ML19209A355

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-329/79-15 & 50-330/79-15 on 790601-0711.No Noncompliance Noted.Major Areas Inspected:Purge Paper in Unit 2 Reactor Bldg Spray Sys Piping & post-weld Heat Treatment of Unit 2 Reactor Coolant Sys
ML19209A355
Person / Time
Site: Midland
Issue date: 08/15/1979
From: Cook R, Knop R, Vandel T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19209A339 List:
References
50-329-79-15, 50-330-79-15, NUDOCS 7910030646
Download: ML19209A355 (9)


See also: IR 05000329/1979015

Text

.

.

I

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-329/79-15; 50-330/79-15

Docket No. 50-329; 50-330

License No. CPPR-81; CPPR-82

Licensee:

Consumers Power Company

1945 West Parnall Road

Jackson, MI 49201

Facility Name: Midland Nuclear Power Plant, Units 1 and 2

Inspection At: Midland Site, Midland, Michigan

Inspection Conducted- Ju 6 1-July 11, 1979

h<

-

[/O 7[

Inspectors:

R. J. Cook

'*

f~h ud (

T. E. Vandel (June 5-7, 1979)

[- 6

,

,

,

,

'

/

-

/.a

e

.

-

- '

Approved By:

'R. C. Knop,' Chief

.> O '

'

'

Projects Section 1

Inspection Summary

Inspection on June 1-July 11, 1979 (Report No. 50-329/79-15; 50-330/79-15)

Areas Inspected: Review of previously identified noncompliance and

unresolved matters; follow up on 50.55(e) reports and other old items for

close out; review scheduling and status of construction for future program

inspection coverage; examination of site conditions, settlement of diesel

generator foundations and structures; modifications to seismic braces for

Class IE battery racks; inadequate cooling water flow to containment

recirculation coolers; investigation into purge paper found in Unit 2

reactor building spray system piping; calculated inadequate cooling water

flow to containment recirculation air coolers; post weld heat treatment

of Ua.it 2 reactor coolant system; corrosion of buried stainless steel

piping; presence of fluid found in 350 MCM-3/C-B-11 power cable; qualifica-

tion of seal and oil coolers used in the auxiliary feed water pumps;

decay heat removal pump baseline inservice inspections; qualification

testing of cable ties; assembly of unit reactor coolant ; ump 2P-51B;

installation of Unit 2 prestress tendons; licensee QA overview inspections

for instrument and control installations; coverage of a fatal industrial

accident initiated from inhalation of argon purge gas; complete loss of

offsite power, and possible existance of an unauthorized weld in the

Unit 2 letdown cooling system. This inspection effort involved a total

of 167 inspector hours by two NRC inspectors.

Results: No items of noncompliance or deviations were identified.

]Qgj

jg{

7910080 87(,

9

.

.

s

DETAILS

Persons Contacted

Consumers Power Company Personnel

D. Miller, Site Manager

  • T. Cooke, Project Superintendent
  • J

Corley, QA Section Head IE & TV

  • D. Keating, QA Group Supervisor
  • B. Peck, Construction Supervisor
  • R. Whitaker, QA Engineer

B. Wollney, Field QA Engineer

M. Schaeffer, QA Engineer

  • J. Balazer, Lead Electrical Engineer

L. Howell, Quality Assurance

R. Ostrowski, Technical Specialist

D. Martin, Quality Assurance

Bechtel Power Corporation Personnel

  • L. Dreisback, Project QA Engineer
  • J. Russell, Assistant Project Field QC Engineer
  • E. Smith , QA Engineer

W. Fish, QC Inspector

J. Smith, QC Inspector

B&W Personnel

  • R. Shope, Project Engineer

G. Cooper, Piping Superintendent

J. Jones, QC Inspector

G. Navratil, ISI Group Leader

  • Denotes those present during at least one of the five exit interviews

conducted during the report period including the one conducted by Mr. T. Vandel.

Numerous other principal staff and personnel were contacted during the

reporting period.

Licensee Action On Previous Inspection Findings

(open) Noncompliance Item (50-329/78-17-01; 50-330/78-17-01):

Personnel

airlocks weld cracking. Review of the completed NCR's CPCo NCR M-01-9-8-096

and Bechtel NCR No. 1636, established that the NCR's have been dispositioned

" accept as is" and had been approved. During discussions with licensee

representatives, it was pointed out that such a disposition overlooks the

fact that the change:1 configuration voids the stress analysis of the

airlocks and nothing was found that established that this was considered

1091

187

-2-

.

.

in the disposition. The licensee representative indicated further that

negotiations are underway currently regarding weld size, post-weld heat

treatment, and tolerances. Further review is planned during future

inspections.

