Forwards IE Insp Rept 50-346/79-25 on 790820-24,31,0904-07, 10-14,17-21 & 24-28 & Notice of Violation
ML19210E595
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/31/1979
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Crouse R
TOLEDO EDISON CO.
Shared Package
ML19210E596 List:
References
NUDOCS 7912050348
Download: ML19210E595 (2)


See also: IR 05000346/1979025

Text

/

'o

UNITED STATFt

+

~ * ,

E

3,7

j

NUCLEAR REGULATORY COMMISSION

.

e

REGION 111

0,, '[

gf

799 ROOSEVELT ROAD

i

'

% '.\\/

g

GLEN ELLYN. ILLINolS 6o137

  • ..+

ggt 31 M

a

i a. 3

Docket No. 50-346

s

Toledo Edison Company

ATTN:

Mr. Richard P. Crouse

Vice President - Energy

Supply

300 Madison Avenue

Toledo, OH 43652

Gentlemen:

This refers to the inspection conducted by Mr. L. A. Reyes of this office

on August 20-24, 31, September 4-7, 10-14, 17-21, and 24-28, 1979, of

activities at the Davis-Besse Nuclear Power Station, Unit 1, authorized by

NRC Operating License No. NPF-3 and to the discussion of our findings with

Mr. T. Murray at the conclusion of the inspections on September 7,14,

21, and 28, 1979.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed Appendix A.

The inspection showed that action had been taken to correct the identified

noncompliance and to prevent recurrence.

Consequently, no reply to this

noncompliance is required and we have no further questions regarding this

matter at this time.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room, except

as follows.

If this report contains information that you or your contractors

believe to be proprietary, you must apply in writing to this office, within

twenty days of your receipt of this letter, to withhold such information

from public disclosure. The application must include a full statement of

the reasons for which the information is considered proprietary, and should

be prepared so that proprietary information identified in the application

is contained in an enclosure to the application.

1494

188

'T 912050 3N

.

I b79

Toledo Edison Company

-2-

.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

s

O

.

2d

. F. Heishman, C;.ief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-346/79-25

cc w/encls:

Mr. T. D. Murray, Station

Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Harold W. Kohn, Poser

Siting Commission

"*j"Oio

'