ML18153B325

From kanterella
Jump to navigation Jump to search
Insp Repts 50-280/93-21 & 50-281/93-21 on 930816-20.No Violations Noted.Major Areas Inspected:Licensee Eds to Assess Corrective Actions Taken or Planned in Response to Findings Identified During Licensee Self Assessments
ML18153B325
Person / Time
Site: Surry  
Issue date: 09/17/1993
From: Julian C, Shymlock M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18153B324 List:
References
50-280-93-21, 50-281-93-21, NUDOCS 9309280171
Download: ML18153B325 (14)


See also: IR 05000280/1993021

Text

Report Nos. :

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION 11

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

50-280/93-21 and 50-281/93-21

Licensee: Virginia Electric and Power Company

Glen Allen, VA

23060

Docket Nos.:

50-280 and 50-281

Facility Name:

Surry 1 and 2

License Nos.:

DPR-32 and DPR-37

Inspection Conducted: August 16-20, 1993

Inspector:---:~.,...--=---*

..... ~----.-*-~o/~~b--:----=-~-~~~~~~~~~~

M. Shymlock,'~hief

Plant Systems Section,

Division of Reactor Safety

Accompanying Personnel:

R. Moore

S. Rudisail

N. Salgado

Approved by: cL,,L~

'

~*c. Juli an, Chief

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

~;_/6-93

Date Signed

Date Signed

This routine, announced, reduced scope inspection of the licensee's EDS was

conducted to assess the corrective actions taken and planned in response to

findings identified during their self-assessments. The adequacy of the

licensee's assessment process was also reviewed.

Results:

The inspection concluded that the licensee's EDSFA was adequate to assess the

design and functional capability of their EDS.

The independent review

verified the licensee's conclusion that the EDS met it's design and functional

capability.

EDSFA findings were adequately identified, tracked, and addressed

for corrective actions.

In the areas inspected, violations or deviations were not identified .

9309280171 930917

PDR

ADOCK 05000280

G

PDR

REPORT DETAILS

1.

Persons Contacted

2.

Licensee Employees

  • R. Bilyeu, Licensing Engineer
  • H. Blake, Supervisor, Design, Electrical Engineering
  • R. Blount, Superintendent, Station Engineering
  • A. Brown, Supervisor, Nuclear Training
  • D. Christian, Assistant Station Manager, Operations and Maintenance
  • R. Cross, Coordinator, Nuclear Procedures
  • J. Downs, Superintendent, Outage and Planning
  • G. Flowers, Manager, Nuclear Electrical Engineering
  • D. Georgianna, Supervisor, Systems Protection
  • G. Jones, Design, Electrical Engineer
  • A. Keagy, Superintendent, Station Materials
  • J. LaFlam, System Engineer
  • J. McCarthy, Assistant Station Manager, Nuclear Safety & Licensing
  • W. McCloskey, Supervisor, Design, Mechanical Engineering
  • D. O'Connor, System Engineer

M. Phillips, Electrical Engineer

  • R. Rasnic, Corporate Supervisor, Mechanical Engineering

J. Ruddy, Senior Electrical Engineer

  • V. Shifflett, Licensing Engineer
  • E. Smith, Jr., Manager, Quality Assurance
  • W. Stallings, Corporate Supervisor, Electrical Engineering
  • J. Surface, Senior Staff Engineer
  • G. Thompson, Superintendent, Maintenance (Acting)
  • J. Waddil, Staff Engineer, Mechanical

Other licensee employees contacted during this inspection included

craftsmen, engineers, operators, and technicians.

NRC Employees

  • M. Branch, Senior Resident Inspector
  • Attended Exit Interview

Acronyms and abbreviations are listed in the last paragraph.

Introduction

In a letter to the NRC dated June 3, 1993 the licensee requested that the

Electrical Distribution System Functional Inspection (EDSFI) scheduled

for Surry be waived.

The licensee indicated that prior to the EDSFI at

North Anna their Corporate Nuclear Safety (CNS) group, with assistance

from outside consultants, performed an internal EDSFA at North Anna.