(Closed) Unresolved Matter (50-329/78-07-01; 50-330/78-07-01): Radiography

reader sheet is inadequate. A radiography reader sheet for core flood

tank MK No. ICF-TIA, drawing No. C 1100-sheet 24 failed to indicate

acceptance or rejection for area 13-14.

Records presently at the site

show that the film of area 13-14 was rereviewed and that a supplemental

reader sheet had been provided that indicated the area was acceptable.

This item is resolved.

(0 pen) Noncompliance Item (50-329/78-03-02; 50-330/78-03-02): This item

was also reviewed and reported in report 50-329/79-12, 50-330/79-12 (see

Section IV, Paragraph 4) for the welding demonstration at Ohio State

University that was observed by NRC inspectors. During this inspection,

licensee representatives were contacted regarding the procedure for

monitoring and the experience to date of this activity.

It was learned

that some NCR's have been generated, as a result of voltage monitoring,

concerning rod size.

In addition it was learned that the procedure

(FPW-6.000) is under further revision.

Further review is planned during

future inspections.

Reportable Deficiencies - 50.55(e) Items

Settlement of Diesel Generator Foundations and Structures

(0 pen) Item No. (329/78-15-03; 330/78-13-03): *ihe sand preloading

of the diesel generator building has been mair.iained during the

reporting period and monitoring of the settlement has been conducted.

Test pits have been dug at different locations of the site. On

June 7, 1979, four representatives from NRR were on site to discuss

the site and settlement monitoring program.

Class 1E Battery Racks, Seismic Braces

During the reporting period the Resident Inspector was informed that

the design change to upgrade Class 1E Battery Racks to withstand a

seismic event and limit buildup of horizontal momentum had been

accepted and parts were delivered to the s:.te.

Installation of the

modification is delayed until installation of the ventilation system

-

for the battery rooms is completed.

Inadequate Cooling Water Flow to Containment Recirculation Coolers

On July 9, 1979, the licensee informed the Resident Inspector that

the calculated essential service cooling water supply pressure to

the containment recirculation air coolers will not meet the minimum

design requirements of the FSAR (Section 6.2.2.2.3) for heat removal

1091

188

-3-

.

.

.

during accident conditions. This reduction in cooling water pressure

to the air coolers is attributed to a decreasei pump suction head

from an assumed decreased cooling pond differer.cial level and addi-

tional loads being applied to the system than were origin,11y intended.

This item has been considered reportable to the NRC under the provi-

sions of 10 CFR 50.55(e) ' d appears to have safety implications if

gone undetected.

10 CFR Part 50, Section 50.55(e) reports reviewed during the inspections

include the following:

1.

Babcock and Wilcox Company (B&W) Weld Filler Certification. B&W

Topical Reports BAW-1402 and BAW-1403 were submitted to NRC offices

(then AEC) in January and April, 1973. The AEC office of Directorate

of Regulatory Operations responded with a letter dated June 19,

1973, expressing satisfaction with the reports as prepared and

concluding thet the tensile and impact values of the 80XX and 70XX

materials used in the manufacture of major NSSS components will be

within acceptable tolerance and that these major comp ~'ents involved

(Midland Units 1 and 2 Steam Generators among others) are acceptable

for their intended service. The inspection concluded that this is

sufficient information to close this report item.

2.

Unit 2 Tendon Sheathing Ommission Review covering this matter is

included in NRC reports 50-329/77-07 and 50-329/77-08 with the

latter report indicating that the licensee final report was scheduled

to be issued by August 15, 1977. The corrective actions to complete

repairs has been reviewed and considered to be adequate. The corrective

actions regarding preventing rgeurrence were reviewed as part of the

NRC review of the license response to the NRC Immediate Action

Letter dated April 29, 1977, which is reported in inspection report

50-329/77-10. This item is considered closed.

Functional or Program Areas Inspected

1.

Site Tours

At periodic intervals during the report period, tours of essentially

every area of the site were performed. These tours were intended to

assess the cleanliness of the site, storage condition of equipment

and piping being used in site construction; the potential for fire

or other hazards which might have a deleterious affect on personnel

and equipment and to witness construction activities in progress.

It was noted during one of these tours that " housekeeping" activities

associated with drilling support anchor bolt holes at the Mesonine

for the east core flood line for Unit 2 were deteriorating. The

licensee took immediate steps to improve the situation and protect

piping in the area.

1091

189

-4-

.

.

.

2.

Purge Paper in Unit 2 Reactor Building Spray System Piping

During the reporting period the Resident Inspector became aware that

a foreign object had been detected in the Unit 2 reactor building

spray system while radiographing Field Weld No. 13 on Drawing No.

,

M-613-2 at the 724 flood elevation. The weld had been cut and a

"soccerball" sized wad of soluble purge paper was removed. No

nonconformance report (NCR) was generated at the time.

