooling Water System 1 5-7-79 M-06EG08 Component Cooling Water S,ystem 2 5-1-79 M-06EG09 Component Cooling Water System 1 4-18-79 M-06EG10 Component Cooling Water System 2 5-23-79 M-06EGli Component Cooling Water System 4 8-9-79 M-06EG12 Component Cooling Water System 4 8-7-79 M-06EG13 Component Cooling Water System 1 4-23-79 M-06EG14 ,

Component Cooling Water System 3 8-13-79 M-06EG15 Component Cooling Water System 1 4-24-79 M-06EG16 Component Cooling Water System 6 6-28-79 M-06EG17 _

~

Component Cooling Water System 0 5-25-79 M-06EG18 Component Cooling Water System 1 5-24-79 M-06EG23 . .

Component Cooling Water System 1 12-7-78 M-06EG24 1599 201

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST F G LM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-06EG25 Component Cooling Water System i 12-19-78 M-06EG26 Component Cooling Water System 4 4-20-79 Component Cooling Water System

  • M-06EG21 Component Cooling Water System
  • M-06EG22 NOTE:
  • Drawings will be issued at a later date.

1599 202

\

5 of 29

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FmM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGb -

IDENTIFICATION NO. TITLE REVISION DATE Essential Service Water 14 6-9-78 M-06EF01 Essential Service Water 26 8-17-79 M-06EF02 Essential Service Water 13 8-15-79 M-06EF03 M-06EF04 Essential Service Water 12 3-23-79 Essential Service Water 17 4-23-79 M-06EF05 Essential Service Water 22 8-15-79 M-06EF06 Essential Service Water 2 6-20-79 M-06EF07 Essential Service Water 2 8-13-79 M-06EF08 Essential Service Water 2 6-27-79 M-06EF14 Essential Service Water O 12-28-78 M-06EF15 Essential Service Water

  • M-06EF13 40TE:
  • Drawings will be issued at a later date.

1599 203 6 of 29

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FGtM S PROJECT: SNUPPS

~

SYSTEM:

PIPE SUPPORT DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

H-06ALO1 Auxiliary Feed Water 12 8-8-79 Auxiliary Feed Water 4 1-17-79 H-06ALO2 H-06ALO3 Auxiliary Feed Water 7 3-2-79 Auxiliary Feed Water 4 3-12-79 H-06ALO4 Auxiliary Feed Water 5 8-13-79 H-06ALOS O

O e

7 of 29 1599 204

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCRM S PROJECT: SNUPPS

~

SYSTEM: .

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE Feedwater 5 4-6-79 M-06AE04 M-06AE05 Feedwater 2 5-25-79 e ~

1599 205 .

~

8 of 29

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 5 PROJECT: SNUPPS

~

SYSTEM:

PIPE SUPPORT DPR INGS IDENTIFICATION NO. TITLE REVISION DATE M-06AB01 Main Stream 5 8-21-79 M-06AB02 Main Stream 3 4-24-79 1599 206 .

9 of 29 \

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCRM S PROJECT: SNUPPS

~

SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06KJ01 Standby Diesel Engine 2 8-13-79 Standby Diesel Engine

  • M-06KJ02 NOTE:
  • Drawing will be issued at a ; ater date.

~

~

1599 207 .

~

  • Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM S PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06JE02 Emergency Fuel Cil 0 6-4-79 H-06JE03 Eeergency Fuel Oil 2 8-9-79 1599 208 9

Rev. 1 IE BULLETIN ,79 DESIGN DOCUMENT LIST PCRM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAVINGS IDD?TIFICATION NO. TITLE REVISION DATE Nuclear Sampling System 0 8-27-79 M-06SJ01

~

1599 209 12 of 29

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FmM S PROJECT: SNUPPS

~

SYSTEM:

PIPE SUPPORT DRAk'INGS IDENTIFICATION NO. TITLE REVISION DATE H-06ECO2 Fuel Pool Cooling & Cleanup 0 8-17-78 M-06EC04 Fuel Pool Cooling & Cleanup 3 9-5-79 1599 210 13 of 29

- Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FGL$i 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06BN01 Borated Refueling Water Storage 12 5-23-79 M-06BN02 Borated Refueling Water Storage 11 7-30-79 1599 211 14 of 29

Rev. 1

~

". IE BULLETIN 79 DESIGN DOCMENT LIST FCRM S PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS TITLE REVISION DATE IDENTIFICATION NO.

M-06GN01 Containment Cooling 8 8-27-79 M-06GN02 Containment Cooling 10 9-18-79

~

1599 212 . .

15 of 29 1

' ' Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST PCRM 5 PROJECT: SNUPPS

. ~

SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06GS01 Containment Hydrogen Control 0 5-24-79 m

1599 213

. O

'

  • Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCRM 5 FROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE Ru'YISION DATE Auxiliary Turbines 6 1-8-79 M-06FC01 Auxiliary Turbines 0 6-7-79 M-06FCO2

~

. 1599 214 -

O

\

Rev. 1 IE BULLETIN 79 DESIGN DOCIMENT LIST FCRM 5 FROJECT: SNUPPS

~

SYSTEM:

f PIPE SUPPORT DRAk'INGS -

IDENTIFICATION NO. TITLE REVISION DATE M-06BM01 Steam Generator Blowdown 5 7-24-79 M-06BM02 Steam Generator Blowdown 4 11-14-78 Steam Generator Blowdown 1 3-12-79 M-06BM03 Steam Generator Blowdown

  • M-06BM20 NOTE:
  • Drawings will be issued at a later date.