Following that effort and the NRC's EDSFI at North Anna, the CNS group

performed a similar assessment of Surry's electrical distribution system.

That assessment included applicable questions and the lessons learned

3.

2

from the NRC's EDSFI and their own internal assessment of North Anna.

Based on this effort a corrective action tracking database for these

issues was developed. This database has been used to track the

resolution of these issues as well as other electrical issues that were

identified.

During the week of June 28, 1993, the Section Chief of the Plant Systems

Section in the Division of Reactor Safety in Region II visited the

licensee's facility. This visit was for the purpose of reviewing the

licensee's self-assessment and to look at some corrective actions.

Further discussions on this matter were conducted with selected licensee

staff and NRC Management in the Regional Office on July 28, 1993. A

decision was made by NRC Management to reduce the scope of the EDSFI at

Surry.

Conclusions

The licensee's self-assessments were well developed and performed by

knowledgeable individuals. The scope of the EDSFA was similar to that of

the NRC's EDSFI Temporary Instruction 2515/107.

It was concluded that

the scope of the EDSFA was adequate to assess the design and capability

of the EDS.

Independent reviews of specific aspects of the EDS were

performed by the inspectors and verified the adequacy of the licensee's

conclusions. A strength was noted in the area of interface between

station and substation personnel in communication and control of work

activities in the switchyard.

The inspectors reviewed the EDSFA results and corrective actions taken

since the conclusion of the EDSFA.

Overall, the licensee has responded

to the EDSFA findings satisfactorily. The licensee was continuing to

assess the status of corrective actions and calculation revisions to

enhance the design of the EDS at Surry.

The licensee developed a database system that categorizes the identified

issues into six areas (Calculations, Procedural, Programmatic, Setpoint,

System Design, and Documentation).

The database is used to track

completion of corrective actions. It includes EDSFA issues, North Anna

EDSFI questions, and self-identified electrical issues. This is a very

useful system.

At the end of the inspection the corrective action status

of the 791 identified issues indicated that only 55 remained open.

The EDSFA scope was adequate to assess the adequacy of the design and

functional capability of the EDS mechanical support systems.

Findings

were appropriately identified, tracked, and addressed for corrective

actions. Mechanical systems were adequately designed and maintained to

support the EDS.

Accident equipment electrical loads were properly

determined.

The emergency diesel generator load testing performed in 1989 was

identified as a strength. The inspector noted however, that no endurance

testing has been accomplished for the EDGs to challenge their capability

for an extended run at rated load.

3

A weakness was identified in the fuel oil chemistry monitoring program in

that particulate analysis of the oil did not provide a specification or

action level. The inspector noted an example where this parameter

exceeded typical values and no actions were taken.

Calculations were not available to verify that all safety related equip-

ment spaces' ambient temperatures did not exceed equipment specifi-

cations. This was identified by the licensee and corrective actions were

in progress.

Review of bounding conditions indicated no apparent

operability concerns.

The EDSFA evaluation of EDS seismic applications was rigorous and

findings were adequately addressed.

4.

EDS Review

The inspectors reviewed the electrical calculations. The calculations

were reviewed with respect to the corrective actions to findings identi-

fied in the EDSFA or in the calculational upgrade program being performed

by the licensee. Limited system walkdowns were performed to assess

material conditions of the EDS.

4.1 Offsite Power System

The licensee conducted a Switchyard Equipment Reliability Assessment

between May 1992 and September 1992. This assessment included the

review of electrical equipment, transmission and distribution

interconnecting lines, and protective relaying equipment in the

switchyard. This effort was performed by Commercial Operations

personnel who were knowledgeable in this field. Their goal was to

identify switchyard equipment conditions and problems that may

affect the overall reliability of the switchyard. The inspectors

reviewed this effort and some corrective actions identified to

address specific concerns. This assessment was very thorough,

complete and objective. The corrective actions were being properly

implemented.

