Letter Sequence Response to RAI |
---|
EPID:L-2019-LLA-0098, Notification of Expected Date of Transfer of Ownership of Nuclear Unit to Holtec Pilgrim, LLC; Notification of Satisfactory Documentary Evidence of Insurance; and Notification of Receipt of All Required Regulatory Approvals (Approved, Closed) |
|
MONTHYEARML18341A2192018-12-0404 December 2018 Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50 Project stage: Response to RAI ML19056A1902019-02-18018 February 2019 Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50 Project stage: Response to RAI ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements Project stage: Acceptance Review ML19234A3572019-08-22022 August 2019 Notification of Expected Date of Transfer of Ownership of Nuclear Unit to Holtec Pilgrim, LLC; Notification of Satisfactory Documentary Evidence of Insurance; and Notification of Receipt of All Required Regulatory Approvals Project stage: Request ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan Project stage: Other ML19276C4202020-01-0202 January 2020 Issuance of Amendment No. 252, Request to Remove Cyber Security Plan Requirements for the Permanently Defueled Condition Project stage: Approval ML20084K4322020-03-24024 March 2020 Issuance of Amendment No. 252 to Renewed Facility License Remove Cyber Security Plan License Condition- Correction of Typographical Error Project stage: Approval ML21090A1932021-05-19019 May 2021 Issuance of Amendment No. 237 Regarding Adoption of 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components of Nuclear Power Reactors Project stage: Approval 2019-05-20
[Table View] |
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23300A0022023-10-27027 October 2023 10 CFR 72.48 Biennial Change Summary Report IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 ML23143A0872023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 And Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 2024-09-18
[Table view] |
Text
Entergy Nuclear Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Tel 601-368-5573 Mandy K. Halter Director, Nuclear Licensing 10 CFR 50.12 10 CFR 50.47 10 CFR 50, Appendix E 2.19.011 February 18, 2019 ATIN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50 Pilgrim Nuclear Power Station NRC Docket 50-293 Renewed License No. DPR-35
References:
- 1) Entergy Nuclear Operations, Inc. letter to NRC, "Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50 Appendix E," dated July 3, 2018 (ADAMS Accession No. ML18186A635)
- 2) NRC email to Entergy Nuclear Operations, Inc., "RAI - Pilgrim EP Exemption (EPID: L-2018-LLE-001"1 )," dated November 6, 2018 (ADAMS Accession No. ML18310A021)
- 3) Entergy Nuclear Operations Inc. Letter to NRC "Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50," dated December 4, 2018 (ADAMS Accession No. ML18341A219)
- 4) NRC email to Entergy Nuclear Operations, Inc., "RAI - Pilgrim EP Exemption (EPID: L-2018-LLE-0011 )," dated February 4, 2019 (ADAMS Accession No. ML19036A651)
In Reference 1, Entergy Nuclear Operations, Inc. (Entergy) submitted a request to the U.S.
Nuclear Regulatory Commission (NRC) for exemption from portions of Title 10 Code of Federal Regulations (CFR) 50.47 and 10 CFR Part 50, Appendix E for the Pilgrim Nuclear Power Station (PNPS).
The NRC requested additional information on November 6, 2018 (Reference 2) related to heat transfer within the adiabatic analysis boundary. By letter dated December 4, 2018 (Reference 3), Entergy provided a response to the NRC request for additional information.
2.19.011 Page 2 of 2 In Reference 4, the NRG requested additional information concerning the exemption request related to justification and/or discussion of how heat transfer could occur to all components within the adiabatic envelope, specifically the upper and lower plenums. to this letter provides the Entergy response to the NRG request for additional information (RAI). Attachment 2 to this letter provides the revision of Entergy calculation PNPS-EC-81416-M1418 in support of the response to the NRG RAI. This revised calculation replaces the calculation that was provided in Attachment 2 of Reference 1.
This RAI response does not impact the conclusions of the evaluation presented in Reference 1.
This letter contains no new commitments and no revisions to existing commitments.
If you have any questions or require additional information, please contact Mr. Peter J. Miner at (508) 830-7127.
A copy of this submittal has been provided to the designated Commonwealth of Massachusetts officials.
lf27~
Respectfully, Mandy K. Halter MKH/db/mp Attachments:
- 1. Response to Request for Additional Information - Exemption from the Requirements of 10 CFR 50.47 and Appendix E to 10 CFR Part 50, Entergy Nuclear Operations, Inc.,
Pilgrim Nuclear Power Station
- 2. Calculation No. PNPS-EC-81416-M1418, Adiabatic Heatup Analysis for Drained Spent Fuel Pool.
cc: NRG Region I Regional Administrator NRG Senior Resident Inspector - Pilgrim NRG Project Manager - Pilgrim Massachusetts Emergency Management Agency, Planning, Preparedness and Nuclear Section Chief Massachusetts Department of Public Health, Director, Radiation Control Program