Letter Sequence Other |
|---|
EPID:L-2018-TOP-0033, Attachment - Resolution of Comments Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) (Approved, Closed) |
|
MONTHYEARML18288A1032018-11-0505 November 2018 Acceptance for Review of Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Acceptance Review ML19108A1402019-05-14014 May 2019 Non-Prop Enclosure 1 Request for Additional Information Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: RAI ML19175A1602019-07-0909 July 2019 04/01-04/15/2019 Summary of Closed Audit of the Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Other ML19269B7492019-10-22022 October 2019 Cover Letter Draft Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Draft Approval ML19337A6172020-01-14014 January 2020 Attachment - Resolution of Comments Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Request ML19337A5442020-01-14014 January 2020 Enclosure 1 - Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Approval ML19337A5092020-01-14014 January 2020 Cover Letter - Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Approval ML20120A3432020-05-13013 May 2020 Verification Letter of the Approval Version of Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Other 2019-05-14
[Table View] |
Text
July 9, 2019 MEMORANDUM TO: Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation FROM: Ekaterina Lenning, Project Manager Licensing Processes Branch /RA/
Division of Licensing Projects Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF APRIL 1-5, 2019, CLOSED AUDIT OF THE WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-18240-P/WCAP-18240-NP, REVISION 0, WESTINGHOUSE THERMAL DESIGN PROCEDURE (WTDP) (EPID: L-2018-TOP-0033)
On April 1-5, 2019, a closed audit was conducted by the U.S. Nuclear Regulatory Commission (NRC) staff at the Westinghouse Electric Company (Westinghouse) office in Cranberry Township, PA. The purpose of the audit was to review the information related to the NRC review of WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (WTDP) Westinghouse Topical Report and discuss open items contained within the audit plan. Based on the audit findings, the NRC issued its request for additional information by a letter dated May 14, 2019, (Agencywide Documents Access and Management System Accession No. ML19108A135).
CONTACT: Ekaterina Lenning 301-415-3151
ML19175A156 (Package);
ML19077A106 (Notice);
ML19175A160 (Memo) *concurrence via e-mail NRC-001 OFFICE NRR/DLP/PLPB/PM NRR/DSS/SNPB/BC NRR/DLP/PLPB/BC NRR/DLP/PLPB/PM NAME ELenning RLukes* DMorey LPerkins(for)* ELenning DATE 06/24/2019 07/02/2019 07/05/2019 07/09/2019