The follow-up of the CNS Switchyard Follow-up Assessment dated

April 28, 1992, was also reviewed. It was noted that the site and

Substation Maintenance had taken corrective actions to address

specific concerns and recommendations identified in the assessment.

A strength was noted in the area of interface between station and

substation personnel in communication and control of work activities

in the switchyard.

Several modifications to the switchyard electrical distribution

system at Surry were referenced in the request from the licensee to

waive the EDSFI inspection at Surry.

One of these modifications was

the 34.5 kV Bus No. 5 Modification.

Due to an event which occurred

in the switchyard on August 26, 1991, the Substation and Protection

Department was assigned the task of evaluating the switchyard

configuration and making recommendations if improvements were

\\.

4

warranted.

The resulting evaluation identified two problems which

needed correction. The first problem identified was with the

existing switchyard configuration. This configuration resulted in a

fault on the switchyard Station Service Transformer No. 1 (SSTX#l)

secondary causing activation of plant emergency systems.

The second

problem identified was that the SSTX#l was directly connected to Bus

  1. 5 without a means of disconnect. This was disadvantageous because

personnel would be required to enter the switchyard to physically

isolate SSTX#l from Bus No. 5 in the event of a failure of the

transformer. This results in additional time with the Reserve

Station Service Transformers out of service.

As a result of the

identification of these problems, a Design Change Package was

developed to evaluate and document switchyard modifications to

eliminate the problems.

The modification to address these problems involved the

reconfiguration of 34.5 kV switchyard Bus #5.

SSTX#l was changed to

an open-wye open-delta connected transformer.

This reconfiguration

included adding a grounding transformer to the secondary of the 500

kV to 34.5 kV transformer No. 1, and installing a set of load break

fused cutout switches between 34.5 kV Bus No. 5 and the primary

bushings of SSTX#l.

This allows disconnection of SSTX#l from the

Bus No. 5.

r

4.2 Onsite Electrical Systems

Medium Voltage System Calculations

The inspectors reviewed calculation EE-0034, Surry Voltage Profiles.

This calculation was recently completed to verify and document

sufficient starting and running voltages existed at the emergency

4.16 kV and 480 V busses. This calculation superseded previous

calculations.

Calculation EE-0034 was developed from Auxiliary Design Optimization

Program (ASDOP).

The inspector reviewed this calculation to ensure

that the results demonstrated adequate voltage for the 4.16 kV and

480 V distribution systems for the system alignments modeled.

During the review of the calculation the inspectors expressed

concern for a system alignment in which the calculated voltage level

had a narrow margin. This narrow voltage margin was on the 480 V

Bus lJ which supplied the containment spray and low head safety

injection pumps.

The calculation demonstrated an available voltage

of 348.97 V.

The required starting voltage was 348.83.

The

inspector requested further examination of this voltage calculation.

The inspector determined that the calculation contained both

conservative and non-conservative assumptions and could not justify

the acceptance of the narrow margin.

The low head safety injection

pump is a 300 hp motor. This was previously a 250 hp motor but when

the pump motor was replaced the smaller size was not available .

This additional load on the bus resulted in the narrow voltage

5

margin.

Licensee engineering personnel had analyzed the voltage

torque-speed curves for the 300 hp pump motor and determined the

motor would accelerate the load at this calculated voltage.

Discussion with licensee personnel indicated that if the required

starting voltage was not available initially, sufficient voltage

would be available prior to the protective devices tripping the

breaker for this motor.

Licensee personnel generated an additional

computer run that demonstrated that once the high head safety

injection pump started on the 4.I6 kV bus, voltage levels would

increase on the 480 V bus to ensure that the lowhead safety injec-

tion pump and the containment spray pump would have sufficient

starting voltage prior to any breakers tripping. The inspectors

agreed that this adequately resolved the voltage concerns of this

calculation.

The inspectors reviewed calculation EE-0502, 4.I6 kV Degraded

Voltage and Undervoltage Relay Setpoints.

EE-0502 determined the

4.I6 kV degraded voltage and loss of voltage relay setpoints for the

4.I6 kV emergency busses.