Consumers

Power Company representatives did not appear to have any knowledge

of this incident nor did the radiographers "readersheet" contain any

-

information regarding the fact that the film could not be read

because of paper inside the pipe.

The NRC Regional Office was

notified and an investigation into this matter was conducted on

June 12-14, 1979, by a Regional Based Investigator.

The results of +his investigation are contained in a separate report.

As a result of this event Quality Action Request Nos. SD-207, SD-208

and SD-209 vere initiated.

3.

Post Weld Heat Treatment (PWHT) of Unit 2 Reactor Coolant System

During the report period, the licensee performed PWHT on the cold

leg weld joints at the Unit 2 reactor vessel nozzles. These joints

are designated WJ4-1, WJ4-2, WJ4-3, and WJ4-4.

The weld joints are

heat treated in pairs. Both sets of weld joints were heated twice

because of a power failure or equipment malfunction. The licensee

has experienced some difficulty in controlling PWHT temperatures

within 1100 F to 1150 F as specified in weld procedure qualification

No. 3259 for procedure WIN-102-3.

The inability to control tempera-

tures within these limitations is addressed in B&W NCR No. WN Nos.

1618,1619,1622, and 1623 for joints WJ4-1, WJ4-2, WJ4-3, and WJ4-4

respectively. Because of the difficulty in maintaining temperature

control, the licensee has modified their field procedure to require

QC inspection to monitor stress relieving (PWHT) every two hours

while temperatures are above 600 F.

Modifications to internal

heaters and insulations have also been performed to aid in developing

more even control heating. During the installation of PWHT equipment

in the cold leg side of the north steam generator, some laxity was

noted in the control of uncovered street shoes inside the reactor

coolant system. The licensee informed shift superintendents, workman

and QC personnel to be more cognizant of contaminating the reactor

coolant system.

4.

Corrosion of Buried Stainless Steel Piping

During the reporting period, a nominal 18 inch section of 6" SCH 10

stainless steel piping which was heavily corroded and appeared to

have been buried was examined by the Resident Inspector.

It was

learned that this section of piping had been removed from the discharge

of the condensate storage tank - a nonsafety related system.

Piping

-5-

.

to the boric acid storage tank - a safety related (Q) system is

fabricated from similar stainless steel piping and is buried and

unprotected from a galvanic corrosion aspect. The licensee has sent

the 6" piping from the condensate storage tank system to their

labroatories in an attempt to determine the cause of this corrosion

and the effects on similar buried stainless steel safety related

systems. Preliminary results have shown that attack of the stainless

steel condensate storage system piping may be due to electro-chemical

attacks.

5.

Presence of Fluid in 350 MCM-3/C B-11 Power Cable

Daring the reporting period, the Resident Inspector was informed

that analyses of fluid removed from one phase of selected reels of

350 MCM Power Cable supplied by ESSEX showed evidence of sulfate,

calcium, magnesium, sodium and a detectable Ph of 6.5 (reference NRC

Inspection Report 50-329/79-13; 50-330/79-13).

Engineering disposition

for the use of this cable in safety re;ated systems is continuing

and is being tracked by Noncompliance Report No. NCR 2175.

Some of

this cable is presently still installed in some safety related

circuits. The Resident Inspector informed the licensee that should

their engineering evaluation show this cable is acceptable, the

results of their evaluation would be referred to other expertise

within the NRC.

6.

Auxiliary Feedwater Pump Seal and Oil Coolers

As stated in NRC Inspection Report No. 50-329/79-16; 50-330/79-16,

Paragraph 6, more review of the qualification documentation for the

auxiliary feedwater pump seal and oil coolers was performed. A

review of Quality Surveillance Reports No. 37 through 46 pertaining

to vendor inspection of these coolers revealed some confusion with

regard to test performed and items shipped. The licensee has prepared

Nonconformance Report No. 2236 which addresses the more confusing

aspects of the associated Quality Surveillance Reports. The licensee

has requested clarification of this documentation from the Bechtel

Power Corporation. The response of Bechtel Power Corporation has

not been completely submitted and/or rcviewed by the Re:ident Inspector

at the completion of the reporting period. Therefore, this item

considered unresolved until such time that clarification can be made

available for review. Unresolved Items (329/79-15-01; 330/79-15-01).

7.

Decay / Heat Removal Pump Inservice Inspection

During the reporting period, the Resident Inspector witnessed a dye

penetrant baseline inservice inspection of the welded pump casing

supports for Decay Heat Removal Pump 2P-60A. All penetrant indications

are being photographed and recorded for future reference. The

licensee stated that 5 to 6 baseline NDE crews would be working on

baseline inservice inspection by August, 1979.

-6-

k0

8.

