Forwards IE Insp Rept 50-346/79-15 & on 790619-22 & Notice of Violation
ML19208A873
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/30/1979
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Jeffery Grant
TOLEDO EDISON CO.
Shared Package
ML19208A874 List:
References
NUDOCS 7909180105
Download: ML19208A873 (2)


See also: IR 05000346/1979015

Text

'o

UNITED STATE 8

e

8\\

'

'n

NUCLEAR REGULATORY COMMISSION

O

3

$ g

  • , , ,' #E

REGION HI

o

799 ROOSEVELT ROAD

'

e

GLEN ELLYN,ILLINol5 60137

.....

JUL 3 01979

Docket No. 50-346

Toledo Edison Company

ATTN:

Mr. James S. Grant

Vice President - Energy

Supply

Edison Plaza

300 Madison Avenue

Toledo, OH

43652

Gentlemen:

This refers to the inspection conducted by Mr. M. D. Riden of this

office on June 19-22, 1979, of activities at Davis-Besse Nuclear

Power Station, Unit 1, authorized by NRC Operating License No. NPF-3

and to the discussion of our findings with Mr. T. D. Murray at the

conclusioa of the inspection, with Mr. G. Wells during telephone

discussions on June 28, 1979 and July 2, 1979; and conversation be-

tween Mr. R. F. Heishman and Mr. L. Roe on July 5,1979.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

As we documented in Mr. Keppler's letter of July 17, 1979

to Mr. Roe, you have already committed to carryout acceptable resolu-

tion of the issues raised in this report, including the items of non-

compliance. Therefore, no written response to the Notice of Violation

is required. We will confirm your corrective action during a future

inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter,

and the enclosures will be placed in the NRC's Public Document Room,

except as follows. If the enclosures contain information that you or

your contractors believe to be proprietary, you must apply in writing

to this office, within twency days of your receipt of this letter, to

withhold such information from public disclosure. The application must

include a full statement of the reasons for which the information is

considered proprietary, and should be prepared so that proprietary

information identified in the application is contained in an enclosure

to the application.

SiiS0W

7 909180 /OE k

.

Toledo Edison Company

-2-

JUL 3 01979

.

.

We will gladly discuss any questions you have concerning this

inspection.

-

Sincerely,

o

'

_f:

"E;f #

R. F. Heishman, Chief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-346/79-15

cc w/encls:

Mr. T. D. Murray, Station

Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Harold W. Kohn, Ohio

Power Siting

Commission

35EiOts8