The original basis for these degraded

voltage and undervoltage setpoints was developed by Stone and

Webster Engineering Corporation {SWEC).

The SWEC calculation relied

on assumptions and did not investigate the influence of voltage

drops down to 480 V Motor Control Center {MCC) loads in sufficient

detail. The licensee revised the degraded voltage section of

EE-0502 to ensure that there was adequate voltage to pick-up all

contactors in the Class IE MCCs, and the minimum continuous running

voltage was supplied to all Class IE motors on the medium and low

voltage emergency busses.

EE-0502 concluded that the degraded

voltage setpoint could be increased to improve motor terminal

voltages.

EE-0502 was being revised to reflect the recommendation.

The licensee will properly coordinate the revision of EE-0502 with

the revision of calculation EE-0034, Surry Voltage Profiles. Until

the TSs are amended to reflect a new degraded setpoint, the 480 V

loads' terminal voltages range from 85% to 90% of rated voltage.

These terminal voltages result when the 4.I6 kV bus voltage is at

the degraded voltage setpoint minus the Channel Statistical Analysis

{CSA).

The licensee determined that the motors are still operable

because no overload protection would activate in this voltage range.

The licensee's calculation revision also concluded that the loss of

voltage setpoints were adequate for the existing setting. The

inspectors identified no deficiencies with the ongoing revision of

EE-0502.

The inspectors reviewed calculation EE-0334, Surry Emergency Bus

Fault Current Analysis.

This calculation provided an updated

review of available fault currents on the emergency 480 V and 4.I6

kV systems for comparison to the existing MCC, loadcenter and

switchgear duty ratings. This calculation was performed using the

ASDOP software. The results of this calculation indicate that the

4.I6 kV switchgear breakers are adequately sized to interrupt the

calculated fault currents. For the 480 V system, the calculations

6

demonstrated adequate breaker interrupting ratings for the 480 V

load centers. However, for the 480 V MCCs the calculation demon-

strated that the available fault current exceeded the ratings of the

molded case circuit breakers.

The circuit breakers were rated at

14,000 A interrupting capacity. They are Westinghouse type FA and

FB circuit breakers.

The calculated fault current was 19,029 A for

a maximum MCC bus voltage of 506 V.

The licensee had conducted a study which determined the

manufacturer's ratings for these breakers was conservative. Actual

ratings for these breakers was 16,600 A for the breaker only.

With

the circuit breaker in combination with a motor starter the

interrupting capacity was 19,000 A.

The results of the study have

been presented to the NRC for consideration. The same issue exists

at the North Anna Power Station. A study with similar conclusions

was also performed for the North Anna Power station. Both of these

studies will be reviewed further by the NRC.

Calculation EE-0372, Surry Non-emergency Bus Fault Current Analysis

was also reviewed. This calculation computed the available faults

for the 4.16 kV and 480 V non-emergency busses.

The results demon-

strated adequate interrupting ratings for the non-emergency power

system with the exception of some molded case circuit breakers.

The

same concern for available interrupting capacity existed on these

breakers as in the 480 V emergency system discussed in the previous

paragraph.

The inspectors reviewed the coordination and protection scheme for

the AC Distribution system. Calculations EE-0335, Relay Settings

for Feeder Breakers on Busses lH and lJ (4160 V), -EE-0313, Relay

Settings for the Protection of Safety Bus lJ at Surry, and EE-0312,

Relay Settings for the Protection of Safety Bus lH at Surry were

reviewed.

The results of these calculations demonstrated adequate

relay setting for acceptable coordination. The licensee's engineers

are considering a revision to the settings of these relays on busses

lH and lJ to improve the coordination of the stub bus breakers with

the EDG output breakers.

The inspectors considered that the review

of these relay settings was satisfactory.

Calculation EE-0497, Safety Related 480 V Load Center Coordination

was performed to review and document the overcurrent protection and

coordination for the 480 V safety related load centers. The

licensee concluded that adequate coordination exists. Several

instances of miscoordination were identified in the calculation but

were not determined to be safety significant. The inspectors agreed

with this determination.

