Letter Sequence Acceptance Review |
---|
EPID:L-2018-TOP-0033, Attachment - Resolution of Comments Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) (Approved, Closed) |
|
MONTHYEARML18288A1032018-11-0505 November 2018 Acceptance for Review of Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Acceptance Review ML19108A1402019-05-14014 May 2019 Non-Prop Enclosure 1 Request for Additional Information Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: RAI ML19175A1602019-07-0909 July 2019 04/01-04/15/2019 Summary of Closed Audit of the Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Other ML19269B7492019-10-22022 October 2019 Cover Letter Draft Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Draft Approval ML19337A6172020-01-14014 January 2020 Attachment - Resolution of Comments Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Request ML19337A5442020-01-14014 January 2020 Enclosure 1 - Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Approval ML19337A5092020-01-14014 January 2020 Cover Letter - Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Approval ML20120A3432020-05-13013 May 2020 Verification Letter of the Approval Version of Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) Project stage: Other 2019-05-14
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML23355A1542023-12-20020 December 2023 WEC Acceptance 2023 DFP Surety Bond Change ML23013A2122023-01-27027 January 2023 Acceptance Letter for Westinghouse License Transfer - Cac/Epid L-2022-LLM-0004 ML21048A3462021-02-18018 February 2021 Westinghouse Electric Company, LLC - Acceptance for Reviewof Request for Alternate Disposal Approval and Exemption for Specified Columbia Fuel Fabrication Waste (Enterprise Project Identifier L 2021-LLA-0013) ML20169A2752020-06-22022 June 2020 Acceptance for Review of Westinghouse Electric Company WCAP-18482-P/WCAP-18482-NP, Revision 0, Westinghouse Advanced Doped Pellet Technology (Adopttm) Fuel ML20113E9732020-04-22022 April 2020 Letter to A. Spalding: Acceptance Letter - Request for a Temporary Change to the Site Emergency Plan ML20014E6722020-01-14014 January 2020 1-14-20 Email Acceptance for Review of Westinghouse Electric Company Topical Report WCAP-18443-P/WCAP-18443-NP, Revision 0, Qualification of the Two-Dimensional Transport Code Paragon2 ML19218A0562019-08-23023 August 2019 Acceptance for Review of Westinghouse Electric Company WCAP-16045-P-A, Addendum 2, Revision 0, and WCAP-16045-NP-A, Addendum 2, Revision 0, Updated Nexus Cross-Section Methodology ML19154A0622019-06-13013 June 2019 Acceptance for Review of Westinghouse Electric Company LTR-NRC-19-15 Notification of Changes to Westinghouse Qms ML19031C9162019-01-31031 January 2019 U.S. Nuclear Regulatory Commission Acceptance of the Fundamental Nuclear Material Control Rev. 43 and Emergency Plans Rev. 18 for Formal Review ML18288A1032018-11-0505 November 2018 Acceptance for Review of Westinghouse Electric Company Topical Report WCAP-18240-P/WCAP-18240-NP, Revision 0, Westinghouse Thermal Design Procedure (Wtdp) ML18141A5992018-06-0808 June 2018 U.S. NRC Revised Acceptance for Review of Topical Report WCAP-16747-P/WCAP-16747-NP, Appendices C and D, POLCA-T: System Analysis Code with Three Dimension Core Model, Appendices C and D ML18120A2492018-05-0303 May 2018 Acceptance of Westinghouse Electric Company, LLC - Application for Consent to Indirect Change of Control 2023-12-20
[Table view] |
Text
November 5, 2018 Mr. James A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company 1000 Westinghouse Drive Cranberry Township, PA 16066
SUBJECT:
ACCEPTANCE FOR REVIEW OF WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-18240-P/WCAP-18240-NP, REVISION 0, WESTINGHOUSE THERMAL DESIGN PROCEDURE (WTDP)
(EPID: L-2018-TOP-0033)
Dear Mr. Gresham:
By letter dated August 27, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18242A238), Westinghouse Electric Company (Westinghouse) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review Topical Report (TR)
WCAP-18240-P/WCAP-18240-NP, Revision 0 Westinghouse Thermal Design Procedure (WTDP).
The NRC staff has reviewed submitted information and performed an acceptance review of the TR. We have found that the material presented is sufficient to begin our review. We expect to issue our initial request for additional information by August 30, 2019, and issue a draft safety evaluation by January 24, 2020. This schedule information takes in consideration the NRCs current review priorities and available technical resources and may be subject to change. If modifications to these dates are deemed necessary, we will provide appropriate updates to this information.
The NRC staff estimates that the review will require approximately 600 staff hours including project management time. The review schedule milestones and estimated review costs were discussed and agreed upon via email between George Yates, Product Line Regulatory Support, Westinghouse, and the NRC staff on October 12, 2018.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours will be billed accordingly.
J. Gresham If you have questions regarding this matter, please contact Ekaterina Lenning at (301) 415-3151.
Sincerely,
/RA/
Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket No. 99902038
ML18288A103; *concurred via e-mail NRR-106 OFFICE NRR/DLP/PLPB NRR/DLP/PLPB* NRR/DSS/SNPB* NRR/DLP/PLPB NAME ELenning DHarrison RLukes DMorey DATE 10/15/18 11/1/18 11/5/18 11/5/18