ML19126A323
| ML19126A323 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 05/06/2019 |
| From: | Richard Guzman Plant Licensing Branch 1 |
| To: | Sinha S Dominion Energy Nuclear Connecticut |
| Guzman R | |
| References | |
| EPID L-2019-LLR-0031 | |
| Download: ML19126A323 (2) | |
Text
From:
Guzman, Richard To:
Shayan Sinha Cc:
RidsNRRLIC109 Resource; Danna, James
Subject:
Acceptance Review Determination: Millstone Unit 2 - Proposed Alternative Request RR-05-01, VT-2 Pressure Testing Requirements for the Lower Portion of the RPV (EPID: L-2019-LLR-0031)
Date:
Monday, May 6, 2019 7:40:53 PM
- Shayan, By letter dated March 29, 2019 (ADAMS Accession No. ML19106A049), Dominion Energy Nuclear Connecticut, Inc. (DENC) requested an alternative for Millstone Power Station, Unit 2 to conduct the VT-2 examination of the pressure retaining surfaces of the lower portion of the reactor pressure vessel following plant cooldown during each refueling outage at ambient conditions.
The purpose of this e-mail is to provide the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the submittal has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed DENCs submittal and concludes that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that the review of the relief requests will take approximately 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br /> to complete. The NRC staff expects to complete this review by April 2020 (i.e., approximately 11 months). If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date (greater than a month) or significant changes in the forecasted hours (greater than 25%), the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
Please contact me if you have any questions. A copy of this email will be made publicly available in ADAMS.
- Thanks,
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Rich Guzman Sr. PM, Division Operator Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Office: O9C-7 l Phone: (301) 415-1030 Richard.Guzman@nrc.gov