Low Voltage DC System Calculations

The inspectors reviewed calculation EE-0499, DC Vital Bus Short

Circuit Current. The purpose of EE-0499 was to evaluate the maximum

fault current on the 125 VDC busses. Charger contributions and

7

maximum electrolyte temperature effects were included when

determining the worst case fault currents.

EE-0499 was initiated to

re-evaluate the fault currents calculated in SWEC calculation

14937.16-E-l, DC Vital Bus Short Circuit Current.

The worst case

fault current calculated was 19,745 A on Bus 28 with two chargers

connected. The results of EE-0499 concluded that under normal plant

operating conditions, the fault currents available to the DC busses

are within the breaker's interrupting ratings.

The licensee's EDSFA identified a concern with the fault current

available when all four UPSs and one battery are connected to the

cross-tied busses.

The fault current available from the four UPSs

was calculated to be 1752 A.

If the cross-tie breaker was closed

this bus would be exposed to the fault contribution of four

chargers, and would allow a current of 20621 A on DC Bus 28. This

would exceed the manufacturer's rating of 20,000 A at 250 VDC for

the breakers. The licensee did not consider this to be an unsafe

condition because the Westinghouse data sheets for the HFB breakers

indicated an interrupting rating of 20,000 A at 250 VDC.

The

breakers at Surry are used in a 125 VDC application.

The licensee

concluded that since interrupting ratings have an inverse

relationship to voltage, a rating higher than 20,000 A would be

available when applied on 125 VDC.

Westinghouse indicated to the

licensee that the HFB breakers were capable of safely interrupting

faults in excess of 20550 A at 125 VDC.

The calculation was

conservative because cable resistances for the cables fed from the

feeder busses to the chargers were not considered in the fault

study. This resistance would lower the fault contribution from the

chargers.

Thus the calculation approach and the breaker's

interrupting rating was adequate.

The inspectors reviewed calculation EE-0046, Surry VDC Loading

Analysis.

The purpose of EE-0046 was to verify the actual loading

on each 125 VDC Distribution Cabinet, confirm battery sizing, and

determine voltage levels at the distribution panels. The load cycle

determined by EE-0046 differed from the calculations which were used

to originally size the station batteries. However, the batteries

were still adequately sized* to satisfy the load cycle required at

the station under a worst case accident condition. The calculation

concluded that the voltage levels for the 125 VDC system are capable

of operating the station equipment as required.

The inspectors con-

cluded that EE-0046 demonstrated that adequate voltage was available

for the 125 VDC system. It was also noted that the 125 VDC

Calculation Upgrade Program (CUP) will develop a detailed model of

the 125 VDC system including loads, load parameters, load operating

requirements for the station batteries. The model will include the

battery duty cycle, voltage drops, fault currents, jumpered cell

analysis, and input to the battery charger sizing analysis.

The inspectors noted that the licensee had installed a non-safety

battery~ This battery is located in a separate building outside'the

turbine building. The battery installation reduced the previous

8

loading of the station's vital batteries by assuming some of the

non-safety loads.

The licensee designated this particular battery

as the "Black Battery". The inspectors assessed that this was a

good approach to increase the load margin on the station's vital

batteries. The inspectors also conducted a limited walkdown

inspection of the black battery room and no problems were

identified.

The inspectors reviewed calculation EE-0493, Black Battery Short

Circuit Duty. The purpose of EE-0493 was to evaluate the maximum

fault current at the*black battery.

EE-0493 was initiated to re-

evaluate the fault currents which were included in older SWEC

calculations. EE-0493 included fault current contributions from the

battery chargers, the emergency oil pump, and the air side seal oil

pump.

The breakers located on the black battery busses have an

interrupting rating of 20,000 A at 250 VDC, and have been previously

determined to have an interrupting rating of at least 20,000 A at

125 VDC.

The calculation concluded that the maximum available fault

current including motor and charger contributions with the maximum

electrolyte temperature effects was 16764.40 A at the 125 VDC

distribution cabinet 1-1.