Qualification Testing of Cable Ties

During the reporting period, qualification testing of nylon cable

ties being considered for lashing Class IE cables to vertical cable

trays was being conducted on site. The testing is being conducted

per specification 7220-C-85Q, Technical Specification for Cable Tie

Testing Program. Test 11C for TY-409 Tefzel cable tie was witnessed

and the tie failed at a test stand loading of 245 pounds.

9m

Assembly of Unit 2 Reactor Coolant Pump

During the reporting period, the Resident Inspector witnessed insertion

of the impeller assembi.y into the lower seal housing for Unit 2

Reactor Coolant Pump 2f'-51B.

The pump is being assembled in a Class

B clean room with material and equipment control being maintained.

Pump vendor represent.itives are on-site to advi;e in the assembly of

the reactor coolant pumps.

10.

Installation of Unit 2 Containment Prestress Tendons

During the reporting period, the Resident Inspector witnessed

installation of vertical tendons from the top of Unit 2 containment.

These activities are being monitored by Bechtel QC and licensee QA

personnel.

11.

QA Overview Inspections For Instrument and Control Installations

During the reporting period, the Resident Inspector discussed with

the licensee their intended QA overview inspection for the installation

of instrument and control (I&C) systems and equipment. The licensee

stated that there was no I&C Group established for the overview of

I&C installations and that mechanically qualified personnel would

monitor the " hardware oriented" aspects of the installation. The

Resident Inspector stated that adequate overlap between the two QA

disciplines (electrical and mechanical) would be expected.

12.

Fatal Industrial Accident

On June 14, 1979, the B&W Project Engineer became overcome with

argon purge gas and subsequently fell into the Unit 2 Incore

Instrument Tank, 2T-87 while attempting an examination of the inside

of the tank. The source of the gas was from purge gas used while

velding on the tank drain line. The accident proved fatal.

13.

Complete Loss of Offsite Power

On June 20, 1079, at 1:45 p.m.,

the site experienced a complete loss

of offsite poscr because of tornado strength winds in the area

between Saginaw and Midland, Michigan. At 2:30 p.m., the site was

evacuated to enhance industrial safety while the power was off. At

-7-

}Q9)

)92

-

.

approximately 3:00 p.m. some partial power was restored to the site.

All power was essentially restored by midnight.

No accidents occurred

during this loss of offsite power and site operations were returned

to normal by the following morning.

14.

Questionable Existance of Unauthorized Weld in Unit 2 Letdown

Cooling System

During the reporting period, the Resident Inspector and a Regional

Based Inspector were informed that an apparent additional weld was

-

noted during radiographir. testing of field weld No. 8 on pipe spool

designated 2CCA-19-S-604-3-2B located in the Unit 2 Letdown Cooling

System. The above referenced spool is fabricated from 3 inch schedule

160 stainless pipe and was supplied by Southwest Fabricators. Field

weld No. 8 was made at a 90' elbow.

B&W nonconformance report NCR

No. 1606 was prepared to track this condition.

Subsequent to this

discovery the weld was cut at the weld cap and the open sections

were examined by the Resident Inspector. Only one root pass, which

had shown inferior weld quality indications, could be detected on

the inside of the pipe. Physical measurements of the elbow indicated

that the external weld cap was not placed over the location of the

weld. This gave the appearance on the radiograph that one satisfactory

weld located undn the cap and anoth~r weld (an unacceptable weld in

this instance) ensted in close proximity to each other when actually

only one weld existed.

The radiographs for field weld No. 8 and

No. 9 (on the same spool) were examined. The radiographs for field

weld No. 9 clearly indicated that the outside weld cap was placed

over a weld root. Weld record documentation for both wel k (field

weld Nos. 8 and 9) indicated that the same welder (B&W No. 441)

installed both welds. The Certificates of Performance for B&W

welder No. 441 were examined and the welder was considered qualified.

A single digit error was noted between the Social Security number

used on the Certificates of Performance and personnel records for

welder No. 441.

It appears that this may be a typographical error.

The licensee has agreed to examine all welding performed by welder

No. 441 and compare these welds to .he existing radiographs to

determine any irregularities.

Unresolved Matters

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, items of noncompliance

or deviations. One unresolved item disclosed during the inspection is

discussed in Paragraph 6.

Exit Interviews

The Resident Inspector attended the Exit Interview conducted by T. Vandel,

J. Creed, and E. Lee, Region III Reactor Inspectors and Investigator on

June 7, June 14, and June 18, 1979, respectively.

-8-

.-

.

,

.

The Resident Inspector met with licensee representatives (denoted under

Persons Contacted) on June 12, June 25, June 29, and July 11, 1979. The

inspector summarized the scope and findings of the inspection effort to

date. The licensee acknowledged the findings reported herein.

_.

1091

194

-9_