| Site: | Calvert Cliffs |
| Issue date: | 08/14/1979 |
| From: | Brunner E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Lundvall A BALTIMORE GAS & ELECTRIC CO. |
| Shared Package | |
| ML19209B260 | List: |
| References | |
| NUDOCS 7910090388 | |
| Download: ML19209B259 (2) | |
See also: IR 05000317/1979010
Text
,
"tb
'
UNITED STATES
Sn nrog
o
NUCLEAR REGULATORY COMMisslON
g
o
R EGION l
$
$
$31 PARK AVENUE
f
KING OF PRUSSI A, PENNSYLVANIA 19406
\\...../
Docket Nos. 50-317
AUG 141979
50-318
Baltimore Gas and Electric Company
ATTN: Mr. A. E. Lundvall, Jr.
Vice President, Supply
P. O. Box 1475
Baltimore, Maryland
21203
Gentlemen:
Subject: Combined Inspection 50-317/79-10 and 50-318/79-08
This refers to the inspection conducted by Mr. D. Johnson of this office on June
21 and 22,1979 at Calvert Cliffs 1 and 2 of activities authorized by NRC License
Nos. DPR-53 and DPR-69 and to the discussions of our findings held by Mr. Johnson
with Messrs. R. Ash and S. Rittenhouse of your staff at the conclusion of the
inspection, and to a subsequent telephcne discussion between Mr. Johnson and Mr.
R. Ash on June 27, 1979.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter. Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
Within the scope of this inspection, no items of noncompliance were observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room.
If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure.
Any such application must be
accompanied by an affidavit executed by the owner of the information, which
identifies the document or part sought to be withheld, and which contains a
statement of reasons which addresses with specifi~ city the items which will be
considered by the Commission as listed in subparagraph (b) (4) of Section
2.790. The information sought to be withheld shall be incorporated as far as
possible into a separate part of the affidavit.
If we do not hear from you in
this regard within the specified period, the report will be placed in the Public
Document Room.
1114
128
7910090Nb
Q
.
.
Baltimore Gas and Electric Company
2
AUG 141979
No reply to this letter is required; however, if you should have any questions
cencerning this inspection, we will be pleased to discuss them with you.
Sincerely,
-
-
o _-
E1
. Brunner, Chief
Rea tor Operations and Nuclear
S pport Branch
Enclosure: Office of Inspection and Enforcement Combined Inspection
Report Numbers 50-317/79-10 and 50-318/79-08
cc w/ encl:
R. M. Douglass, Manager, Q';ality Assurance
L. B. Russell, Chief Engineer
W. Gibson, General Surervisce, Operations QA
R. C. L. Olson, Senior Engineer
K. H. Sebra, Principal Engineer
.
1114