The licensee concluded that the fault

currents calculated were less than the interrupting ratings of the

circuit breakers. Therefore, the 125 VDC protective devices had

adequate interrupting capacities. The inspectors also noted that

the 125 VDC CUP model will also include the black battery .

5.

MECHANICAL SYSTEMS

The inspector reviewed the mechanical area of the licensee's EDSFA to

determine if the scope was adequate to appropriately assess the design

and functional capability of EDS mechanical support systems.

The EDSFA

findings and associated corrective actions were reviewed.

Additionally

the inspector accomplished an independent review of various mechanical

areas such as accident equipment electrical loads, Emergency Diesel

Generator (EDG) maintenance and testing, and fuel oil chemistry

monitoring.

Documents reviewed included the licensee's EDSFA, EDSFA

follow-up report, Updated Final Safety Analysis Report (UFSAR),

maintenance procedures and documentation, mechanical system calculations

and design information.

5.1 Accident Equipment Load Values

The inspector reviewed the licensee's calculations for accident

equipment electrical load values for safety related pumps and fans.

These values provided input to the EDG loading calculations.

Calculation EE-0035, EDG Loading Analysis, revision 1, listed

equipment load values. Calculation EE-0029, Surry Electrical Load

List, revision O, provided the basis for these load values and

included safety related pump and fan curves.

The inspector verified

accident flow values with the Design Basis Documents (DBDs) and the

5.2

9

UFSAR.

The inspector concluded that the accident equipment load

values were appropriately determined and input to the EDG load

calculation.

EDG Testing and Maintenance

The inspector reviewed the licensee's design and test documentation

which verified the EDG capability to meet its design load require-

ments. Additionally, the inspector reviewed maintenance activity on

the EDGs.

The licensee conducted comprehensive load testing with

resistive load banks in 1989 to verify accident loading capability.

Calculation EE-0045, EDG Voltage and Frequency Response, revision 0,

documented EDG response characteristics to worst case loading. This

test verified the EDG ability to provide adequate starting and

running voltages for safety related equipment.

The EDG frequency

and voltage criteria of Regulatory Guide 1.9, Selection, Design, and

Qualification of Diesel Generator Units Used as Standby Electric

Power Systems at Nuclear Power Plants, revision 2, were used as

acceptance criteria for testing.

The load testing was accomplished on EDG 3 and equivalency of EDGs 1

and 2 was verified. Equivalency was established by performance of

maintenance and minor modifications recommended by the EDG vendor,

Morrison-Knudsen.

Primarily, the voltage regulators were calibrated

and tested and the governors were modified to assure equivalent

response.

The equivalency was documented in Report No. 5714-2R,

Maximum Cold Diesel Load Carrying Capability, revision I, by

Morrison-Knudsen.

The vendor recommended a restriction on initial

loading of the EDG to account for cold start conditions. It was

recommended that the pressurizer heater load be delayed for two to

three minutes.

The licensee delayed the loading of pressurizer

heaters for 180 seconds.

The inspector reviewed the load sequencing

logic for the heaters and verified that the load was delayed 180

seconds.

The inspector concluded that EDG load capability testing

was a strength.

The inspector noted that no endurance testing had been accomplished

for the EDGs to assure their capability to run at rated load for an

extended period of time, as could be required in an accident

condition.

The longest documented continuous run was 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> on

February 29, 1992.

Two hours were at rated load and the remainder

was at 900 kW.

The operating logs indicated that operating

parameters stabilized, however this run did not approximate the

conditions of an extended run.

An endurance run was not required by

TS.

The licensee met all TS operability requirements for the EDGs.

Review of maintenance demonstrated that the licensee performs

adequate routine maintenance to maintain the design capability of

the EDGs.

The inspector reviewed the work orders which documented

performance of the last 18 month service inspection of each EDG .