1599 215 18 of 29

--= =.a . . -- .

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCELM 5 PROJECT: SNUPPS SYSTEM:

t PIPE SUPPORT DRAVINGS P

IDENTIFICATION NO. TITLE REVISION DATE M-06BLO3 Reactor Make-up water 2 4-27-79 e

~

1599 216 O

  • Rev. 1 IE BULIITTN 79 DESIGN DOCUMENT LIST FCRM S PROJECT: SNUPPS

. ~

SYSTEM: -

PIPE SUPPORT DRAk'INGS IDENTIFICATION NO. TITLE REVISION DATE Containment Purge System - -

NOTE: Drawings will be issued at a later date. Drawing number presently not assigned O

1599 217 -

9

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST F(RM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAk'INGS IDENTIFICATION NO. TITLE REVISION DATE M-06LF02 Floor & Equipment Drains 14 8-17-79 M-06LF10 Floor & Equipment Drains 5 8-27-79 1599 218 o

  • O

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST PORM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAk'INGS IDENTIFICATION NO. TITLE REVISION DATE Fire Protection 6 9-18-79 M-06KC21 1599 219 22 of 29

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCRM 5 PRO.7ECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-05GP01 Containment Leak Rate Test 0 3-27-79 1599 220 23 of 29

, , Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCRM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAk'INGS -

IDENTIFICATION NO. TITLE REVISION DATE M-06KA01 Compressed Air 7 12-28-78 M-06KA43 Compressed Air 0 8-14-79 1599 221

~ - .

24 of 29

  • Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FORM 5 PROJECT: ShW PS SYSTEM:

PIPE SUPPORT DRAVINGS

'mF IDENTIFICATION NO. TITLE REVISION DATE M-06HB01 Liquid Radwaste 6 8-27-79 M-06HB24 Liquid Radwa.. I 1-30-79 M-06HB28 Liquid Radwaste 1 9-18-79 Liquid Radwaste

  • M-06HB27 NOTE:
  • Drawing vill be issued at a later date.

1599 222 e

6

  • O e e a

. . . . . ._ -. . . . , . . . ~ . - . . - . . . .

~'

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST FCRM S PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06BB08 Reactor Coolant 1 8-13-79 M-06BB09 Reactor Coolant 0 9-5-79 M-06BB11 Reactor Coolant 3 8-14-79 M-06BB12 Reactor Coolant 0 8-27-79 M-06BB13 Reactor Coolant

M-06BB15 Reactor Coolant

~. '

N0'IE :

  • Drawings will issued at

. a later date. .

1599 223

  • Rev. 1 TE BULLETIN 79 DESIGN DOCUMENT I,IST FCRM 5 PRO.7ECT: SNUPPS

~ .

SYSTEM:

PIPE SUPPORT DRAVINGS IDENTIFICATION NO. TITLE REVISION DATE M-06BG01 Chemical & Volume Control 16 8-27-79 M-06BG02 Chemical & Volume Control 17 9-5-79 M-06BG03 Chemical & Volume Control 16 7-13-79 M-06BG04 Chemical & Volume Control 20 8-14-79 M-06BG05 Chemical & volume Control 18 6-14-79 M-06BG09 Chemical & Volume Control 0 7-24-79 M-06BG11 Chemical & volume Control 12 5-31-79 M-06BG15 Chemical & Volume Control 12 5-25-79 M-06GB16 Chemical & Volume Control 10 3-13-79 M-06BG17 Chemical & Volume Control 2 7-23-79 M-06BG18 Chemical & Volume Control 0 5-30-78 M-06BG21 Chemical & Volume Control 5 8-17-79 M-06BG22 Chemical & volume control 15 8-15-79 M-06BG23 Chemical & Volume Control 8 9-18-79 M-06BG24 Chemical & Volume Control 0 5-16-79 M-06BG33 Chemical & Volume Control 0 5-23-79 M-06'G34 B Chemical & Volume Control

  • NOTE: Drawing vill issued at a later date 1599 224

.,.______,_-.. _.2. ._ _

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST PCRM 5 PROJECT: SNUPPS SYSTEM:

PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE M-06EM01 High Pressure Coolant Injection 15 7-24-79 M-06EM02 High Pressure Coolant Injection 13 9-13-79 M-06EM03 High Pressure Coolant Injection 2 8-23-79 M-06EM04 High Pr.tssure Coolant Injection 4 7-23-79 M-06EM05 High Pressure Coolant Injection 1 7-23-79 M-06EM08 High Pressure Coolant Injection 1 3-9-78 M-062.2'10 High Pressure Coolant Injection 0 5-1-79 M-06EM06 High Pressure Coolant Injection

  • M-06EM12 High Pressure Coolaat Injection
  • NOTE:
  • Drawings will be issued at a later date.

e e

~

1599 225

Rev. 1 IE BULLETIN 79 DESIGN DOCUMENT LIST YGtM 5 PROJECT: SNUPPS SYSTEM: ~. -

t PIPE SUPPORT DRAWINGS IDENTIFICATION NO. TITLE REVISION DATE Wolf Creek M-K60111 ESWS Pumphouse

  • Callaway Unit 1 M-U60111 ESWS Pumphouse 1 5-9-79 M-U60211 URS Cooling Tower 4 5-16-79 Callaway Unit 2 ,

M-W60211 UHS Cooling Tower

  • Rochester M-R60111 ESWS Pumphouse
  • NOTE:
  • Drawings will be issued at a later date.

~

1599 226 ..

\

29 of 29