Work orders 3800118417, 3800132112, and 3800118418 documented

10

inspection results for EDGs 1, 2, and 3, respectively.

The inspec-

tions and maintenance accomplished implemented vendor recommenda-

tions and the results met recommended acceptance criteria.

Overall, the inspector concluded that the EDGs were adequately

maintained and TS operability requirements were met.

The

reliability of the EDGs was good at 0.99 and unavailability was

limited to approximately 53 hours6.134259e-4 days <br />0.0147 hours <br />8.763227e-5 weeks <br />2.01665e-5 months <br /> for 1993.

The 1989 load testing

provided assurance of the EDG loading capability.

An endurance test

would provide further assurance of the EDGs accident capability.

5.3

EDG Support Systems

Air Start System

The EDSFA reviewed the air start system design. A finding in this

area identified that the design requirement stated in the UFSAR

regarding the three start capability of the system had not been

adequately verified. The testing previously performed did not

initiate the test from the air receiver 165 psi low pressure alarm

point.

In response to the finding the licensee performed an

appropriate test on the EDG 2 air start system and verified this

design requirement. Similar testing was scheduled for the next unit

1 refueling outage to verify the requirement on EDGs 1 and 3.

The

inspector noted that the licensee did not directly monitor air start

system air quality, however adequate routine start up testing of the

EDGs would identify a degrading system capability.

Fuel Oil System Capacity

The inspector reviewed the fuel oil storage calculations and the

scope of the licensee's review in this area. Calculations 01039.34-

10-M-3, EDG Base and Day Tank 3 Hour Usable Fuel Oil Supply,

revision O, and 01039.3410-M-2, Underground Fuel Oil Storage Tank 7-

Day Useable Fuel Oil Supply, revision 0, demonstrated that adequate

fuel oil capacity existed to meet design and TS requirements.

The

EDSFA identified that the TS minimum day tank level requirement of

290 gallons did not meet the UFSAR design statement of a minimum 3

hour capacity.

The licensee's corrective action was to initiate a

TS change to require a minimum 594 gallons requirement which was the

3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> volume.

The inspector concluded that the fuel oil system met

system design and functional requirements and the findings were

appropriately identified and resolved.

Fuel Oil Chemistry Monitoring

The inspector reviewed the licensee's program for monitoring of fuel

oil quality and identified a weakness in this area.

The licensee

had a history of fuel oil quality concerns.

Biological fouling was

identified in 1989 after which the tanks were cleaned and a biocide

was added to the oil. A particulate problem was identified in 1991

as a result of frequent EDG fuel filter changes.

As a corrective

11

action the onsite fuel oil was cleaned with a portable filtration

system and the fuel oil vendor was changed.

The new vendor provided

a consistently higher grade of fuel oil. Additionally, in 1992, the

licensee added particulate analysis to the chemistry parameters

which were.monitored.

The program weakness was that the licensee

provided no limiting specification for this parameter. A "typical

value" of 10 mg/1 was referenced in the chemistry manual monitoring

program, Nuclear Plant Chemistry Manual, section 52.10.

The EPRI

guide in this subject area, Electrical Power Research Institute

Guide for Nuclear Power Plant Maintenance, Storage and Handling of

Fuel Oil for Standby*Oiesel Generator Systems, August 1988,

recommended a maximum value for this parameter of 10 mg/1.

The inspector reviewed fuel chemistry analysis results for 1992 and

1993. These results demonstrated that the particulate content of

the oil in the above ground storage tank and one of the underground

tanks exceeded the "typical value" in the first quarter of 1993.

No

action was taken to re-sample the tanks until the next routine

sample in the following quarter. The second quarter sample analysis

indicated values were below the "typical value" of 10 mg/1.

Based

on the previous history of fuel quality problems at Surry, this lack

of response to an indication of fuel quality problems was considered

a weakness which was attributable to the lack of a limiting

specification for this parameter *

Heating Ventilation and Air Conditioning (HVAC)

The inspector reviewed the EDSFA HVAC scope, corrective actions for

findings, and available calculations which demonstrated the adequacy

of the HVAC systems' design. The control room and safety related

switchgear room calculation was completed and verified that HVAC

system design ensured that equipment ambient temperature specifica-

tions were not exceeded. This calculation was 02071.2110-M-2,

Control Room Envelope Heat Load.

The HVAC calculations for other

safety related equipment spaces had not been developed. This was an

EDSFA finding.

The inspector verified that these calculations were

being developed as corrective action for this finding.

The

scheduled completion date for the calculations was December, 1993.

The inspector reviewed test and design information to verify that no

operability concerns existed. Operating logs demonstrated that

ambient temperatures for the EOG room with the EOG at rated load

during summer operation stabilized at 89 degrees F.

The logs were

dated July 17, 1992. Site meteorological information indicated that

anticipated site maximum outside temperature was 93 degrees F,

Based on this information it was improbable that EOG room tempera-

tures would exceed the 120 degree F equipment rating. The charging

pump room was

assumed to be the most limiting safety related pump

room because it had the largest pump, 600 horse-power, _and lowest

12

ventilation flow, 7000 cubic feet per minute.

Historical

temperature data for this space demonstrated that ambient

temperatures did not exceed equipment specifications.

Overall, HVAC for safety related equipment spaces was adequately ad-

dressed by the EDSFA.

Findings were appropriately identified and

addressed.

Identified problems were related to a lack of documenta-

tion to verify system capacity.

No apparent operability concerns

were identified.

Seismic Issues

The inspector reviewed the EDSFA scope and assessment of the EDS

seismic applications. The licensee identified examples of unquali-

fied seismic category 2 over qualified category 1 equipment in the

EDG rooms.

These included the steam piping and heaters for space

heating, and overhead lights. The licensee evaluated the piping and

heaters using Seismic Qualification Utility Group (SQUG) criteria

and determined this equipment was adequate to sustain anticipated

seismic stress. Calculation SEQ-1278, EPL Lighting Evaluation dated

November 17, 1992 was developed to assess the lighting. A minor

modification installing additional lighting fixture supports was

accomplished with Engineering Work Request EWR 89-373.

The air start system air receiver pressure switch and connecting

tubing were identified as not seismically qualified.

This tubing

connected into the seismically qualified portion of the system

upstream of the air compressor/receiver check valve.

The tubing was

evaluated and portions upgraded to meet the seismic criteria of the

plant piping standard 831.1.

The tubing which could not be fully

qualified was upgraded with supports to increase seismic capability

and permanent modifications were scheduled under EWR 89-762.

The inspector concluded that the EDSFA accomplished a sufficiently

rigorous review of EDS seismic applications.

Identified findings

were appropriately addressed.

6.

Exit Meeting

The inspection scope and results were summarized on August 20, 1993, with

those persons indicated in paragraph 1.

The inspectors described those

areas inspected.

Proprietary information is not contained in this

report. Dissenting comments were not received from the licensee .

13

7.

Acronyms and Abbreviations

A

- Amperes

ASDOP - Auxiliary System Design Optimization Program

CSA

- Channel Statistical Analysis

CNS

- Corporate Nuclear Safety

CUP

- Calculation Upgrade Program

DBD

- Design Basis Documents

DC

- Direct Current

EOG

- Emergency Diesel Generator

EDS

- Electrical Distribution System

EDSFA - Electrical Distribution System Functional Assessment

EDSFI

Electrical Distribution System Functional Inspection

EPRI

- Electrical Power Research Institute

EWR

- Engineering Work Request

GDC

- General Design Criteria

HVAC

- Heating Ventilation and Air Conditioning

kV

- Kilovolts

kW

- Kilowatts

MCC

- Motor Control Center

mg\\l

- milligrams per liter

SQUG

- Seismic Qualification Utility Group

SSTX

- Station Service Transformer

SWEC

- Stone and Webster Engineering Corporation

TS

- Technical Specification

UFSAR - Updated Final Safety Analysis Report

V

- Volts

VDC

- Volts Direct Current